Construction of cll 3.3, 3.6, 3.7 & 4.1
- It is well-established that provisions in a contract are to be interpreted objectively, by reference to its text, context (the entire text of the contract as well as any other contract, document or statutory provision referred to in the text of the contract) and purpose: Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104 at [47]. Both parties referred to this decision in their submissions. About context and purpose, a similar description is to say that the Court is to take into account the "surrounding circumstances known to the parties and the objects the agreement is intended to secure": Jingalong per Sackville JA (Meagher JA and Leeming JA agreeing) at [69].
- I understood the defendant to submit that properly construed, cl 3.3 was not a 'condition' in default of which the plaintiff was capable of exercising a right to procure the Court's enforcement of consent orders (being in the form of Annexure C to the Deed), whereby the plaintiff would obtain a Judgment in its favour for the sum of $186,000 and an order for costs on an indemnity basis (for the entirety of the proceeding).
- This submission flies in the face of the text. Clause 3.6 expressly states that time was of the essence for the defendant's performance of its obligation in cl 3.3. Read in the context of other provisions of the Settlement Deed, the strictness of the obligation is reinforced in cl 3.7(c) and again in cl 4.1. Read as a whole, cll 3 and 4 provide a careful structure for the staged payment of the Settlement Sum in instalments. Where there was default in the payment in accordance with those phases, cl 4 addressed the consequences of such default, including relevantly, the right to apply to enforce judgment (held in escrow) for the 'Amount Outstanding'. The 'Amount Outstanding' was what the defendant agreed was "presently due and payable" (cl 3.2).
- The context, more generally, does not indicate anything to the contrary. This included that the agreement was entered into through the process of alternative dispute resolution, in which the parties were legally represented. Further, they received independent advice about the Settlement Deed - the last fact being a matter which the defendant acknowledged in the Settlement Deed. The parties thus received advice about their respective rights and liabilities, which were subsequently reduced to an arm's length bargain. I see no reason why contextual matters would displace the ordinary and plain meaning of the obligations which, relevantly, were that breach of the time stipulation went to the root of the agreement; no matter what the insubstantiality or triviality of the lack of timeliness constituted by the defendant's delay. As the Privy Council said in Brickles v Snell [1916] 2 AC 599 at 604, the plaintiff is entitled to "stand upon the 'letter of his bond'"; followed in Hoad v Swan (1920) 28 CLR 258 at 263. Clause 3.6, in particular, removes any doubt: United Scientific v Burnley Borough Council [1978] AC 904 per Lord Diplock at 936. These principles are solidly entrenched in both the common law and in equity: Armada Balnaves Pte Ltd v Woodside Energy Julimar Pty Ltd [2022] WASCA 69 at [557]-[558].
- The defendant's submission that principles regarding the enforcement of essential time stipulations were qualified by Gaudron J in Sunbird Plaza Pty Ltd v Maloney (1988) 166 CLR 245, is misconceived. In that case the vendor sued a guarantor following the purchaser's omission to pay the balance of the purchase price prior to completion of the conveyance. There was no contractual provision contrary to the general position that the balance of the purchase price was payable at completion. Amongst other things, the guarantors raised the point, in their defence, that the vendor was itself in anticipatory breach, which thereby entitled the purchaser to terminate the contract. Although her honour referred to Hoad v Swan, that was not in the course of addressing the present point in issue; being whether a party in breach of what was expressed to be an essential time stipulation could be excused from the legal consequences on the basis that the breach was trivial or insubstantial.
- As to purpose, one object, or purpose, was that although the parties agreed that the defendant's liability to the plaintiff should be quantified at the sum of $186,000, inducement was offered to the defendant to receive a substantial (nearly 25%) discount, being the sum of $140,000, if that could be paid off in the period from 29 April 2022 to 7 July 2022 (a period of nearly 10 weeks), in accordance with closely regulated stages. Whilst this yielded incentive to the defendant to pay, it also assisted the plaintiff, in getting the settlement sum paid expeditiously and consequently obviating its need for a drawn out process in which it would have to enforce the settlement sum by other means. In this way, the provisions instilled certainty. But another and arguably predominant purpose, or object of the settlement Deed, was to instil the inherently related value of finality in the parties' positions; and to minimize, to the extent possible, further recourse to litigation.
- It is understandable that the defendant would say that a substantial compliance with the dates for payment was not inconsistent with the purpose of the agreement to give incentive to pay a discounted settlement sum as soon as possible, but its construction subverts the main, or at least very important, purpose of the agreement of instilling finality or certainty; since it was an inherently uncertain notion to construe the obligation to pay by reference to what was 'reasonable'. It has also subverted the other purpose of ensuring expeditious payment of the settlement sum since its construction creates uncertainty as to when, and in what circumstances, the time stipulations for payment by instalment could be altered.
- I reject the defendant's argument that the construction that the plaintiff argues for, and which I accept - giving effect to the ordinary and plain meaning of the defendant's obligations in cll 3 and 4 - would be absurd or impracticable. To the contrary, it is readily understandable in the context that the agreement was made and consistent with its objects.