Wambo Coal Pty Limited v Mine Subsidence Board
[2006] NSWLEC 528
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2006-08-24
Before
Lloyd J
Source
Original judgment source is linked above.
Judgment (16 paragraphs)
Introduction 1 HIS HONOUR: The applicant, Wambo Coal Pty Limited, seeks payment from the respondent, Mine Subsidence Board, of the sum of money in respect of expenditure incurred in anticipation of subsidence damage to its surface drift conveyor as a result of the workings conducted on the land underneath. This is the separate determination of the question as to whether there is an entitlement under s 12A(1)(b) of the Mine Subsidence Compensation Act 1961 (NSW) ("the MSC Act") to claim compensation for expense incurred in preventing or mitigating reasonably anticipated damage prior to any subsidence occurring or, alternatively, whether it is necessary for damage resulting from a subsidence to have occurred prior to any claimable expenditure being incurred. There was no suggestion that this Court does not have jurisdiction to determine this question.
Background facts 2 I do not understand that any material facts in the present case are in dispute. On 17 February 1992 the applicant obtained a development consent for works which included, inter alia, the erection of a surface drift conveyor. The conveyor, approximately 1.07 km in length, was then constructed in 1999 and commissioned for operation shortly thereafter. A third party, namely United Colliers Pty Limited, conducts underground coal mining in the locality. 3 In August 2003, a firm of consulting civil structural and maritime engineers, C W Henstock and Associates Pty Limited, prepared a report on potential subsidence impacts on the conveyor arising from the anticipated commencement of two underground workings directly underneath, Long Wall 3 and Long Wall 4. The engineers predicted a maximum ground subsidence in a transverse direction along each opening in the order of 1.3 metres. They also predicted that the conveyor would suffer strain, curvature and tilt with rotation which in turn would cause warping/deformation of welded support frames, torsional or bucking failure of tubular columns and shear failure of bolted sections. The engineers recommended consideration of four options to meet these predictions, one of which was to dismantle the conveyor before the underground mining operations occurred. 4 In November 2003, a firm of geological engineers, G E Holt & Associates, provided a further assessment of the potential subsidence associated with anticipated underground mining operations in Long Wall 3 and Long Wall 4. Their estimate was of a range between 1.65 and 1.92 metres. 5 Because of the concern over the potential subsidence causing inevitable damage to its conveyor, the applicant opted to dismantle it and re-use in some other location. The conveyor was removed in two stages between February 2004 and November 2004. It is common ground that that it was reasonable to anticipate some damage to portions of the conveyor arising from the predicted subsidence, if it were left in the state it was. 6 Mining operations by United Colliers Pty Limited in Long Wall 3 and Long Wall 4 began and the subsidence commenced to occur in the areas at the times agreed to by the experts engaged by the parties and which occurred reasonably approximated that which was estimated to occur. 7 On 19 February 2004, the applicant lodged a claim for compensation under s 12A of the MSC Act for expenses it incurred in dismantling and removing the conveyor. On 27 April 2005, the respondent refused the claim. On 14 June 2005 the applicant commenced the present proceedings in this Court pursuant to s 12B of the MSC Act.