It will be seen that the parties were left at large to prove commission of the torts referred to, so long as the specified pleadings and particulars were adhered to.
14 Counsel for the Comerford parties, in his opening address to the referees on 14 July 1999, said (Grey 54V-55Q):
"The Comerfords, in either negligence or public nuisance, need to establish an act of misfeasance by the RTA as a highway authority. As you probably are both well aware, it is not good enough for this bridge to have fallen into disrepair and that condition to have materially contributed to the collapse as found by Referee Verge. Something must have been done by the RTA to have caused or materially contributed to the state of affairs that led to the collapse, as found by you, Mr Referee Verge.
To establish public nuisance the RTA needs to establish all that it is required to establish to get up on its negligence claim. So we will concentrate on the negligence cause of action.
We do not pursue the breach of statutory duty cause of action so that you will be invited to find the RTA liable, at the suit of the Comerfords, by reason of the RTA's negligence, by reason of an act of misfeasance. Now, what was that act?
It will be the Comerfords' contention, or it is the Comerfords' contention, that repairs effected to the bridge materially exacerbated problems within the bridge, particularly materially exacerbated problems of [in plane] compression forces in the concrete deck slab [in plane], which deck slab Referee Verge found, by reason of those [in plane] compression forces, to have acted in a particular way and to have led to the collapse of the bridge.
The burden of the Comerfords' position is that the repairs to cracks in the bridge, and the placement of product in the expansion joints of the bridge, exacerbated the [in plane] compression forces and materially contributed to the collapse by the so-called toggle buckle.
It is, if you like, in that positive way, by those positive acts, rather than mere omissions that the Comerfords will seek to establish the act of misfeasance in the Roads and Traffic Authority."
15 The Comerfords were thus relying on two acts of misfeasance. The first was that the RTA, in carrying out routine repairs, had injected a rigid epoxy as opposed to a flexible epoxy in certain cracks which had opened up over the years in the piers of the bridge. The second act of misfeasance was carrying out work to certain rotation joints in the bridge. There were gaps in the bridge which over the years had closed because of movements back and forth. Both gaps - the rotation joints - had cover plates over them and the traffic passing over the cover plates had caused them to pop up and down. That led to spalling of the concrete below. The RTA, as part of its regular maintenance, removed the cover plates and refilled them, using only epoxy material, and replaced the cover plates.
16 Counsel for Mr Welling did not disagree with the issues as propounded by counsel for the Comerford parties. The issues as presented in opening did not change during the hearing of the reference. The referees summarised them as being (Grey 47K-L):
"(a) injection of Megapoxy into cracks (in the piers); and
(b) inserting Set 45 into the gaps in the deck over piers 6 and 8."
17 On 30 September 1999 the referees reported that the RTA was not liable to the Comerford parties and Mr Welling.
18 On 10 December 1999 the primary judge heard argument in which the RTA contended that the second report should be adopted and the other parties contended that it should not. He reserved judgment, and made reference to two applications for special leave being heard that day in which the High Court was being asked to reconsider the law on non-feasance in relation to highway authorities. In fact the High Court referred both applications to a full bench to be argued as on an appeal.
19 The primary judge then re-listed the matter on 11 February 2000 and invited further submissions from the parties, which were heard on 8 March 2000. The topic which the primary judge raised with the parties was whether there was a negligence issue not addressed in the second report which ought to be considered.
20 On 15 March 2000 the primary judge made the orders against which this appeal is brought, and in a reserved judgment stated his reasons for that course. After setting out the background, he referred to the two acts of negligence relied on against the RTA. He said (Red 21 line 11-23 line 40):
"In relation to the first alleged act of negligence, the referees noted the following:
'The experts agree and we concur that cracks in the piers would reduce their stiffness and increase their flexibility thus more readily accommodating the movements. [The Authority's engineer] proposed that the cracks should be sealed with a flexible epoxy to maintain the status quo; in the event the pier cracks were sealed with a rigid epoxy.
If the cracks were sealed with a flexible material this would permit the cracks to move so that the flexibility of the cracked piers would not alter in any significant way.
… we are of the view that sealing the pier cracks with rigid epoxy probably had only a marginal and temporary effect on the behaviour of the bridge. The fundamental defects in the original design and construction of the bridge led to the excessive compression of the bridge deck and its ultimate failure. Any change to the flexural rigidity of the piers arising from sealing the cracks was not significant compared with the movement of the Wellington end abutment, the closing of the gaps and temperature expansion of the deck.'
