[2006] HCA 46
Beecham Group Ltd v Bristol Laboratories Pty Ltd (1968) 118 CLR 618
[1968] HCA 1
Blacktown City Council v Penatrators Pty Ltd [2013] NSWLEC 169
[1998] HCA 30
Ross v State Rail Authority of New South Wales (1987) 70 LGRA 91
Samsung Electronics Co Ltd v Apple Inc (2011) 217 FCR 238
Source
Original judgment source is linked above.
Catchwords
[2006] HCA 46
Beecham Group Ltd v Bristol Laboratories Pty Ltd (1968) 118 CLR 618[1968] HCA 1
Blacktown City Council v Penatrators Pty Ltd [2013] NSWLEC 169[1998] HCA 30
Ross v State Rail Authority of New South Wales (1987) 70 LGRA 91
Samsung Electronics Co Ltd v Apple Inc (2011) 217 FCR 238
Judgment (7 paragraphs)
[1]
EX TEMPORE Judgment
Presently before me as Duty Judge is a Notice of Motion seeking interlocutory relief.
On 15 August 2017 Strathfield Municipal Council ('Council') commenced Class 4 proceedings pursuant to s 123 of the Environmental Planning and Assessment Act 1979 (NSW) ('Act') seeking to remedy a breach of s 76A of the Act arising from the respondents allegedly carrying out development in contravention of development consent DA 0405/176/03 ('Consent'). There are three respondents in the proceedings, Michael Raad Architect Pty Ltd, the project architect and the named applicant for the Consent and modification applications to which I will come; Hallmark Constructions Pty Ltd, the builder; and Telmet Ventures Pty Ltd, the property developer and the project manager.
The Consent related to a development situated at SP 87671 81-86 Courallie Avenue, Homebush West ('land'). These interlocutory proceedings relate specifically to the part of the development known as Building 6. Council seeks to restrain each of the respondents from carrying out further development on the land other than in compliance with the Consent, and in particular to restrain the respondents from constructing the level 1 basement at Building 6 other than in accordance with the Consent.
The Summons was originally filed on 15 August 2017, and an Amended Summons was filed on 22 August 2017 seeking relief as follows:
1 A declaration that:
a. the Respondents have breached section 76A of the Environmental Planning and Assessment Act 1979 (NSW) by carrying out development on Building 6 at SP 87671 (also known as '81-86 Courallie Avenue, Homebush West - Stage 1D') (the Land) in contravention of development consent DA0405/176/03.
2 Orders that:
a. the Respondents demolish all unauthorised development on the Land, including;
i. the reinforced concrete columns and piles;
ii. the reinforced concrete lift and stair shafts;
iii. the in-ground stormwater drainage; and
iv. the Basement 1 level concrete slab;
b. the Respondents, their servants, and agents, do not construct the basement of Building 6 at SP 87671 otherwise than in accordance with the development consent DA0405/176/03; and
c. the Respondents pay the Applicant's costs.
3 Any further Order that the Court deems appropriate.
On 15 August 2017, Council filed a Notice of Motion seeking interlocutory relief, which was also amended on 22 August 2017 ('Motion'). The amended Motion sought interlocutory relief as follows:
1 That the Respondents, having carried out development on Building 6 at SP 87671 (also known as '81-86 Courallie Avenue, Homebush West - Stage 1D') (the Land) in contravention of development consent DA0405/176/03, are in breach of section 76A of the Environmental Planning and Assessment Act 1979 (NSW).
2 That the Respondents, their servants, and agents, do not construct the basement of Building 6 at SP 87671 otherwise than in accordance with the development consent DA0405/176/03.
3 That the Respondents pay the Applicant's cost of this Notice of Motion.
4 Any further Order that the Court deems appropriate.
As this matter has been before me as Duty Judge on three separate occasions within the last week I note the following background leading up to this morning's decision.
The Motion first came before me late in the afternoon on 15 August 2017. The applicant was represented by Mr Leggat SC and the respondents were represented by Ms Berglund of counsel. Mr Leggat relied upon two affidavits of Roberto Giglio, Council's Development and Compliance Officer, affirmed 10 and 15 August 2017 respectively. The matter at that time was apparently to proceed on an ex parte basis and I note that Ms Berglund had received instructions very shortly before the matter came before the Court.
In summary, Council's concern was that it had become aware that there were "unauthorised" works being undertaken in relation to Building 6 on the land. More specifically, that construction work was being (or about to be) undertaken to construct a single-level basement car park that Council submits was not in accordance with the Consent, which provided for a two-level basement car park. Although a modification application had been lodged pursuant to s 96 of the Act to modify the Consent to delete one of the basement level car parks ('Modification Application'), the Modification Application, at least at 15 August, and as at today's date, has not been determined.
