Water Management Plan (WMP)
63Part 3A of the EPA Act sets out a process to occur and for the material prepared pursuant to that process to be the subject of consideration, unlike an assessment under s79C in Part 4, which enumerates a list of mandatory matters of consideration.
64Once the project application is lodged and the project is classified as a major project under Part 3A, the Director-General prepares environmental assessment requirements (DGRs), pursuant to s75F(2) and consults relevant public authorities, having regard to the need for the requirements to assess any key issues raised by those public authorities, pursuant to s75F(4).
65The Sydney Catchment Authority's (SCA) letter, dated 24.9.10, to the DoPI in response to a request from the DoPI for input regarding key issues to assist in the preparation of the DGRs (Exhibit K, Folios 78 - 80) included the following advice:
As the project has been classified a Major Project to be assessed and determined under Part 3A of the Environmental Planning and Assessment Act, it is not formally subject to the requirements of the Drinking Water Catchments Regional Environmental Plan No 1. Nevertheless, the SCA considers water quality issues should be comprehensively considered in the assessment process and that this planning instrument establishes appropriate assessment criteria. The SCA considers that the environmental assessment of the project should include an assessment of whether the project will have a 'neutral or beneficial effect on water quality'.
The EA should include a framework for the mitigation, management and monitoring of water quality impacts during operation and closure activities.
The EA should include management measures including existing and/or proposed for avoidance, minimisation, mitigation, remediation and offset measures.
The EA should assess the cumulative environmental impacts of all components of the project. This assessment should consider the impacts that have arisen from previous mining activities in the locality.
Monitoring
The EA should include a minimum of 2 years of baseline data - as specified in the Impacts of Underground Coal Mining on Natural Features in the Southern Coalfields: Strategic Review.
The EA should detail the proposed monitoring program - both pre-mining and ongoing. The program should nominate triggers for different levels of impacts.
66The DGRs for the proposal, issued 8.8.10 (Exhibit N, Volume 1, Appendix A), required the following to be addressed by the Environmental Assessment (EA) in relation to surface and groundwater:
The Environmental Assessment of the proposal must include:
• A detailed assessment of the key issues specified below, and any other significant issues identified in the risk assessment which includes:
- a description of the existing environment, using sufficient baseline data;
- an assessment of the potential impacts of the project, including any cumulative impacts, taking into consideration any relevant guidelines, policies, plans and statutory provisions (see below [refers to a list of planning instruments and policies, see Exhibit N, Volume 1, Appendix A]); and
- a description of the measures that would be implemented to avoid, minimise and if necessary, offset the potential impacts of the project, including detailed contingency plans for managing any significant risks to the environment;
• Groundwater and surface water - including:
- an assessment of the potential impacts of the project on the quantity and quality of the surface and groundwater resources in the project area, including an explanation of site water balance and groundwater drawdown;
- an assessment of the potential impacts of mine water discharge on the Wingecarribee River and its tributaries, paying particular attention to downstream uses of the water;
- a description of the measures that would be implemented to prevent adverse impacts on the Wingecarribee River and its tributaries; and
- a detailed description of surface water management at the pit-top and Loch Catherine;
67The DGRs for the proposal included a requirement for the proponent to consult with the SCA and that the consultation process and issues raised be described in the EA.
68The EA (Exhibit N) included, at Appendix D, a Groundwater Study prepared by Australian Groundwater and Environmental Consultants Pty Ltd (AGE report). The experts agree that there is a lack of data in the AGE report to support an assessment of the impacts of the proposal.
69The Director-General's Environmental Assessment Report (the report) recommended approval of the proposal, subject to conditions. The report included the following in regard to the AGE report and impacts on groundwater (Exhibit K, Folio 454):
Boral argues that Berrima Colliery has been in existence and operation for over 85 years, and as such, it is reasonable to assume that groundwater hydrology is approaching steady-state conditions. That is, the zone of depressurisation around the existing mine workings is likely to have reached close to its maximum extent. Boral also argues that the continuation of mining operations would not significantly increase the total exposed coal seam face (relative to the existing extensive workings) and as a consequence, it is unlikely to significantly increase groundwater infiltration rates. This assertion is supported by the calculations of predicted groundwater inflows to the mine, which indicate roughly a 10% increase over the life of the project, to 3.1ML/day.
While the Department accepts that Boral's groundwater assumptions hold merit, the absence of actual monitoring data to calibrate and confirm these assumptions means that Boral's position cannot yet be confirmed. However, the Department also considers that the risk to groundwater hydrology as a result of continued operations is likely to be both low and manageable. The Department accepts that groundwater depressurisation is likely to have approached its maximum extent as a result of historical mining operations, and continued operations are unlikely to significantly increase this. Coal extraction would not move any closer to the more sensitive area, including those along the Wingecarribee River. Any additional depressurisation effects are likely to expand to the north and west, away from the river. Further, the timeframes for mining allow for additional groundwater monitoring to be undertaken during the early stages of the project and for that monitoring data to be applied (if warranted) to an adaptive management approach.
The submission made by NOW to Boral's Response to Submissions generally endorses the need for additional monitoring data to inform an adaptive management approach. The proposed monitoring program is aimed at confirming groundwater conditions in the area, and any potential connection between groundwater aquifers and surface water. NOW has recommended that this monitoring be undertaken and completed prior to the project being permitted to extract more than 220,000 tpa. While the Department appreciates NOW's desire to place a trigger on the need to undertake groundwater monitoring, it considers that a time-based trigger is more appropriate than an extraction rate limit.
