28Generally, it is the Builder's submission that if it is not successful in its claim for variations because the variations do not comply with the contract then it is entitled to claim on a quantum meruit basis.
29The contract provides for variations and the way they are to be dealt. The Tribunal cannot accept that the builder can do what it likes beyond the terms of the contract and then expect to recover the cost of its actions on a quantum meruit claim. To do so, for these variations within the control of the Builder would defy the reason for the provisions in the contract for variations and the notion of a fixed price contract.
30The Home Owner's and the Builder's evidence in relation to each of the variations under dispute is as follows:
A Variation 24:
(1)The Builder claims that this variation was made because the windows were held in storage at the Home Owner's request for a longer period between manufacture and delivery and they needed to be re-revealed at a cost of $1722.89. They allege the delay was caused by the Home Owner's delay in clearing the site, in which the Tribunal makes a finding below.
(2)The Home Owners evidence is that he did not request the Builder to hold the windows in storage. He disputes being charged for such a variation when the windows were in any case held in storage.
(3)Clause 11 (f) of the Contract provides for compensation for delay. This issue is dealt with below.
(4)The Tribunal notes there is no writing signed by both the Builder and Home Owner for this variation.
(5)The amount claimed is not allowed to the Builder.
B Variation 28:
(1)The Builder claims an additional $484.80 being the additional cost of an amended hydraulic plan obtained as a consequence of variation 5 which was incorporated into the Contract. The additional amount is because the original charge was less than actual cost.
(2)The Home Owner claims that this variation should not be allowed because it is a claim for an additional cost that was covered on a fixed price quote.
(3)The Tribunal notes that there is no writing by both the Builder and Home Owner for this variation and it is a claim for an additional amount when a fixed price for the item had been agreed.
(4)The Tribunal does not allow the Builder this variation.
C Variation 29:
(1)The Builder claims an amount of $175.17 being the GST alleged to have not been charged on variation 15.
(2)The Home Owner claims that the amount paid under variation 15 includes GST.
(3)Variation 15 tendered with the Home Owners Bundle of documents is signed by both the Builder and Home Owner. The amount payable states that it is inclusive of GST.
(4)Variation 29 does not have a signature of the Home Owner on it.
(5)The Tribunal finds that variation 29 is not allowed as on the face of the evidence GST was included in variation 15 agreed to by the Builder and Home Owner at the time.
D Variation 30:
(1)The Builder claims an amount of $244.20 being a charge in addition to variation 24 because a crainage charge had not been made for handling windows.
(2)The Home Owner claims that it is a charge consequential on the Builder holding the windows in storage and was not agreed to or authorised by him.
(3)Clause 11 (f) of the Contract provides for compensation for delay. This issue is dealt with below.
(4)The Tribunal notes there is no writing signed by both the Builder and Home Owner for this variation.
(5)The Tribunal does not allow the variation to the Builder.
E Variation31:
(1)The Builder claims a charge for delay arising from the actions of the Home Owner claiming 7 weeks damages at $1,587.17 per week. The Builder relies on Schedule 2 page 7 of the Contract.
(2)The Contract provides for an amount to be paid by the Home Owner of $1,587.17 per week if clause 11(f) is breached.
(3)Clause 11(a) provides:
Should the progress of the works be delayed by any of the following matters, conditions or consequences resulting from: ....
(v) any act, default, delay or omission on the part of the Owner in providing instructions, making payment or doing a thing necessary to allow the works to proceed (including signing instructions concerning variations)
...then in any such case the Builder must receive a fair and reasonable extension of time of the Construction Period.
(4)Clause 11 (f) provides
If the delay results from any of the matters listed in paragraphs (ii), (iii), (iv), (v), (vi) or (xi)of clause 11 (a), then the Contract price is to be adjusted to include an amount calculated to cover the cost or expense of the delay incurred by the Builder. Variation delays are adjusted pursuant to Clause 14.
The amount payable will be determined with reference to Item 3 (b) of Schedule 2. In addition to any actual costs incurred by or payable by the Builder because of the delay which in total exceed the amount payable with reference to the period of delay and the amount stated at Item 3 (b) of Schedule 2, to the extent of the difference, will also be payable by the Owner.
