[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE
[This headnote is not to be read as part of the Judgment]
Spotlight Pty Ltd (Spotlight) was the lessee of premises in Nowra under a registered lease granted by the lessor Fatseas Investments Pty Ltd (Fatseas) on 28 April 2004. The premises became damaged a result of water entering through the roof following a heavy rainfall event on 3 November 2007.
In October 2013, Spotlight commenced proceedings in the Supreme Court against, among others, Fatseas, claiming damages for negligence, nuisance and breach of the lease. In November 2015, Fatseas filed a second cross-claim against Spotlight alleging breaches of the covenants in the lease to maintain and repair the premises, and to regularly clean and clear all gutters, downpipes, drains and other pipes. Fatseas claimed damages or indemnity for the costs of repair and reinstatement of the premises, and loss of rent and outgoings for the period after the flooding from November 2007 to July 2008. Spotlight's claims were ultimately settled by the parties in August 2017.
Fatseas' second cross-claim was transferred to the District Court. On 27 August 2019, the primary judge (Olsson SC DCJ) gave judgment in favour of Fatseas finding that the "only available inference" was that Spotlight had installed decorative grates and gauze in the box gutters on the roof of the premises, and that their placement constituted the breach of certain clauses of the lease and were a cause of the overflow of water which damaged the premises. On 13 December 2019 by agreement of the parties, the primary judge reduced the amount of the judgment in favour of Fatseas to $497,769.00. In a second judgment given on 27 February 2020, her Honour awarded pre-judgment interest from November 2015 under s 100 of the Civil Procedure Act 2005 (NSW).
Spotlight appealed against the whole of the principal judgment and Fatseas cross-appealed against the part of the second judgment relating to the award of pre-judgment interest. The principal issues before the Court were:
whether the primary judge erred in finding that the grates and gauze were installed by Spotlight or one of its contractors, sub-contractors or agents;
whether the primary judge erred in finding that Spotlight breached cl 5.1 (covenant to maintain and repair premises) and cl 10.5 (covenant to clean and clear gutters, downpipes and drains) of the lease;
on the cross-appeal; whether the primary judge erred in finding that the contractual entitlement to interest under cl 11.3 of the lease did not apply to that part of Fatseas' claim for damages or indemnity for loss of rent and outgoings of $208,921.98 from November 2007 to July 2008; and
whether the primary judge erred in the exercise of her discretion in awarding pre-judgment interest on the balance of the judgment sum under s 100 of the Civil Procedure Act only from November 2015 and not from June 2008.
Held, dismissing the appeal and the cross-appeal (per Gleeson JA; White JA and Emmett AJA agreeing)
As to issue (i):
The primary judge erred in finding that find the "only available inference" was that Spotlight or one of its contractors or sub-contractors or agents had installed the grates and gauze in the box gutters, because that stated the evidence too highly. It was open to the Court on appeal to review the evidence and make any finding that ought to have been made: at [37]. The reasonable inference to be drawn was that it was more probable that the grates and gauze were installed by Spotlight or one of its contractors or sub-contractors or agents, than the possibility they were installed by Fatseas: at [70].
Jackson v Lithgow City Council [2008] NSWCA 312 considered.
As to issue (ii):
Spotlight's failure to remove the grates and gauze answered the description of breach of cll 5.1 and 10.5. Spotlight failed to maintain and keep the premises in good and substantial repair, order and condition, and to clean and clear the gutters of rubbish and debris: at [80]. The primary judge's finding that Spotlight's failure to clean and clear the gutters of rubbish and debris was a cause of the water damage was sufficient for the purpose of causation of loss: at [87]-[88].
As to issue (iii):
The case as pleaded by Fatseas did not give rise to an entitlement to contractual interest under cl 11.3 of the lease for the loss of rent and outgoings from November 2007 to July 2008. The only pleaded claim was an unliquidated claim for damages and indemnity for loss and damage for breach of cll 5.1, 5.10 and 10.5 of the lease: at [97]. Such a claim for unliquidated damages did not answer the description of "moneys due … pursuant to the Lease" in cl 11.3: at [101].
Arnold v Forsythe [2012] NSWCA 18; and
Merritt Cairns Constructions Pty Ltd v Wulguru Pty Ltd [1995] QCA 273 considered.
As to issue (iv):
No House v The King error was shown in the exercise of the primary judge's discretion to award pre-judgment interest from November 2015. While delay is a relevant factor to take into account when determining whether or not to award interest, no submission was made by Fatseas below as to the absence of detriment suffered by Spotlight as a result of delay. That the Court was deprived of the primary judge's discretionary judgment addressing this point had it been raised, and Spotlight could have responded to it by adducing new evidence, were sufficient grounds to preclude Fatseas from raising a new argument on appeal: at [104]-[111].
Simonius Vischer v Holt & Thompson (1979) 2 NSLWR 322;
Consolidated Lawyers Pty Ltd v Abu Mahmoud [2016] NSWCA 4;
Suttor v Gundowda (1950) 81 CLR 418;
Coulton v Holcombe (1986) 162 CLR 1; and
Water Board v Moustakas (1988) 180 CLR 491 considered.