Dealing with the second alleged act of negligence, the referees concluded that both the rotation joints and the expansion joint had ceased to operate as a result of them being 'practically closed'. The Authority's repair work was described by the referees as follows:
'Apparently the steel cover plates to the rotation joints had worked loose under the traffic and the edge of the concrete had broken away to form an irregular space at the top of the concrete slab. The joints were repaired by the following procedure:
remove the steel cover plates;
insert a temporary timber spacer at the top of the joint and against the steel protection angle at the end of the steel span;
provide a temporary filler to close the bottom of the gap between the slabs;
fill the space with Set 45 a rapid setting mortar;
remove the timber spacer and insert a compressible seal in the space at the top of the joint; and
replace the steel cover plate and fix to the steel span with chemical anchors.
Clearly this work was intended to cure problems arising from the loose cover plates, the spalling of concrete at the edge of the concrete approach spans and the ingress of deleterious matter into the joints. It did not attempt to address the long-term problems in the design and construction of the bridge.'
The referees reached the following conclusion:
'Considering all the evidence regarding the repair of the rotation joints, we are not able to determine the precise effect of this work on the likely behaviour of the joint if it were subject to in-plane compressive forces. However, on the balance of probabilities we consider that this repair work is unlikely to have appreciably altered the performance of the bridge deck compared with its condition prior to the work.'
As a result of the way in which the second reference was conducted, the referees did not address any responsibility of the Authority in performing repair work on expansion and rotation joints which was ineffective in restoring the function for which those joints were designed and which aided serviceability of the bridge deck for traffic. The significance of that omission, in my view, is reflected in the following opinion of the referees in the second report:
'The expert evidence of Dr Ivering and Mr Kell is conflicting in part on the issue of foreseeability. Dr Ivering's opinion is that a structural analysis as suggested by Mr Kell if carried out prior to 1988, was not warranted and in any event would not have predicted a buckling failure. And further that no reasonably competent bridge engineer could have foreseen that the bridge would suffer the catastrophic collapse as found in the previous reference.
Mr Kell's opinion is that an investigation should have been undertaken to assess the condition of the abutments and the probable compressive force induced in the deck. And that if this disclosed a force in excess of any value for which the bridge may have been designed, the unrestrained deck slabs should have been examined to check their susceptibility to buckling failure.
This apparently prudent approach advocated by Mr Kell may have been coloured by hindsight. Nevertheless we concur with his view that similar buckling failures have occurred in slabs on ground and that the construction of the Wellington bridge deck is unusual in that the concrete slabs are not restrained by the supporting steel beams. We do not accept the inference from Dr Ivering's comment that because there was no visible distortion of the concrete slabs, a structural analysis was not warranted. Unfortunately a buckling type failure is especially dangerous : (a) it may be difficult to predict and (b) if it occurs it does so often without any warning.
An engineering investigation of the bridge structure if carried out in 1988, probably would have disclosed a large compressive force in the deck and the vulnerability of the unrestrained concrete slabs to a buckling or pop-up failure . Although a structural analysis of the slabs probably would not have been conclusive it should have raised the possible risk of a deck failure. If a deck slab were to pop up this would pose some danger to a vehicle traversing the bridge at that time. But it would require a highly imaginative and risk averse engineer to predict the possibility of a catastrophic collapse such as occurred.'
[emphasis added]
In my view, those opinions of the referees call for consideration of a negligence issue which was not addressed in the second report. I raised these concerns with the parties by re-listing the matter on 11 February 2000 and invited further submissions from the parties which were head on 8 March 2000. In light of those submissions I have decided that, in determining whether the second report should be adopted, varied or rejected, Comerford and Welling should be afforded the opportunity of having a wider issue of negligence considered than that addressed by the referees. The wider issue of negligence is of the kind examined in Hill v The Commissioner for Main Roads (1989) Aust. Torts Reports ¶80-260; (1989) 68 LGRA 173; and McDonogh v The Commonwealth (1985) 73 ALR 148; (1985) 9 FCR 360."
21 Whatever the third issue was which was raised by the primary judge, it was one which he raised of his own motion, though he gave the parties full opportunity to debate whether it should be considered. This Court was informed that the same arguments which the appellant propounded to this Court were put to him.