© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2020] NSWLEC 112
Land and Environment Court (NSW)
2020-09-23
Moore J
Original judgment source is linked above.
Introduction
The terms of the remaining Summonses
Introduction
The POEO Act
The Sentencing Procedure Act
The Fines Act
The maximum penalty
The sentencing hearing
The evidence
The Statements of Agreed Facts
Configuration of the Marina before demolition 33 Prior to the demolition of the pontoons at the Marina, the Marina comprised: (i) a main walkway 2.7 m wide and 67 m long (Main Walkway); (ii) a northern arm (Northern Arm), 2.1 m wide and approximately 102 m long, perpendicular to the Main Walkway; (iii) a southern arm (Southern Arm), 2.1 m wide and approximately 106 m long, perpendicular to the Main Walkway; and (iv) 'finger pontoons', 1.2 m wide and each between 7.1 and 10.9 m long, perpendicular to both sides of the Northern Arm and Southern Arm. 34 The configuration of the Marina can be seen from the plan of the Marina prior to the demolition of the pontoons commencing at page 82 of the Bundle [of Agreed Documents on Liability]. 35 The WUC involved the demolition of pontoons, pontoon walkways, pontoon fingers and pontoon gangways at the Marina, such waste including, without limitation, plastic flotation chambers, metal frames, wooden planks, carpet lengths, metal fixtures, and wiring derived from the demolition (Waste Materials). Commencement, carrying out, and completion of WUC 36 ECWC commenced the WUC in November 2015. ECWC had primarily completed the WUC by 24 December 2015. 37 In performance of the WUC, ECWC stripped down various Waste Materials at the Marina into their component parts. Photographs and videos taken during the demolition depict ECWC's activities, including Mr King and/or others acting on behalf of ECWC: a. walking on the pontoons; b. approaching the pontoons and demolished pontoons by boat; c. using a crane to remove demolished pontoon segments; d. moving floating demolished pontoon sections by boat; and e. loading demolished pontoon segments, including floatation chambers, onto a boat and onto a barge by crane. Removal of the Waste Materials from the Marina 38 Following demolition of the structural components of the Marina, some of the demolished pontoons were stored at the Marina in an area described by Mr King as 'the duck pond'. In a recorded interview with RMS on 22 March 2017 (the ROI), Mr King stated that: (a) ECWC commenced stripping down the demolished pontoon segments and disposing of their component parts from that location; (b) initially, portions of the stripped down metal frames were taken to a scrap metal yard, however, Mr King felt that stripping down the pontoons at the Marina and disposing of the Waste Material in this way "turned out to be just a headache" and was "too much of a cluster to keep pulling it all apart, and too slow"; (c) after this, the sections of demolished pontoon were either: (i) cut up and taken directly to the tip from Berowra; (ii) cut up and stored for around 12 months in a yard in Windsor before being taken to the tip and disposed of as general waste; (iii) given away; or (iv) transported by water to the Mooring; (d) in so far as (c)(iv) is concerned, "a whole bunch" of the smaller pontoon segments were tied together and towed by ECWC from the Marina to the Mooring; and (e) ECWC tied the Waste Materials together for their transportation by water from the Marina to the Mooring. 39 Aerial images obtained by RMS from the Office of Environment and Heritage depict the Dumb Barge attached to the Mooring on 6 December 2015 with no pontoon material attached around the Dumb Barge. Those aerial images are produced in the Bundle commencing at page 81. 40 In December 2015, an RMS officer sighted the Dumb Barge and a number of demolished pontoons and other items of building waste attached to the Mooring. 41 On 6 February 2016, an RMS officer inspected the Mooring and observed a Dumb Barge attached to the Mooring with numerous sections of pontoons, in poor condition, tied to it, together with rubbish including PVC pipe, planks, marine carpet and general debris. Photographs were taken during this inspection. 42 Aerial images obtained by RMS from the Office of Environment and Heritage depict the Dumb Barge at the Mooring with pontoon segments stored at the side of the Dumb Barge on 13 February 2016. Those aerial images are produced in the Bundle commencing at page 83. 43 On 16 February 2016, an RMS officer inspected the Mooring and observed a Dumb Barge attached to the Mooring with numerous sections of pontoons, in poor condition, tied to it. The pontoons were constructed of large black plastic buoyancy chambers with a combination of steel framework and timber decking. Photographs taken by the RMS officer on that date are produced in the Bundle commencing at page 85. 44 On 23 February 2016, an RMS Officer inspected the Mooring. Some decking and rubbish had been removed but a considerable amount of Waste Material remained on the barge. 