(5)The Home Owner is responsible for removal of any burden or spoil and to remove rock from the site pursuant to Clause 7 of the Schedule 4.
(6)The evidence adduced by the Builder tendered through its former building supervisor of delay is a Job sheet for the works showing delay "By Owner" from 15 August 2012 until 3 October 2012 with the cause noted as "placing rock at rear of block in way of drainage"
(7)The evidence of the plumber and drainer is that when he went to the building site to install an absorption pit and external drainage he could not do so because rock and spoil had not been removed. As a result work on the site was delayed.
(8)The Builder's evidence is that the delay in the removal of the rock and spoil caused the works to be delayed.
(9)On the Builder's evidence before it, the Tribunal is satisfied that the Home Owner did not fulfil his obligations to remove the rock and spoil. The installation of drainage within the proposed slab area and beyond that area and the associated absorption pit needed to be carried out before the concrete for the slab to be poured. Until the footing or foundation in the nature of the slab was completed the substantive building works could not proceed and was a fundamental cause of the overall building works being delayed.
(10)The effect of Clause 11 is twofold. It permits the time for completion of the Contract to be extended by the term of the delay caused by the Home Owner and also entitles the Builder to compensation.
(11)The Home Owner denies that the rock and spoil he was responsible for resulted in the works being delayed. He also submits that the other works proceeded and the Contract works were completed well within the time allowed under the Contract and therefore the Builder suffered no loss and is not entitled the damages for delay. The Home Owner's evidence is that a variation to the Contract in relation to piering was agreed to on 20 August 2012. The Home Contends that variation allows a conclusion to be drawn that the building works were not delayed.
(12)The Tribunal prefers the evidence of the Builder on this issue and when that evidence is considered together he has satisfied the civil standard of proof that the failure by the Home Owner to remove the spoil caused delay to the works.
(13)The Tribunal is satisfied that the Builder has established that the Home Owner by failing to remove the rock and spoil out of the way or completely form the site caused the delay.
(14)Clause 11(f) contemplates on the happening of an event referred to in Clause 11 (a) (v) that the "The Contract price is to be adjusted to include an amount calculated to cover the cost or expense of the delay incurred by the Builder... the amount will be determined with reference to Item 3 (b) of Schedule 2."
(15)The Tribunal is further satisfied that the amount claimed by the Builder under variation 31 is a proper charge to make and is made in accordance with Clause 11 of the Contract. The Tribunal allows the Builder the amount claimed of $11,110.19.
F Variation 32:
(1)The Builder has claimed an additional amount of $225.15 for the additional cost of perimeter fencing alleged to have been caused by the delay of the Home Owner.
(2)The Home Owner submits that for the claim the Builder relies on an invoice that is for fence hire from 30 May 2012 to 20 November 2012. The Contract was entered into on 16 July2012. Works commenced on 14 August 2012.
(3)The allowance in variation 31 covers costs incurred as a result of the delay. Clause 11 (f) "...In addition any actual costs incurred by or payable by the Builder because of the delay which in total exceed the amount payable with reference to the period of the delay and the amount stated in Item 3 (b) of the Schedule 2, to the extent of the difference, will also be payable by the Owner." That is, the Builder is not entitled to actual costs over and above the amount in Item 3 (b) until they exceed that amount.
(4)Further, the Tribunal notes there is no writing signed by both the Builder and Home Owner for this variation.
(5)The Tribunal does not allow the Builder the variation.
G Variation 33:
(1)For the same reasons as those given for variation 32 the amount claimed for additional toilet hire is not allowed to the Builder.
31To summarise the amounts allowed to the Builder for variations the table is now reproduced with those amounts identified and set out.
Variation Number Amount Claimed($) Amount allowed by Tribunal ($)
24 1,722.89 0
28 484.80 0
29 175.17 0
30 244.20 0
31 11,110.19 11,110.19
32 225.15 0
33 195.79 0
Total 14,158.19 11,110.19