[A reference to the finding for the cross-claimant to the first cross claim in the sum of $230,996.00]
4 In order to follow the challenge to the referee's ultimate finding it is necessary to track through:
· the relevant paragraphs of the first report;
· the relevant paragraphs of the second report;
· the challenge to the reasoning adopted in the second report mounted by the cross-claimant;
· The contradictor submissions of the cross-defendant
5 The referee expressed his material findings in the second report in terms of an acceptance of submissions put to him by the cross-defendant.
Dealing with the matter
6 As explained in the 28 September 2004 judgment (at [13]), the appropriate construction of the relevant communications by the referee had to take into account the relevant background as known to all parties and as proven before him. That same consideration is ultimately pervasive in relation to the present challenge to the further report.
7 I have come to the conclusion that the challenge is without substance.
8 The September judgement included a section setting out the principles which are to be applied. It may be appropriate to amplify that examination briefly:
· the principles which inform the Court's discretion whether and to what extent to adopt, vary or reject the referee's report are as set out in Super Pty Ltd v SJP Formwork (Aust) Pty Ltd (1992) 29 NSWLR 549 [an appeal from Giles J in SJP Formwork (Aust) Pty Ltd v Leda Constructions Pty Ltd (19 May 1992, unreported)];
· on the appeal the appellant submitted that Giles J misconceived the nature of his duty under Pt 72. It was submitted that his Honour was obliged to consider and determine for himself, all issues whether of fact or of law, in respect of which the appellant was not satisfied with the referee's report. In particular, that Giles J should have re-heard some of the evidence and formed his own view as to their reliability;
· this contention was rejected by Gleeson CJ (Mahoney JA and Clarke JA agreeing). Gleeson CJ agreed with Giles J's approach (as set out above) - see (1992) 29 NSWLR 549 at 564.
· Gleeson CJ reviewed the provisions of Part 72 (see (1992) 29 NSWLR 549 at 556-558). His Honour emphasised the importance of Pt 72 r 8 and the wording on r 13(1), which "appear[s] to confer a wide discretion". Gleeson CJ concluded that:
"The proposition that all litigants are entitled to have a judge (or, presumably, a master) decide all issues of fact and law that arise in any litigation, is unsustainable… Again, one thing that is clear about Pt 72, r 13 is that the procedure it establishes is not that of an appeal from a referee to a judge." (at 558) [emphasis added]
· Gleeson CJ then reviewed the historical development of Pt 72 (see (1992) 29 NSWLR 558-560). In particular, the cases of Buckley v Bennell Design & Construction Pty Ltd (1978) 140 CLR 1 (per Stephen J and Jacobs J) (which concerned the provisions of the Arbitration Act 1902) and Astor Properties Pty Ltd v L'Union des Assurance de Paris (1989) 17 NSWLR 483 (per Cole J).
9 A comprehensive summary of the relevant principles that have been established is set out in the judgment of O'Keefe CJ in Comm D in Peabody Resources Limited v Allco Construction Pty Ltd [NSWSC, unreported, 14 March 1994, pages 10-13]. They were also distilled by Hunter J in Walter Construction Group Limited v Walker Corporation Limited (2001) 47 ATR 48 and recently approved by Barrett J in Abigroup Contractors Pty Limited v Peninsula Balmain Pty Limited [2001] NSWSC 752 at paras, 19-21. The appeal in Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Limited did not concern his Honour's reasoning as to the relevant principles that should apply on an application to adopt a referee's report].
The construction issues
10 One of the difficulties which is involved in determining the merit of the present challenge to the further report is that the construction of the material correspondence again becomes critical at a number of levels. In deference to the cross-claimant's current challenge I returned to the material correspondence and carefully read it and of course also carefully examined the material sections of the first and second report. All this in the context of the submissions presently made on the motions.
11 As already observed the procedure established by Pt 72, r 13 is not that of an appeal from a referee to a judge.
12 In my view the referee is not shown to have erred in his reasoning where he accepted in its entirety the cross-defendant's submissions which the referee set out in the further report (at [27]).
13 Without being exhaustive it is convenient to refer to the following matters:
· paragraphs [19]-[22] of the second report have not been shown to exhibit an error calling for a rejection of the report within the above described principles;
· paragraphs [23]-[ 25] of the second report have not been shown to exhibit an error calling for a rejection of the report within the above described principles;
· paragraph 28 of the second report [accepting as correct the cross- defendants submissions (detailed in paragraph 27 [26-35] of those submissions)] has not been shown to exhibit an error calling for a rejection of the report within the above described principles;
· paragraphs [4]-[9] have not been shown to exhibit an error calling for a rejection of the report within the above-described principles.
14 It is inappropriate to do more than to make the points that the referee in a fairly difficult context documented by imperfect materials had to endeavour to deal with the concepts:
· substantial alteration to the design or scope of works [letter of 31 August 1992];
· future costs variations [letter of 24 May 1994].
15 The difficulties involved included the fact that whilst (1) an alteration to the design or scope of the work might result in a costs variation, and (2) whilst a costs variation might result from an alteration to the design or scope of the work, it was also possible:
· that substantial design changes involving omissions or substitutions could result in no costs variation;
· that a costs variation could arise from a variety of causes entirely unrelated to changes in the design or scope of the work.
16 The relevant context made it necessary for the referee to deal with the asserted need for a different method of valuation for on the one hand, changes in scope, and on the other hand, changes in design. . The real issue however concerned whether, properly construed, the agreement: