14 MARCH 2005
WALTER CONSTRUCTION GROUP LTD v FAIR TRADING ADMINISTRATION CORPORATION
FAIR TRADING ADMINISTRATION CORPORATION v THE OWNERS, STRATA PLAN 43551
Judgment
1 SHELLER JA: Between December 1991 and December 1992 the appellant, Walter Construction Group Limited, (then known as Concrete Constructions Pty Ltd), (Walter), constructed a residential strata apartment block at 17-25 Spring Street, Bondi Junction. On 30 March 1993 the respondent, the owners, Strata Plan 43551, came into existence and represents the collective interests of the strata title owners of the building. The owners lodged a series of claims under the Building Services Corporation Comprehensive Insurance Scheme against the respondent, Fair Trading Administration Corporation, (FTAC) the administrator of that scheme. Two of those claims are relevant to these appeals, one dated 14 September 1998 and the other, 3 November 1998, both of which were declined by FTAC. The claims were based upon FTAC's liability to indemnify losses reasonably incurred by a beneficiary in respect of residential building work in rectifying defects in insured building work due to:
"(i) bad workmanship; or
(ii) faulty or unsuitable materials; or
(iii) failure to comply with plans and specifications; or
(iv) faulty design used by the contractors in a design and construct contract; or
(v) faulty design provided by the beneficiary when the design fault should have been obvious to a reasonably competent holder of an appropriate licence; or
(vi) failure to comply with the legislation or subordinate legislation applicable to the work."
2 However, the controlling cl 7(1) distinguished between major structural defects, as defined, and other defects commonly referred to as "general defects". In the case of major structural defects, the beneficiaries were required to notify FTAC or its predecessor within six months from first becoming aware of the defect but not later than seven years "from the commencement of insured building work". In the case of defects other than major structural defects, the beneficiaries were required to give such notification not later than three years from that commencement. There was a discretion to extend the time period if FTAC, or its predecessor, was satisfied that the delay in notification was due to circumstances outside the control of the beneficiary. FTAC resisted the claims on the basis that the claims were to indemnify for rectification of defects and not major structural defects.
3 On 12 February 1999, the owners lodged an appeal to the Commercial Tribunal of New South Wales, by then called the Fair Trading Tribunal and now known as the Consumer Trading and Tenancy Tribunal, under s85(d) of the Building Services Corporation Act 1989. In its decision of 5 November 2001, the senior member of the Tribunal observed that there was little dispute as to the nature of the defects the subject of the appeal. What was in dispute was whether the defects were major structural defects or general defects for the purposes of the scheme. The Tribunal upheld the owners appeal and found that FTAC was liable to indemnify the owners in respect of all losses relating to the defects subject to the claims. The Tribunal held that the defects were major structural defects.
4 FTAC's appeal to the Supreme Court of New South Wales under s61 of the Fair Trading Tribunal Act 1998, an appeal limited to questions of law, failed and was dismissed by Burchett AJ on 12 July 2002. It is to be observed that by that time probably at least seven years had passed since the claims were made. What occurred before this and during the hearing before the Tribunal makes doleful reading. I refer to the Tribunal's decision. After the decision of Burchett AJ on 24 October 2002, FTAC wrote to the owners to advise that "Approval has been granted to settle your claim for the amount of $852,598 under cl5(1)(d) of the Comprehensive Insurance Scheme." That sum was the difference between what had already been paid out and the maximum sum for which indemnity could be obtained. The letter continued:
"Settlement of the claim is subject to:
1. Completion of the works described on the written quotation.
2. Execution of the enclosed 'Authorisation of Payment' form.
3. The production of a final account from the rectifying contractor.
4. Verification by FTAC of satisfaction rectification/completion of the residential building work.
All settlement conditions must be complied with before any payment can be made by FTAC."
5 Separately on 5 July 2000, the owners had instituted proceedings against Walter in respect of the alleged defects. Walter's defence and cross-claim against sub-contractors raised the issue of whether the defects were excluded by cl 9 of the scheme, in short, faulty design. On learning of the FTAC letter to the owners, Walter communicated to FTAC that in its view FTAC would have no right to recovery against Walter in respect of amounts paid under the claim. Apparently as the result of a mediation conference in September 2003, FTAC stated it had become aware that the pleadings in those proceedings showed there was a contention of substance that the defects were of a character excluded by cl 9. Relying on this, FTAC sent a letter to the owners on 12 September 2003 purporting to revoke its earlier approval of the insurance claim.
6 On 24 September 2003, the owners instituted proceedings against FTAC seeking relief against the revocation of the approval of the claims. Walter commenced proceedings against FTAC seeking declaratory relief that FTAC had no right to institute recovery proceedings against Walter in respect of the claims because its approval of the claims was a nullity. Walter supported the right of FTAC to revoke the earlier decision in reliance on cl 9.
7 I have had the benefit of reading in draft the judgment prepared by Santow JA where there are set out the questions considered by Grove J in determining these claims. Grove J held that FTAC was not entitled to revoke the earlier decision to indemnify based as it was on the decision of Burchett AJ nor was the decision to approve a nullity which could not be revoked. Further, Grove J found that FTAC had engaged in misleading and deceptive conduct under the Fair Trading Act in its course of dealing with the owners.
8 FTAC and Walter now seek the leave of this Court to appeal against Grove J's decision. It is to be observed that FTAC has amongst its objectives to "promote and protect the interests of owners and purchasers of dwellings" and to provide a "centralised, simplified and logical one stop shop" and to "address complications that have existed in the past".
9 A prominent argument now put in support of this application is that assuming the defects for the rectification of which the owners now seek indemnity were due to faulty design of the sort described in cl 9, the FTAC had no power to make the offer contained in the letter of 24 October 2002 or alternatively, no "jurisdiction" to make the offer. This was an offer made following a decision of the Supreme Court upholding a decision of the Tribunal that FTAC was liable to indemnify the owners in respect of all losses relating to the defects the subject of the claim. There has now been yet another decision of the Supreme Court in which the trial Judge, Grove J, held that "the statutory construct, the scheme and the conduct of the FTAC combined so as to prevent re-opening of the earlier decision." Importantly there reference was made to the decision of Gummow J in The Minister v Kurtovic (1990) 92 ALR 93 at 112 where his Honour observed:
"The result is that when the decision maker attempts to resile from his earlier position he is prevented from doing so not from any doctrine of estoppel, but because his power to do so is spent and the proposed second decision would be ultra vires. The power is one of interpretation of the statute conferring the particular power."
10 The decision of Burchett AJ upholding the decision of the Tribunal was not challenged by FTAC. Further, FTAC acted upon it. The fact that FTAC apparently was persuaded by Walter to revoke its approval of 24 October 2002 adds nothing to its legitimacy and detracts in no way from its impropriety. In any event, as Santow JA has explained, it has no merit. Now after the deplorable delay brought about by FTAC's failure to accept a decision of the Tribunal and two decisions of the Supreme Court, it has what I can only describe as the effrontery to seek to rely upon cl 10 and the ten year limitation expressed in terms that it has no further liability under the scheme more than ten years after the commencement of the residential building work. If such were the law, which in my opinion, as the reasons of Santow JA demonstrate, it is not, it would open the scheme to be administered irresponsibly, lazily and, though obviously not in this case, corruptly.
11 I would refuse leave to appeal on both claims and order the claimants to pay the opponent's costs of these applications. As Santow JA has pointed out, the revocation and the reliance of the claimants upon it involved an abuse of process. I would afford the opponent an opportunity to apply for an order that its costs be paid on an indemnity basis, in the manner proposed by Santow JA.
12 SANTOW JA:
OVERVIEW
There is one central issue in these proceedings. In the events that happened, was the administrator of the New South Wales statutory building insurance scheme entitled under that legislation to revoke its approval of the strata title owners' claim against the builder for deficient work, or treat it as a nullity?
13 The statutory administrator, Fair Trading Administration Corporation ("FTAC"), in seeking leave to appeal claims that entitlement, contrary to the holding of the trial judge, Grove J. FTAC relies on the terms of the statutory scheme for insurance against deficient building work under Part 6 of the Building Services Corporation Act 1989 (subsequently re-named Home Building Act 1989 from 1996). It relies also upon the regulations under that Act defining the scope of the scheme, in particular Schedule 1 of the Building Services Corporation Regulation 1990. (I shall refer to these respectively as "the Act" and "the Regulation").
14 The builder Walter Construction Group Ltd ("Walter"), now in liquidation, supports FTAC in that application.
15 That application is opposed by the Owners' Corporation, called "the Owners-SP 43551". It represents the collective interest of the strata title owners of the building. I shall refer to that entity as "the Owners".
16 The challenge sought to be mounted turns on the nature of the approval given, and on its permissibility and status under the terms of the statutory scheme. FTAC variously contends:
(a) that any approval was provisional only, so revocable,
(b) that even if not a nullity it could be revoked before any losses were incurred by the Owners as beneficiaries of the statutory policy and was revoked,
(c) such approval was in any event a nullity as indemnity was only available under the statutory scheme for "major structural defects" this being a jurisdictional fact; any defects here were not of that character.
17 These contentions form the basis of challenge to the decision of the trial judge, Grove J, which was in favour of the Owners on these issues. Grove J also concluded in favour of the Owners on another basis, namely, the doctrine referred to as Anshun estoppel. It is more accurately described as a species of abuse of process. If applicable in the circumstances, it would preclude agitation by FTAC and Walter of matters which they had failed previously to raise; this is provided these matters now raised were so relevant to the original proceedings that it was unreasonable for FTAC to have failed to raise them.
18 Grove J accepted that FTAC had originally resisted payment on one basis only. That basis, one of time limitation, was decided against FTAC in separate proceedings both at first instance and on appeal. FTAC had unsuccessfully contended that the Owners' claim was for general defects, not major structural ones. Hence it was said that the claim was time barred as it fell outside the three-year statutory time limitation for general defects as against seven years for major structural ones. In successive proceedings before the Consumer Trader and Tenancy Tribunal ("CTTT" ) and then on FTAC's appeal to Burchett AJ in the Supreme Court from CTTT on a question of law, FTAC raised that defence only. At no stage did FTAC rely on the defences now sought to be raised. Hence Grove J concluded that Anshun estoppel defeated FTAC and Walter in any event. The present application for leave to appeal is now the fourth attempt at resistance by FTAC to the Owners' claim, having so far failed at each juncture.
19 The key factual events of the purported revocation were these. Following the Owners' success against FTAC before Burchett AJ, FTAC had written to the Owners on 24 October 2002 approving, subject to various matters, payment of the full amount available under the Comprehensive Insurance Scheme, taking into account payments that had already been made. Thereafter FTAC purported to revoke that approval in a letter dated 12 September 2003 to the Owners. This revocation was put on an entirely new basis. This was that the claim in reality was for design defects which were excluded from insurance coverage altogether under the relevant provisions of the Comprehensive Insurance Scheme. This was said to render any approval by FTAC outside its statutory power and thus a nullity.