The evidence was that Council officers had observed work being undertaken by the respondents or being prepared to be undertaken which would have not been in conformance with the Consent as it stood but was likely to be in conformance with the Consent if it was modified. The primary concern of Council at the time, based on its evidence, was the site had been prepared for a concrete pour and that certain concrete pillars had been constructed which provided "a single level basement on Building 6 without excavating for two basement levels as approved by condition 1 of the Consent".
There was further evidence that a private certifier, Steven Saad (who had issued a Construction Certificate on 14 October 2016 in relation to the "...construction of concrete elements in buildings 5 and 6") had been advised by Council that "the basement does not comply with his approved Construction Certificate plans". Mr Saad then sent a Notice of Proposed Order dated 9 August 2017 to the third respondent (the property developer and project manager) stating that he was intending to issue an order pursuant to s 121B of the Environmental Planning and Assessment Act as the construction works were not being undertaken in accordance with approved plans.
Based upon the material before me on 15 August 2017, and adopting the principles which I will come to in due course, but particularly those considered by Preston CJ of LEC in Tegra (NSW) Pty Ltd v Gundagai Shire Council [2007] NSWLEC 806; (2007) 160 LGERA 1 ('Tegra') and Shoalhaven City Council v Bridgewater Investments Pty Ltd [2010] NSWLEC 103 at [4]-[5], I was satisfied that despite no undertaking of damages being proffered by Council, it was appropriate to grant interlocutory relief (see Strathfield Municipal Council v Michael Raad Architect Pty Ltd (No 1) [2017] NSWLEC 105 for my reasons). Accordingly, on 15 August 2017, I made orders as follows:
The Court orders that, until further order:
(1) The respondents, their servants, and agents, cease all unauthorised development on the Land.
(2) The respondents, their servants, and agents, do not construct the basement of Building 6 at SP 87671 otherwise than in accordance with the development consent DA0405/176/03.
Note: The matter is returnable before Justice Robson at 1:15pm on 17 August 2017.
On 17 August the Motion came before me again at 1:15pm. Mr Leggat SC again appeared for Council and Mr Lancaster SC appeared for the respondents. Mr Pickles SC attended and sought leave to appear for Rail Corporation New South Wales ('Rail Corporation') as the Crown pursuant to s 64(1) of the Land and Environment Court Act 1979 (NSW).
Mr Pickles indicated that, although Rail Corporation did not have detailed knowledge of the application presently before the Court (nor the Modification Application) it had a concern that any change in the nature of the construction or development that had been the subject of the Consent may have an effect on the main eastern rail corridor, which was situated adjacent to the site. Accordingly, Rail Corporation sought to participate in the proceedings, at least to ensure that its interests were not likely to be deleteriously affected by any change in the nature, extent and manner of construction of the development. I have been informed today that Rail Corporation's concerns have been addressed between the parties themselves and Mr Pickles has accordingly been excused.
When the matter came before me on 17 August 2017, Council had marshalled further affidavit evidence that there had been a number of additional non-compliances that had not been brought to the Court's attention in the earlier affidavits of Mr Giglio.
Mr Lancaster at that time indicated to the Court that the respondents had marshalled and filed a number of affidavits, including expert engineering evidence, which addressed the nature and conduct of the work that had been undertaken and opined that the construction work apparently of concern to Council would not preclude appropriate compliance with the Consent if the Modification Application was unsuccessful.
It was clear at the time that neither party had had the opportunity of considering closely the other party's further evidence. Accordingly, I made the following orders:
(1) Until 4:00pm Tuesday 22 August 2017, the respondents, their servants and agents, do not construct the basement of Building 6 at SP 87671 otherwise than in accordance with development consent DA0405/176/03.
(2) The applicant is to file and serve any further expert evidence by 5:00pm Friday 18 August 2017.
(3) The respondents are to file and serve any further expert evidence by 12:30pm on Monday 21 August 2017.
(4) The parties are to serve copies of expert evidence on Rail Corporation New South Wales on the respective dates for filing and service in orders 2 and 3 above.
(5) The interlocutory matter is stood over to 10:00am on Tuesday 22 August 2017 for hearing.
The hearing of the Motion proceeded on 22 August. Council read six affidavits, being:
1. two affidavits of Roberto Giglio affirmed 10 August 2017 and 15 August 2017;
2. an affidavit of Geoffrey Baker, Council's in-house solicitor, sworn 16 August 2017; and
3. three affidavits of Roderick James Broune, a consulting structural engineer, sworn 16 August 2017, 17 August 2017 and 18 August 2017.
