JUDGMENT
1 BELL J: This is an appeal from the decision of Harrison AsJ made on 18 July 2007 declining to order the plaintiff, U.S. Manufacturing Co Pty Ltd (USM) to provide security for costs.
2 USM is a company which at material times was trading in lubricants, welding rods, gearboxes and other specialised equipment. It brought proceedings in the Local Court at Parramatta against ABB Service Pty Ltd (ABB) claiming payment for goods sold and delivered in the sum of $23,593.80 and interest. The goods were particularised in USM's amended statement of liquidated claim as six new custom made gearboxes and two reconditioned gearboxes, which were delivered to ABB on 17 January 2003.
3 The matter was referred for arbitration. USM sought a re-hearing before the Local Court following the arbitration. The hearing proceeded before Magistrate Johnson on 22 April, 30 June, 1 July and 7 September 2005. His Honour reserved his decision and on 17 October 2005 gave judgment for ABB.
4 On 9 November 2005 USM commenced proceedings by summons in this Court appealing against the Magistrate's judgment as being erroneous in point of law.
5 On 20 December 2006 ABB filed a notice of motion claiming orders that USM provide security for its future costs of the proceedings in the sum of $50,000.00 within seven days and that the proceedings be stayed until such time as the security is given.
6 The evidence before Harrison AsJ on the hearing of the motion comprised the affidavit of Francis Reginald Lawson, the solicitor acting for ABB and, in USM's case, the affidavit of Eddy Dogramaci who had been one of its two directors at the time of these events and who was responsible for the delivery of a number of gearboxes to ABB.
7 Before turning to the grounds of challenge it is convenient to refer to the history of the proceedings and to the Magistrate's reasons for decision.
8 There was a substantial factual issue before the Magistrate concerning delivery of the gearboxes, the subject of the claim. It was common ground that ABB, a service company employed by Sydney Water at its Winmalee Sewerage Treatment plant, contracted with USM for the supply of a number of gearboxes and that a number of gearboxes were delivered by Eddy Dogramaci on behalf of USM to ABB at the Winmalee site in December 2003. It was also common ground that a number of gearboxes were delivered by Eddy Dogramaci to ABB at the Winmalee site in January 2003 and that this delivery included two reconditioned gearboxes which were supplied without charge. It was USM's case that eight gearboxes were delivered in December 2002 and that a further six gearboxes and the two reconditioned gearboxes were delivered in January 2003. USM pleaded that the two reconditioned gearboxes were delivered without charge on the condition that within one day of delivery ABB would furnish USM with an order number for the accompanying six gearboxes and certain other equipment. It was ABB's case that it had placed an order for a total of eight new gearboxes with USM and that only four had been delivered in December and that the balance of the order was delivered in January together with the two reconditioned gearboxes which were gifts designed to encourage it to place further orders with USM.
9 Relevant to the Magistrate's reasons for decision was the evidence that there were four treatment tanks at the Winmalee site and that each tank had two reduction gearboxes which drove the machinery. In all, the plant employed eight active reduction gearboxes and maintained two new gear boxes at the site as "critical spares". In November 2002 Sydney Water had decided to replace the eight reduction gearboxes that were in use but not the two unused critical spares.
10 The Magistrate found that USM had not proved the delivery of the six new gearboxes, which were the subject of the claim. Mr Dogramaci conceded in evidence that the two reconditioned gearboxes were delivered as an unconditional gift in the hope of attracting more business (J at [32(b)].
11 The Magistrate took into account the following matters in concluding that USM had not established its case:
(i) Mr Dogramaci's evidence was, "not without problems" (J [32(b)]). His account was contradictory, including with respect to the basis on which the two reconditioned gearboxes had been delivered to ABB;
(ii) USM tendered a delivery docket dated 3 December 2002, which included the words "8 units" on it. A carbon copy of the docket tendered in ABB's case did not contain these words. Mr Dogramaci asserted that he had written the words "8 units" on the docket before handing it to Mr Heydon, who received the gearboxes on behalf of ABB. Subsequently in oral evidence he said that he had written the words "8 units" on the docket at a later time (J at [14]);
(iii) There was no reason for ABB to order a further eight gearboxes (assuming eight gearboxes to have been delivered in December) unless those earlier delivered had been stolen or lost. There was no evidence that any gearboxes had been stolen or were missing from the ABB site. Regular stock takes had been carried out and nothing in ABB's documents, or documents maintained by Sydney Water, indicated that equipment was missing;
(iv) No order number was issued for the supply of gearboxes by USM in January 2003 and USM had not shown any instance in which goods had been supplied without an order number having been provided;
(iv) ABB paid for eight gearboxes on 24 December 2002. This was relied upon as establishing that ABB had received eight gearboxes before that date. His Honour considered there were other possible explanations which were consistent with acceptance of ABB's evidence that only four of the eight gearboxes had been delivered by the end of December. These included that payment for the full order may have been made on partial delivery because of the history of dealings between the parties or that the accounts department may have prematurely authorised payment;
(v) The evidence of the witnesses called in ABB's case was generally credible.
12 On 22 March 2006 USM filed a notice of motion seeking to adduce new evidence on the hearing of its appeal. The application related to the evidence of Mr O'Brien, that eight new gearboxes were delivered and installed at the ABB site before the end of December 2002. On 26 April 2006 Brett Heydon, who was employed by ABB at the time of these events and who had given evidence before the Local Court, affirmed an affidavit asserting that he did not recall Mr O'Brien being present when the gearboxes were delivered in December 2002. On 3 July 2006 Malpass AsJ dismissed USM's application to adduce the evidence of Mr O'Brien on the hearing of the appeal.
13 On 3 August 2006 USM brought a further motion to adduce new evidence. This motion is yet to be determined and relates to the evidence of Brett Heydon. In an affidavit sworn on 8 August 2006 Mr Heydon contradicts the evidence that he gave before the Local Court and states that eight gearboxes were delivered to the ABB site before the end of 2002. He says that he signed his earlier affidavits without reading them.
14 USM was required to provide $20,000.00 by way of security for costs in the Local Court. The Magistrate made an order that USM pay ABB's costs of the proceedings. These were assessed in the sum of $56,908.69. ABB registered the cost assessors' determination in the registry of the Local Court and this took effect as a judgment in the sum of $36,908.69 ($20,000.00 which had been paid into court pursuant to the order for security having been received by ABB).
15 On 15 September 2006 ABB served a statutory demand for payment in the amount of the judgment debt on USM. USM did not satisfy the statutory demand and on 11 October 2006 ABB commenced proceedings seeking an order for the winding up of USM.