45 In the ROI, Mr King stated: (a) The materials were ratchet-strapped together and attached to the Dumb Barge. (b) While the materials were being stored at the Mooring, Mr King observed people inspecting and showing interest in the pontoon segments that were stored at his Mooring and on three or four occasions found that pontoon segments were being taken away from the Mooring. (c) On multiple occasions, Mr King found that materials (including pontoons sections up to 9m in length) had been moved from the Mooring to various locations around Pittwater including the beach at Lovett Bay and Careel Bay (see map at page 100 of the Bundle). (d) On these occasions, Mr King rounded up the materials that he found and strapped them all together again at the Mooring. The First Clean Up Notice issued to ECWC on 24 February 2016 46 On 24 February 2016, RMS issued a Clean Up Notice to ECWC pursuant to s 91 of the Protection of the Environment Operations Act 1997 (First Clean Up Notice). A copy of the First Clean Up Notice commences on page 94 of the Bundle. 47 The First Clean Up Notice directed "Mr Benjamin Peter KING of East Coast Wharf Constructions Pty. Ltd", amongst other things, to remove, within seven days of 9am, Friday 26 February 2016: "...the unsecured materials and pontoon type sections attached to commercial mooring CL8027 from the navigable waters of NSW, by means of land disposal at Cargo Wharf, Church Point, Pittwater, to an appropriate land based refused disposal site. The materials must not be moved to another location on navigable waters of NSW." Inspection of demolished materials stored at the Mooring on 7 March 2016 48 On 7 March 2016, an RMS officer observed that the materials the subject of the First Clean Up Notice continued to be attached to the Mooring. Photographs taken by the RMS officer on that date are produced in the Bundle commencing at page 98. The Second Clean Up Notice 49 RMS issued a further Clean Up Notice to ECWC on 15 March 2016 (Second Clean Up Notice). A copy of the Second Clean Up Notice commences at page 105 of the Bundle. 50 The Second Clean Up Notice stated that "In view of the pollution hazard that is likely to occur as a result of the pontoons remaining in their current state in navigable waters", Mr King and ECWC were directed within seven days of 9am, Friday 18 March 2016, to "remove the dilapidated pontoon type sections attached to commercial mooring CL8027" and to comply with the other directions in the First Clean Up Notice. Removal of Waste Materials 51 In his record of interview, Mr King stated: (a) ECWC pulled lengths of pontoons out of the water, stripped them back and cut them up into smaller pieces at the Mooring. (b) Waste Materials were then taken to Church Point Cargo Wharf where they were taken out of the water with a crane and placed onto a truck. (c) A portion of the Waste Materials were disposed of by ECWC at landfill tips, taken to metal recyclers and also placed into storage. 52 On 23 March 2016, Mr King wrote to RMS on behalf of ECWC and stated that "I wish to advise that all action, requirements and clean up has been removed and taken to the tip" [sic]. A copy of that letter commences at page 107 of the Bundle. 53 At the end of March, an RMS officer observed that there were no more waste materials derived from the Marina at the Mooring. RMS' salvage of sunken pontoons 54 On 27 September 2016, RMS salvaged three pontoon segments from the seabed of Pittwater (the Pontoon Segments). 55 The Pontoon Segments were retrieved from the seabed of Pittwater at a location with the latitude and longitude co-ordinates of 33° 38.11932'S and 151° 17.19396'E. 56 The distance between the location of the Mooring and the salvage location has been been calculated by the Prosecutor's geospatial analyst, Amanda Kildea, as approximately 282.88m. 57 The three Pontoon Segments formed part of the Berowra Waters Marina, prior to the works being undertaken by ECWC. 58 The Pontoon Segments consist of a galvanised metal frame lined with treated pine plank floorboards, surmounting black plastic flotation boxes 1.0 m x 0.9 m wide, and 0.72 m deep, with 28 flotation boxes in total. A roll of marine carpet was found tied to the third Pontoon Segment. 59 Photographs taken by an RMS officer at the time of the retrieval of the Pontoon Segments commence at page 116 of the Bundle [of Agreed Documents on Liability]. 60 The deposition of the Pontoon Segments and connected materials into the marine environment of Pittwater resulted in an alteration to that environment by: (i) direct means (smothering of the sea floor and the provision of hard structures where there were none beforehand); and (ii) indirect means (altering the hydrodynamic environment surrounding the pontoons as they lay on the bottom). 61 The deposition of the Pontoon Segments into the marine environment caused actual harm and likely harm to the to the environment. Criminal Antecedents and Compliance History 62 Mr King's criminal antecedents and non-compliance history are set out in Annexure A.