The respondents read eight affidavits, being:
1. two affidavits of Javier Toledo, an architect for the first respondent, affirmed 16 August 2017 and 18 August 2017;
2. three affidavits of John Raymond Frendo, construction manager for the second respondent, one affirmed 17 August 2017 and the others affirmed on 21 August 2017;
3. an affidavit of Ben Cheong, structural engineer for the second respondent, affirmed 17 August 2017;
4. an affidavit of Michael Sarkis Raad, principal of the first respondent, affirmed 17 August 2017;
5. an affidavit of Pushpachandra Wijewickrama Ratnayake, structural engineer, affirmed 21 August 2017.
The primary background facts are uncontentious and can be summarised as follows:
1. Development consent for the proposed development was originally granted to the first respondent on 12 June 2007 and provided for a residential building of three levels (plus an attic) above the ground floor, with a single basement level car parking.
2. A modification application was made to modify the development to increase the height of the then approved Building 6, which sought to increase the number of apartments in the building and provide for a second level of basement parking to accommodate the additional apartments.
3. Council approved the application (which became DA0405/176/03) on 24 August 2015 in a modified form by allowing the second level of basement parking but not approving the additional apartments.
4. According to the evidence of the respondents, as the extra levels of apartments were not approved, the second basement level for Building 6 was no longer required. As a consequence, on 20 July 2017 the respondents made the Modification Application to delete the second level of the basement of Building 6.
5. The Modification Application is before the Independent Hearing and Assessment Panel ('IHAP') which is to give consideration to the matter on or about 7 September 2017. There is evidence before the Court that the respondents have been informed by an officer of Council that the report to be provided by Council to the IHAP will be supportive of the Modification Application.
Put simply, the respondents' position is that while work has been undertaken in anticipation of the Modification Application receiving approval, even if it is refused, it will still be feasible to excavate and construct the level 2 basement using a method commonly referred to as "top-down" construction. Accordingly, the respondents submit that regardless of the outcome of the Modification Application, the development will be (or is able to be) in compliance with the Consent. I note that there is dipsute in relation to this matter.
Although the respondents accept that the present works may well not be the most practical way to proceed, they maintain that the manner in which the work is being undertaken does not affect the ability to properly and fully comply with the Consent. While there is some attendant risk and not insignificant expense in proceeding in this manner, the respondents submit that this is a matter for them, and that they are prepared to and indeed have assumed this risk.
I note that when the matter was first before me on 15 August 2017, it appeared to be common ground that if the Modification Application was successful, the works which were of concern to Council would otherwise be the subject of approval. This position has changed according to Council's more recent evidence.
[2]
Consideration
The principles governing the grant of interlocutory relief are well‑known. Council must demonstrate there is a serious question to be tried such that there is a sufficient likelihood of success to justify the granting of interlocutory application, and that the balance of convenience favours the grant of an interlocutory application.
The principles have been stated on many occasions and I refer to: Australian Broadcasting Corporation v O'Neill (2006) 227 CLR 57; [2006] HCA 46 at [19]; Patrick Stevedores Operations No 2 Pty Ltd v Maritime Union of Australia (No 3) (1998) 195 CLR 1; [1998] HCA 30 at [170]; Samsung Electronics Co Ltd v Apple Inc (2011) 217 FCR 238; [2011] FCAFC 156 at [44] and, Tegra at [6], [7], [13]-[19] and [54].
The Court must also consider whether there are any discretionary reasons for refusing the injunction, such as delay and the like. When considering the balance of convenience, the Court will consider whether Council will suffer irreparable harm for which damages will not be an adequate remedy.
[3]
Serious question
Council submits that the potential breach of s 76A of the Act creates a serious question to be tried. To demonstrate this breach Council points to the approved plans, which are the subject of consideration and considerable evidence in the proceedings, and states that first, a number of works that have already been constructed not in accordance with the Consent, and second, it is clear on the evidence that, if not restrained, there will be further work carried out which will also not be in accordance with the Consent.
Council relies upon the evidence of Mr Broune set out in his affidavit of 18 August 2017 at pars 15, 18 and 21 to demonstrate the unlawful works. This evidence related to four discrete concerns in relation to the completed and proposed construction, being, first, the reinforced concrete columns; second, the concrete shafts; third, the stormwater drainage works; and fourth, the construction of the level 1 basement ground floor slab. Mr Broune's concerns were expanded in his oral evidence.
In relation to the reinforced concrete columns, Mr Broune's evidence made clear that there are 59 columns presently constructed which are 1200 millimetres wide and which do not have approval. To the extent these columns were the subject of approval, the evidence is that they should be (or should have been) 350 millimetres wide. Mr Broune gives evidence in relation to his consideration of the concrete columns and has produced markings on the plans which were attached to the Construction Certificate (being annexures to his affidavit of 18 August 2017). Mr Broune made a number of corrections to the markings in colour on those plans, and the annotations clearly show his opinion that there has been non-compliance. He also attests that, as a result of the layout of the works presently being undertaken, and likely to be undertaken, there will be insufficient room to maintain the approved layout of the car parking on the level 2 basement if the 1200 millimetre diameter piles are to be retained in place of the approved 350 millimetre wide (by 1 metre long) columns.
Mr Broune also indicated his concern regarding non-compliance in relation to the concrete lift and stair shaft. Specifically, Mr Broune stated that the constructed shafts are 1.2 metres longer and wider than the approved shafts, and that the reinforced concrete bases seal off the open shafts that are required by the Consent to build level 2 of the basement. Mr Broune attests that these concrete bases would need to be demolished to build the level 2 basement, and that the existing reinforced concrete lift and stair shafts would need to be extended.
In relation the stormwater works, Mr Broune's evidence indicates, while the Consent provides for a reinforced concrete stormwater detention pit below the level 2 basement, the stormwater drainage has already been constructed by the respondents under the level 1 basement. Accordingly, Mr Broune's evidence is that if the respondents were required to construct the currently approved level 2 basement in accordance with the Consent, the stormwater drainage works currently built under the level 1 basement would need to be removed and replicated below the level 2 basement.
Finally, Mr Broune also gives evidence in relation to his observations that the concrete slab that is in the course of being constructed for the level 1 basement floor, and the manner that it is being constructed, will not provide proper support if the level 2 basement is required to be constructed. Accordingly, Mr Broune attests that the concrete slab would need to be demolished and replaced with a heavier concrete slab if the level 2 basement is ultimately required.
The response of the respondents, both in relation to the expert evidence marshalled and the submissions, is that whilst there is no concession that the basement, or other works, have been constructed otherwise than in accordance with the Consent, relying particularly on Mr Frendo, the respondents' evidence is that if there is a failure to obtain approval for the Modification Application, the work that has been undertaken, can be deconstructed and the level 2 basement is able to be constructed.
In relation to the concrete slab in particular, the respondents' evidence is that if necessary to remove the slab it would be simple to do, and using the "top-down" construction method, a standard industry practice, this would be replaced by a post-tensioned suspended slab which would also then allow construction of the level 2 basement floor. Mr Frendo attests that, in relation to Mr Bourne's concern regarding temporary supports during this process, it is "universal practice" for these to be used to prop a removed supporting element until a new supporting element is constructed.
In relation to the stormwater detention pit, Mr Frendo stated in cross-examination that that which has been constructed is not in fact a stormwater detention pit, and that in any case, can be moved if so required.
There is some dispute in relation to Mr Broune's evidence, however on balance, I find the respondents' evidence unsatisfactory given the nature of the works constructed thus far, and find that Mr Broune's evidence is to be preferred. In the circumstances I accept his evidence and find that the works presently undertaken are most likely to be unauthorised such that there is clearly a serious question to be tried.
[4]
Balance of convenience
In relation to the balance of convenience, it is clear from the authorities, in particular Beecham Group Ltd v Bristol Laboratories Pty Ltd (1968) 118 CLR 618; [1968] HCA 1 at 622-623 and Tegra at [13], that the Court must consider whether the inconvenience or injury which the applicant for interlocutory relief would be likely to suffer if the injunction were refused outweighs or is outweighed by the injury which the defendant would suffer if an injunction were granted.
The question of irreparable injury tends to be treated by the courts not as an independent consideration but as part of a balance of convenience (Tegra at [15]). Council submits, and I accept, that the irreparable harm or any harm does not need to be suffered by Council personally and that the harm can be the failure to enforce the law for the orderly development and use of the environment. Those matters have also been considered by Hunters Hill Council v Fraser [2006] NSWLEC 744 at [50].
In relation to the balance of convenience, I accept the material set out in Mr Broune's affidavit of 16 August 2017, particularly at par 12 that the complexity and the risk involved with complying with the Consent are likely to increase as the construction of the building proceeds to higher levels. Further, in his affidavit of 17 August Mr Broune sets out material which responds to the suggestion by the respondents that the work which is undertaken can be, to use my word, "deconstructed".
