© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2019] NSWDC 224
District Court of NSW
2017-11-24
Original judgment source is linked above.
Solicitors: McCulloch Robertson (NSW Department of Industry, Skills and Regional Development) Seyfarth Shaw (Defendant) File Number(s): 2016/174236 Publication restriction: None
TABLE OF CONTENTS TABLE OF CONTENTS Judgment Introduction Facts General background The dewatering system Sumps Drain holes Strainers Large capacity pumps The organisation of mining activities The safety procedures at the mine The Mine Safety Management Plan (MSMP) The MOC Procedure The CSA Controls The CSAfe Procedure The JSA Procedure Safe Work Procedures Drug and Alcohol Policy Safety topic of the month Enforcement of Safe Work Procedures The Health Safety Environment and Training Department (HSET) Regular Inspections by a dedicated Mines Inspector General practices in relation to sumps prior to the incident Events leading up to the incident The 8670 Pump Station Project Events of 11 June 2014 Evidence of Anthony Gaydon Evidence of James Russell Evidence of Tony Chaplain Evidence of Terry Roberts Evidence of Jamie Baber Evidence of Dan Howard Evidence of Robert Cownie Evidence of Kenneth McMillan Evidence of Gavin Booth Findings of fact relating to the incident Events after the incident The Manager's Specific Instruction - Working in and Around Sumps Events of 16 June 2014 The autopsy report The Sump Procedure The elements of the offence The relevant law consideration Element 3 - Did the defendant fail to comply with its health and safety duty by failing to take the steps particularised in [6] of the Summons? The pleaded risk The likelihood of the risk occurring The degree of harm The defendant's knowledge of the risk and the ways of eliminating or minimising the risk The defendant's knowledge of the pleaded risk Was the pleaded risk reasonably foreseeable? Mr McMillan's instructions at the pre-shift meeting The particulars of breach [16] Of the Summons [17] Of the Summons [18] Of the Summons [19] Of the Summons Conclusion on Element 3 Element 4 - Did the defendant's breach of duty expose Mr Hern to a risk of death or serious injury? Causation The intoxication issue The Evidence of Dr Judith Perl Evidence of Dr Michael Robertson Consideration of the Intoxication Issue Conclusion on Element 4 Conclusion and Orders
Introduction
General background
The dewatering system
Sumps
Drain holes
Strainers
Large capacity pumps
The organisation of mining activities
The safety procedures at the mine
The Mine Safety Management Plan (MSMP)
The MOC Procedure
The CSA Controls
The CSAfe Procedure
The JSA Procedure
Safe Work Procedures
Drug and Alcohol Policy
Safety topic of the month
Enforcement of Safe Work Procedures
The Health Safety Environment and Training Department (HSET)
Regular Inspections by a dedicated Mines Inspector
General practices in relation to sumps prior to the incident
The 8670 Pump Station Project
Events of 11 June 2014
Evidence of Anthony Gaydon
Evidence of James Russell
Evidence of Tony Chaplain
Evidence of Terry Roberts
Evidence of Jamie Baber
Evidence of Dan Howard
Evidence of Robert Cownie
Evidence of Kenneth McMillan
Evidence of Gavin Booth
Findings of fact relating to the incident
Events after the incident
The Manager's Specific Instruction - Working in and Around Sumps
Events of 16 June 2014
The autopsy report
The Sump Procedure
The elements of the offence
The relevant law
Element 3 - Did the defendant fail to comply with its health and safety duty by failing to take the steps particularised in [6] of the Summons?
The pleaded risk
The likelihood of the risk occurring
The degree of harm
The defendant's knowledge of the risk and the ways of eliminating or minimising the risk
The defendant's knowledge of the pleaded risk
Was the pleaded risk reasonably foreseeable?
Mr McMillan's instructions at the pre-shift meeting
The particulars of breach
[16] Of the Summons [16] The Defendant failed to ensure, so far as was reasonably practicable, that a safe work environment was provided for undertaking the task of unblocking the 8820 North sump. In particular, the Defendant failed to reduce the depth of the water in the 8820 North sump by pumping water out of the 8820 North sump prior to Mr Hern being required to undertake the task of unblocking the 8820 North sump drain hole.
[17] Of the Summons [17] The Defendant failed to ensure, so far as was reasonably practicable, that a safe system of work was provided for the blocking and unblocking of the 8820 North sump drain. In particular, the Defendant failed to: (a) conduct a Job Safety Analysis (JSA) for the task of unblocking of the 8820 North sump; and/or (b) develop, implement and enforce an adequate work procedure for the task of blocking and unblocking of sump drains, which specified: (i) that before blocking drain holes a risk assessment must be carried out considering how the hole will be unblocked and water managed during the time that it is blocked; and/or (ii) that before unblocking the drain holes a risk assessment must be carried out considering the safety of personnel performing the task as well as the management of water at the lower levels when the drain is unblocked; and/or (iii) the reduction of the volume of water in a sump before working in, around and under sumps; and/or (iv) the installation of a pump to reduce the water level before attempting to unblock sump drain holes with high water; and/or (v) a prohibition on workers entering sumps where the level of the water was above 'gum boot height' or the level of water could not be easily determined; and/or (vi) that where work was required to be performed in relation to a sump using an Integrated Tool Carrier, that workers must work from a work basket using a fall arrest system; and/or (vii) that, where possible, drain holes in sumps should be unblocked from below using a drill rig.
The completion of a JSA
Implement a Safe Work Procedure
[18] Of the Summons [18] The Defendant failed to ensure, so far as was reasonably practicable, the provision of adequate information and instruction to Mr Hern, in respect of the task of unblocking the 8820 North sump drain, in particular in respect to: (a) the depth of water that was in the sump; and/or (b) the location of the drain hole; and/or (c) the equipment that had been used to block the drain; and/or (d) the procedure to use for unblocking the sump drain, including the plant, tools and equipment required for the task; and/or (e) a prohibition on entering the water at the 8820 North sump where the level of the water was above 'gum boot height' or the level of water could not be easily determined.
[19] Of the Summons [19] The Defendant failed to ensure, so far as was reasonably practicable, the provision of adequate supervision to Mr Hern, in respect to the task of unblocking the 8820 North sump, in particular in respect to: (a) ensuring, so far as was reasonably practicable, a safe work environment in accordance with paragraph 16 above; and/or (b) ensuring, so far as was reasonably practicable, a safe system of work in accordance with paragraph 17 above.
Conclusion on Element 3
Element 4 - Did the defendant's breach of duty expose Mr Hern to a risk of death or serious injury?
Causation
The intoxication issue
The Evidence of Dr Judith Perl
Evidence of Dr Michael Robertson
Consideration of the Intoxication Issue
Conclusion on Element 4
Conclusion and Orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 04 June 2019
Stephen James Orr
Cobar Management Pty Ltd
[2019] VSCA 50
[2011] WASCA 117
[1999] NSWIRComm 453
(2012) 246 CLR 92
(1985) 11 IR 467
(1986) 5 NSWLR 209
(2016) 49 VR 676
(1952) 87 CLR 313
(2010) 239 CLR 531
(2006) 14 VR 321
(1991) 172 CLR 378
(2001) 205 CLR 304
(1957) 97 CLR 337
(2010) 78 NSWLR 94
(2004) 135 IR 166
(1998) 82 IR 80