Contextual background facts
Mr King's record of interview
The photographic evidence
The Defendants' pleas of guilty
The issues for determination
Introduction
Introduction
Introduction
The Company's history
Mr King's history
Introduction
The three sunken pontoon sections
The evidence - a general outline
Mr Conradi's evidence
Mr MacDiarmid's evidence
The submissions concerning the provenance of the sunken pontoon section
Consideration
Environmental harm caused by the three sunken pontoon sections
Introduction
Dr Petch's evidence
The Prosecutor's submissions
The Defendants' submissions
Conclusion on environmental harm - the sunken pontoon sections
Control over the causes of the actual and potential environmental harm
Practical measures to mitigate harm
Surface dispersal and appearance issues of the transported material
Introduction
Mr Nugent's evidence
Mr King's record of interview
The Prosecutor's written submissions on visual impact
The Prosecutor's oral submissions on dispersal of the materials and on aesthetic impacts
The Defendants' submissions
Consideration
Conclusion on environmental harm
Introduction
The extent of harm (s 21A(2)(a))
Prior convictions (s 21A(3)(e))
The Company's character (s 21A(3)(f))
Contrition and remorse (s 21A(3)(i))
Entry of the Company's guilty pleas (s 21A(3)(k))
Cooperation with the Prosecutor (s 21A(3)(m))
The extent of harm (s 21A(2)(a))
Prior convictions (s 21A(3)(e))
Mr King's character (s 21A(3)(f))
Contrition and remorse (s 21A(3)(i))
Entry of Mr King's guilty pleas (s 21A(3)(k))
Cooperation with the Prosecutor (s 21A(3)(m))
Introduction
Specific deterrence
General deterrence
Characterisation of the Defendants' offending conduct
Introduction
Introduction
The waste transportation offences
The waste storage charges
Comparable cases for sentencing consideration
Introduction
The waste transportation charges
The waste storage charge
Introduction
The Prosecutor's submissions on the guilty plea discount
The Defendants' position
Consideration
The Defendants' financial capacity to pay a fine
Totality and accumulation
Costs
Requiring publication notices concerning the offences
Introduction
The Defendants' resistance to a publication order
Consideration
The terms of the notice proposed by the Prosecutor
The terms of the notice to be published
The appropriate publications in which the notice is to appear
The Manly Daily is now a digital-only newspaper
Afloat Magazine
No penalty moderation for the costs of publication
Orders
Annexure C Conviction of East Coast Wharf Constructions Pty Ltd (ACN 113 385 443) and Benjamin Peter King for Environmental Offences East Coast Wharf Constructions Pty Ltd (the Company) and Mr Benjamin King have each been convicted by the Land and Environment Court of NSW of two waste-related offences. The offences were breaches of the Protection of the Environment Operations Act 1997. Mr King was, and is currently, the sole shareholder, director and secretary of the Company. In these capacities, Mr King has what is known as "special executive liability" - meaning he is also liable for offences committed by the Company. The first offences arose from the Company transporting sections of a marina it demolished at Berowra to the Company's commercial mooring located in Pittwater to the west of Scotland Island. This constituted the offence of transporting waste to a location that could not be used as a waste facility for that waste. The second offences arose from the Company using its commercial mooring as a location to store the demolished marina materials pending further processing and disposal. This constituted the offence of using its commercial mooring as a waste facility without lawful authority to do so. The Court found, amongst other things, that three marina pontoon segments from those demolished from the Berowra Marina that had sunk in the marine environment of Pittwater caused actual harm to the environment and were likely to cause harm to the environment. The prosecutions were commenced by Transport for NSW following an investigation conducted by its NSW Maritime Branch. On 1 September 2020, the Company and Mr King pleaded guilty to these offences. On 16 October 2020, the Land and Environment Court convicted the Company and Mr King of the offences to which they had pleaded guilty. The Company and Mr King were ordered to pay a combined penalty of $133,000 and to pay the Prosecutor's costs of the proceedings. In addition, they were also ordered to pay for the cost of publishing this notice.