70The report included the following in regard to impacts on surface water (Exhibit K, Folio 455):
Boral proposed to continue discharge of groundwater to the Wingecarribee River subject to the requirements of its EPL. Despite this being current practice, OEH, NOW and SCA have raised concerns about potential water quality and hydrological impacts and have suggested that more detailed characterisation of discharge water and water quality in the Wingecarribee River is required. While the Department accepts the agencies' position that a continuation of current performance does not necessarily imply that the highest-achievable environmental outcomes are being attained, it still considers ongoing discharge of mine water to be low risk, given the monitoring data presented in the EA and the fact that discharges have been occurring for many years. The Department does, however, consider it appropriate to accept recommendations made by the agencies that Boral develop a more comprehensive water quality monitoring program and that data from such a program is then used to establish a broader suite of water quality objectives for the project.
71The PAC project approval 10_0172 imposed environmental performance conditions on the consent, at schedule 3 of the conditions. The environmental performance measures included requiring a WMP to be prepared (condition 31), to include a Site Water Management Plan, a Surface Water Management Plan and a Groundwater Management Plan. The WMP was to be prepared and implemented to the satisfaction of the Director-General and was to be reviewed, audited and revised regularly.
72The PACs determination report included the following relevant statements under 'Ground and Surface Water Impacts' (Exhibit L, Folio 918):
The lack of appropriate data, on which to make a proper assessment of water impacts is raised in government agency, local government and public submissions alike. The Proponent also acknowledged to the Commission that the data were inadequate.
This situation appears to arise from reliance on the long history of a mine with no obvious serious incidents and a level of operational and regulatory complacency that is out of step with current requirements. It means that the Commission is again faced with a decision as to whether to delay or refuse a Project until the required data are available for consideration, or construct an approval framework that will ensure collection of the required data, proper assessment of the options and retro-fitting of any actions required into the approval.
Given the long history of this mine and its small size, the Commission is prepared in this instance to adopt the approach of constructing an approval framework that will ensure collection of the required data, proper assessment of the options and retro-fitting of any actions required into the approval. However, the Commission considers this to be poor practice and that its acceptability is likely to come under increasing scrutiny in the future.
The Commission considers that the amended conditions establish an appropriate management approach for assessing and monitoring surface water and groundwater impacts. The conditions will also drive continuous improvement of water quality over time.
73The preparation of a management plan as a condition of consent should not be a panacea to overcome the necessity to consider a requisite matter, as the consent authority has an obligation to consider and determine all relevant matters, as required by the DGRs for a Part 3A major project. Priestley JA held in Mison & Anor v Randwick Municipal Council & Anor (1991) 23 NSWLR 734 (page 737 par C) the following:
'if the effect of an imposed condition is to leave open the possibility that development carried out in accordance with the consent and condition will be significantly different from the development for which the application was made, then again, it seems to me that the Council has not granted consent to the application made.'
74In relation to surface and groundwater issues of this proposal, the DGRs required an assessment of the potential impacts of the project on the quantity and quality of the surface and groundwater resources in the project area, an assessment of the potential impacts of mine water discharge on the Wingecarribee River and a description of the measures that would be implemented to prevent adverse impacts on the Wingecarribee River.
75When the requested data was not provided in the EA, the response of the DoPI in its report, quoted above, was to acknowledge that there was an absence of actual monitoring data to calibrate and confirm Boral's assumptions, however despite this and on the assumption that the risk to groundwater hydrology as a result of continued operations was likely to be both low and manageable, they recommended approval of the proposal with a condition imposed on the consent requiring the preparation of a WMP, to address the absence of monitoring data.
76The requirement for the preparation of the WMP as a condition of the consent left major and fundamental issues undetermined in respect of the impact of the proposal, which essentially deferred consideration of a matter that the consent authority was required to consider and determine, in accordance with the DGRs.
77In our opinion and based on the evidence before us, the surface and groundwater issues are major and fundamental issues in regard to this proposal and they cannot be left for later resolution, as consideration of the impacts and the means of controlling those impacts is important, when weighing up all relevant matters for consideration in determining this proposal. The condition in the PAC consent, requiring the preparation of the WMP, left open the possibility that development carried out in accordance with that consent and conditions may have been significantly different from the development for which the application was made.
78We have in evidence before us the WMP dated 11 January 2013 (Exhibit L), prepared in response to Condition 31 of Project Approval 10_0172. Much discussion occurred during the proceedings as to the status and adequacy of this document. The WMP includes the following qualification regarding its draft status (at 1.1):
The Scoping Document highlighted the progressive nature of the studies required by both the Project Approval and licence PRP which will result in further updates to this plan as required.
79There is a lack of detailed information about the nature and extent of past impacts from the operation of the mine in relation to groundwater, the SGDE and the riverine ecosystem, as the colliery has not previously been the subject of an assessment under the provisions of the EPA Act and the past regulatory system was less extensive. Since the approval of the proposal, there has been a considerable increase in the data available to inform the assessment, but nevertheless a key question remains as to whether there is adequate information now available to permit an assessment and the granting of approval.
80If we are not satisfied that we have adequate information with which to determine the major and fundamental issues of groundwater and river water quality associated with this proposal, then we are unable to grant consent.