I find that the evidence of Mr Broune demonstrates that the coordinated nature of the additional controls and complexities that arise in what he calls the "retrofitting" of the level 2 basement (should it be required) is compelling in establishing that the balance of convenience lies in favour of Council. I accept also Mr Broune's evidence that if Building 6 proceeds to higher levels it increases the complexity of the support that is otherwise required and that therefore the nature and extent of the further work that would be required to then construct is greater if the injunction is not granted.
Whilst not conceding that there is a serious question to be tried, the respondents raise a number of reasons why, on the balance of convenience, relief should not be granted. First, they submit that there has been significant works completed already on part (or up to half) of the level 1 basement. I do not find this fact particularly compelling in the circumstances where there is a prima facie case that that work (or part thereof) is unauthorised.
Second, the respondents submit, that although the possible deconstruction will be more expensive, and with some risk, these are steps which the respondents are prepared to undertake. The respondents also repeat their submission that the level 2 basement can be constructed through top-down construction. While I accept that from a technical engineering point of view the top‑down construction could be undertaken to fulfil the requirements presently involved in the Consent, I do not find it compelling in relation to the balance of convenience given the concern that the works are not in accordance with the Consent.
Third, the respondents submit that the Modification Application is one which, on the evidence, I am entitled to assume, is likely to receive approval. I accept that the Modification Application was lodged on 20 July 2017 and that it is likely that a decision will be given in the relatively near future, such that if approval is received then most of that which has been undertaken is unlikely to remain a matter of concern. The mere fact that it is likely, on the respondents' highest case, that the Modification Application will be successful is not a matter which I find compelling. I accept that if the Modification Application is approved the injunction which I am asked to impose may have a relatively limited life. I do not however consider this to be a determining factor as to whether I grant relief.
The final matter raised on behalf of the respondents is that, as a practical and planning matter, the level 2 basement is unnecessary. I accept that this may be the case from a commercial and practical point of view and I accept the respondents' evidence, which has not been the subject of any contrary evidence, that there may be good planning reasons for the deletion of the extra car parking otherwise provided for in the level 2 basement. However, in the circumstances of the Consent being on foot and given the Modification Application has not yet been determined, I do not find this aspect to be compelling and I do not accept that an injunction would have little or no utility, as submitted by the respondents.
Although it is also submitted by the respondents that there are third parties who have an interest in relation to the progress of the construction of the development, I am not satisfied and there is little evidence to suggest that the interests of any third party, nor the commercial considerations of the respondents, are of weight in this matter. Further, there is no evidence of any real commercial detriment. Although I accept that there would be a preferred construction pathway, there is no evidence to the effect that there is a critical path which would otherwise be deleteriously affected by the grant of interlocutory relief.
Council has not proffered an undertaking as to damages and prays in aid the comments of the then Chief Judge of this Court in Ross v State Rail Authority of New South Wales (1987) 70 LGRA 91 and recently reiterated by Pepper J in Blacktown City Council v Penatrators Pty Ltd [2013] NSWLEC 169; (2013) 199 LGERA 73 at [33]-[35]. In the circumstances, I am satisfied that the proceedings are brought in the public interest insofar as there is a real and necessary public interest in upholding the planning laws of the State by Council. A similar approach was taken by Pain J in Tenterfield Shire Council v Budd [2016] NSWLEC 89 at [13].
I note that the respondents have submitted that the relief sought by Council may in fact require the removal of that which has already been constructed. I do not accept this. The interlocutory relief sought is to preserve the status quo until the hearing of the substantive proceedings.
[5]
Conclusion
On the evidence before me, it appears that the respondents' conduct, although understandable from a practical, result-driven objective, did involve work which Council (and indeed the certifier), has not approved. I accept that there is a Modification Application that is pending, however the mere fact that that which is being undertaken can be deconstructed if the Modification Application is not forthcoming is not persuasive. The respondents clearly took a calculated risk in undertaking this further work, however the Court should not countenance what appears to be a flouting of the planning regime simply because the respondents are prepared to take what is said to be a commercial risk.
For the reasons stated above, I am therefore of the view that there is a serious question to be tried and that the balance of convenience favours Council. There has been no unreasonable delay in seeking interlocutory relief and there does not appear to be any significant prejudice to third parties.
[6]
ORDERS
The Court orders that:
1. Until further order of the Court, the Respondents, their servants and agents, do not construct the basement of Building 6 at SP 87671 otherwise than in accordance with development consent DA0405/176/03.
2. The matter is stood over for further directions before the List Judge on 15 September 2017.
3. The parties have liberty to apply.
4. Costs are reserved.
[7]
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 14 September 2017