50 Clause 8 of the Contract provided exclusive possession of "the site" to the Builder for the performance of work. The "site address" was the same address as "the property", but it is clear that "the site" was not intended to be the whole of "the property" by reason of the provision that possession of the site included "access to other parts of the property" necessary to enable the builder to carry out work: clause 8(a)(i). But when it came to payment of the Builder, the Owner could be prevented from "entry" to the "property", not merely the "site", until the Builder was paid. The costs incurred by the Builder to secure "the property" to prevent entry were to be paid by the Owner. The Builder's contractual right for non-payment was to exclude the Owner from the "property", thereby preventing the Owner from taking possession of or receiving the keys to "the works" until he was paid: cl 23(e). This sub-clause, together with the reference to the provision of a key in clause 23(d), provides support for the conclusion that the expression, "the works", in clause 23(d) referred to the buildings, as constructed or partially constructed, rather than the work, or building services, including the provision of the Certificate, provided by the Builder.
51 Although the expressions "work" and "works" are used in different contexts throughout the Contract, the only sensible and businesslike interpretation of the word "works" in clause 23 (d) is that it means the completed buildings, the townhouses, and does not include pieces of paper, including certificates and insurance policies that may be held by the Builder either at the site or off-site. The inducement for prompt payment of the Builder was the contractual right of the Builder to lock the Owner out of the "property" on which the "works" were erected or constructed.
52 The Builder's submission that the provision of the Certificate to the Owner was equivalent to the Owner taking possession of the "works" because it enabled the Owner to submit the Certificate to the Council to obtain the registration of the sub-division and complete the sale of one of the townhouses does not accommodate any discretion in the Council to refuse to register the sub-division plan for reasons that may not have anything to do with the Certificate. In any event that submission is inconsistent with the plain words of the Contract. The provision of the Certificate to the Owner may have fallen within what was described as the "work" the builder was required to do, however it is not part of "the works" as that expression is used in clause 23 (d).
53 The trial judge fell into error in finding that the "certificate being part of, as well as being the embodiment of part of, the works, its use would constitute taking of possession within the meaning" of clause 23(d) of the Contract with the consequential affirmative answer to the separate question.
Proposed Orders
54 The orders I propose are as follows: