E. The strength of Symich's cross-claim
- While Symich's cross-claim seeks liquidated damages for delay, and damages for incomplete and defective work, only the former was pressed before me, perhaps because there was limited, if any, admissible evidence of the quantum of damages arising from the alleged incomplete and defective work.
- The claim for liquidated damages was the significant component of the reduction at adjudication of Team Dreegan's tenth payment claim. Whilst this decision by the adjudicator is not determinative of the result in the pending contractual proceedings, it indicates that Symich has already received substantial credit for its liquidated damages claim. The parties agree that only about $80,000 of the liquidated damages claimed by Symich was not allowed by the adjudicator. In addition, there were reasons of substance - for some of the residual period, Team Dreegan was barred from the site - why only part of this reduced amount could be maintained. The residual amount of the liquidated damages claim is thus far less than the judgment sum sought to be stayed, even assuming that Team Dreegan's claim for the retention moneys has no merit.
- Symich advances an alternative related argument. It submits that Team Dreegan did not comply with certain contractual provisions in issuing payment claim 10. [11] Whether only payment claim 10 (and not payment claim 11) was impugned in this allegation is not altogether clear. In any event, Symich maintained that the requirements in cl 37.1 of the subcontract needed to be satisfied in order to be a valid claim requiring payment.
- Symich conceded that the matters in cl 37.1 of the subcontract do not preclude a valid payment claim under the Act. Section 13 of the Act alone identifies the requirements of a valid payment claim, and s 34 of the Act precludes any purported contractual modification. Symich argued that the contractual provision remains effective in respect of the pending proceedings in contract, and that by virtue of s 32 of the Act, nothing in Pt 3 of the Act, including s 13, affects those proceedings.
- So far as the argument goes, this is correct, yet it suffers from two defects.
- First, contractual provisions requiring additional features for a valid progress claim only have operation in respect of the very subject matter dealt with under the Act, namely interim payments. If cl 37.1 has no work to do other than to purport to render invalid a payment claim which the Act validates under s 13, then the provision offends the bar on contracting out of the Act in s 34. In this way there is a real question as to whether cl 37.1 purports to modify s 13, and thus be void under s 34 of the Act.
- The second point is related. The existence of a contractually invalid progress claim does not, of itself, determine the rights and liabilities of the parties under the contract, and in this case, under a terminated contract. Symich was unable to identify any contractual provisions that identified how a party's contractual rights were affected by the payment of a progress claim validated by the Act, even if there was contractual non-compliance. Symich did not press the submission that it could recover all progress claims made and paid, validly under the Act, merely because there were, in the progress claim, omissions of some contractual stipulations. How the omissions led to any damage was not explained, once it is accepted that, for the purpose of progress payments, the Act cured any defects.
- Ultimately, this issue about the form of the payment claims did not matter. I was not satisfied that there was any contractual defect in the payment claims or that payment claim 10, or any earlier or later payment claim, did not provide the contractual details required by Symich. The evidence indicates the contrary, [12] that the payment plan was in the form and provided the detail required by Symich. In that event, there appeared to be no force in the challenge to the moneys paid by Symich. Symich was left with a relatively small claim for liquidated damages, and then only if Team Dreegan's claim for the retention moneys is dismissed.