Amendments 16 October 2020 - References to 'Transcript 24 September 2020' altered to read 'Transcript 23 September 2020). The date on the transcript, when compiling judgment shown as Wednesday 24 September 2020, whilst the footer referred to 23/9/20.
Amended pursuant to the Slip Rule on 16 October 2020. 19 October 2020 - Front cover of judgment amended to read Class 5 rather than Class 4, pursuant to Slip Rule on 19 October 2020. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 19 October 2020
al Development Services; Environment Protection Authority v Botany Building Recyclers Pty Ltd; Environment Protection Authority v Foxman (No 2) [2016] NSWLEC 120 Environment Protection Authority v Hughes [2019] NSWLEC 108 Environment Protection Authority v Laison [2015] NSWLEC 89 Environment Protection Authority v Rands [2019] NSWLEC 23 Environment Protection Authority v Terrace Earthmoving Pty Ltd [2016] NSWLEC 158 Environment Protection Authority v Waste Recycling and Processing Corporation (2006) 148 LGERA 299; [2006] NSWLEC 419 EPA v Barnes [2006] NSWCCA 246 Hoare v The Queen (1989) 167 CLR 348; [1989] HCA 33 Markarian v The Queen (2005) 228 CLR 357; [2005] HCA 25 Newcastle City Council v Pace Farm Egg Products Pty Ltd [2002] NSWLEC 66 R v Olbrich (1999) 199 CLR 270; [1999] HCA 54 R v O'Neill (1979) 2 NSWLR 582 R v Thomson; R v Houlton (2000) 49 NSWLR 383; [2000] NSWCCA 383 Shoalhaven City Council v Knight [2019] NSWLEC 138 Veen v The Queen (1979) 143 CLR 458; [1979] HCA 7 Veen v The Queen (No 2) 164 CLR 465; [1988] HCA 14 Walden v Hensler (1987) 163 CLR 561; [1987] HCA 54 Wollongong City Council v Eldridge [2017] NSWLEC 35 Texts Cited: COVID-19 Pandemic Arrangements Policy Category: Sentence Parties: Transport for NSW (Prosecutor) East Coast Wharf Constructions Pty Ltd (Defendant in Matters 344508 and 344550 of 2018) Benjamin Peter King (Defendant in Matters 344556 and 344557 of 2018) Representation: Counsel: Mr E Muston SC/Ms B Anniwell, barrister (Prosecutor) Ms K Hawes, solicitor (Defendants)
[2005] HCA 25
(1993) 32 NSWLR 683
(2006) 148 LGERA 299
(1989) 167 CLR 348
(2005) 228 CLR 357
(1999) 199 CLR 270
(1979) 2 NSWLR 582
(2000) 49 NSWLR 383
(1979) 143 CLR 458
(1987) 163 CLR 561
(1988) 164 CLR 465