Tryhaz v FielderFielder v Tryhaz
[2005] NSWSC 906
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2005-09-09
Before
Mr P, Macready J
Source
Original judgment source is linked above.
Judgment (14 paragraphs)
Background facts and history of the proceedings 3 These are not in issue and I will adopt with some modification the non-contentious matters set out in the helpful submissions of the parties. 4 Multiplex Constructions Pty Ltd ("Multiplex") was the design and construct contractor engaged for the marine works, including the wash barrier. Multiplex subcontracted the detailed design and construction of the marine section of the King Street Wharf works, which included the wash barrier, to the First Defendant/Cross Claimant, Tryhaz Pty Ltd ("Tryhaz"). 5 The sub-contract included specifications that required the design and construction of the wash barrier to certain performance requirements, including the requirement for the wash wall to withstand an ultimate wash force of 80 tonne wash force, assumed as originating 15 metres from the barrier and dispersing at a 10º angle. 6 Tryhaz engaged the plaintiff, Fielder Engineers Pty Ltd ("Fielder"), to provide engineering and project management services in connection with the marine works, including the wash barrier design. The wash barrier deteriorated after completion and there is a need for its reconstruction. 7 Fielder commenced the proceedings in 2001 against Tryhaz and its principal director, Mr Mark Steele to recover unpaid fees due as a result of "design savings" and claiming damages arising out of representations made to Fielder in connection with Fielder's retainer. 8 Tryhaz then brought a cross claim against Fielder arising out of the collapse of the wash barrier. It claimed damages for breaches of contract, alleging deficiencies in design and project management on Fielder's part. That cross claim included a claim for an indemnity in respect of Tryhaz's liability to Multiplex. 9 Multiplex claims damages by way of cross claim both against Tryhaz and against Fielder arising out of the defects in the wash barrier. The basis of the Multiplex claim is a matter of some dispute before me. The Referee's principal findings 10 The Referee found that there should be verdict for Fielder against Tryhaz for the design savings fee of $216,863 plus interest from October 2000 and a verdict for Mr Steele on the claim by Fielder against him. This finding is not challenged by Tryhaz; 11 The Referee found that Multiplex was entitled to recover the cost of reconstructing the wash wall so that it confirms to the sub-contract by way of a sheet pile solution, being the amount of $1,507,380 plus GST, less agreed retention of $168,137, 60% against Fielder and 40% as against Tryhaz. 12 Fielder and Tryhaz challenge the Referee's finding that Multiplex is entitled to GST on the rectification costs and the quantum of the rectification costs which it submits should not include painting but should include the costs of providing cathodic protection. On the evidence before the Referee, this had the effect of reducing quantum by $121,000. 13 Fielder and Tryhaz do not otherwise challenge the liability findings made by the Referee or the apportionment determined by the Referee; 14 The Referee also found that Multiplex should be entitled to interest on the rectification costs, but not before the end of 2002 on the grounds that Multiplex did not agitate the collapsed wall before that time. In the hearing before me Multiplex did not seek to receive any interest pre judgment on the basis that it has not yet carried out the rectification works and that damages were based on May 2005 costings. This matter can be put to one side and the Referee's report will not be adopted in this respect. Principles of law on the adoption of the Referee's report 15 As a result of the provisions of Paragraph 10 of Schedule 6 of the Civil Procedure Act 2005 the provisions of Part 72 of the Supreme Court Rules still apply to the consideration of the report. In any event there is no substantial difference between that Part and Part 20 of the Uniform Civil Procedure Rules so far as it affects these proceedings. 16 The most recent summary of the well developed relevant principles was by McDougal J in Seven Sydney Pty Ltd v Fuji Zerox Australia Pty Ltd [2004] NSWSC 902 in these terms: "11 The principles to be applied, in exercising the discretion conferred upon the Court by Pt 72 r 13 to adopt, vary or reject in whole or in part a report of a referee, are well established. There are a number of cases to which, customarily, reference is made. They include Super Pty Ltd v SJP Formwork (Aust) Pty Ltd (1992) 29 NSWLR 549; the unreported proceedings in that case before Giles J (19 May 1992: the relevant considerations referred to by his Honour are sufficiently extracted in the decision of the Court of Appeal); Chloride Batteries Australia Ltd v Glendale Chemical Products Pty Ltd (1988) 17 NSWLR 60; White Constructions (NT) Pty Ltd v Commonwealth of Australia (1990) 7 BCL 193; and Foxman Holdings Pty Ltd v NMBE Pty Ltd (1995) 38 NSWLR 615. As to the nature and content of the referee's obligation to give reasons, the relevant authorities include Xuereb v Viola (1988) 18 NSWLR 453 and Hughes Bros Pty Ltd v Minister for Public Works (Rolfe J, 17 August 1994, unreported; BC 9402885).