Lincoln
31 On 27 May 2016, Lincoln entered into a contract with Rimfire Constructions (Qld) Pty Ltd, a company related to CRCG, for the design and construction of a residential high rise apartment complex called "Lincoln on the Park" located at 48-54 Lincoln Street, Greenslopes in Brisbane (the Lincoln contract).
32 On 13 March 2017, the Lincoln contract was novated to CRCG and thereafter CRCG took over the role of contractor. As required by the novated Lincoln contract, on 10 April 2017, CRCG provided two bank guarantees to Lincoln totalling $2,150,000.
33 In the meantime, CRCG, and, before it, Rimfire Constructions, proceeded with the constructions of the Lincoln on the Park Project. As mentioned earlier, in early June 2017, Mr Thornton became aware that some of the subcontractors on that Project were not being paid (see at [16]) above. The primary concern at that time was to ensure that the construction works on the Lincoln on the Project were completed. That concern was reflected in the following passages in the email Mr Petrie sent to Mr Li and Mr Zhao on 13 June 2017 (see at [17] above)
Lincoln on the Park
o Murray advised that with Progress Claim 14 unless confirmation is given on payment of debt before payment due date, Devcorp will hold money to pay subcontractors directly
o Minter Ellison has advised CRCG that they are not obligated for the outstanding debt from [Rimfire Constructions]
o Adam [Moore] has shares and Adam [Moore] has proposed to sell shares to pay subcontractors, however, legal advice is that cannot be done
o CRCG priority is to keep site ongoing to finish on time
o CRCG board members have not approved to pay out the debts owed to the creditors
o CRCG (Alex [Mr Li] and Charlie [Mr Zhao]) advised that they will tomorrow start communication with creditors
o Charlie [Mr Zhao] advised that the plan is for CRCG to not pay the outstanding debts but speak to all of the creditors face to face
o Murray advised he believes [Rimfire Constructions] has deadline of June 22 for voluntary administration and so resolution of the creditors needs to happen immediately
Lincoln on the Park Action Items
1. CRCG to provide tomorrow signed letter advising of the General Manager position and also the action CRCG will take to ensure the Lincoln project will continue unaffected
2. CRCG to provide tomorrow written resolution nominating Charlie [Mr Zhao] as the General Manager
3. CRCG to provide tomorrow revised organisation chart nominated Charlie [Mr Zhao] as General Manager/Director
4. CRCG to provide tomorrow [CRCG] aged creditors report for the Lincoln project
(Bold and underlining in original)
34 On 24 August 2017, CRCG served a Notice of Anticipated Practical Completion of the Lincoln on the Park Project. In response, Mr Thornton, as Managing Director of Lincoln, sent a letter dated 4 September 2017 to Mr Kirkwood as CRCG's Contractor's Representative notifying him that "in accordance with clause 44.6(b) the Principal's Representative will be inspecting Site 8am Tue 5 Sep 2017 to further inspect the works, to which the Contractor's Representative is requested to attend" (underlining in original). It appears from Mr Thornton's letter that the process of attending to defects in the building had commenced by agreement between the parties with onsite inspections from 29 June 2017. This puts in context the following paragraph of the letter:
Please be advised the defect reports issued to date & moving forward will continue to be considered Punchlists for the specific areas inspected. To date, the majority of items within the Units being inspected are minor in nature, however the items below are considered Punchlist A items that are required to be completed prior to Practical Completion on or before 5 October 2017.
(Underlining in original)
35 Under the heading "Punchlist A items - as at 4 Sep 2017 (all previously raised under separate cover)" (bold in original), the letter went on to list the following eight items:
- Eastern façade rectification (re; jointing, render, workmanship, windows)
- Automatic irrigation installation to all garden beds
- Basement storage cages installation
- Roof Top Pergola - workmanship, finishing & sagging issues
- Roof Top Pool - sharp step edges, compliance & safety concerns
- Kitchen sink scratches requiring rectification or sink replacement
- Unit 102 - Rectification of exposed plumbing drain through façade of building
- Lift - Compliance re weather protection (warranties, longevity, maintenance)
36 On 19 October 2017, CRCG made a formal request that a Certificate of Practical Completion be issued for the Project. In response, on 24 October 2017, Mr Thornton, as Principal's Representative and Managing Director of Lincoln, sent a letter to Mr Kirkwood which stated, in part:
…
In accordance with clause 44.6(c)(ii) of the Contract, the Principal's Representative advises that Practical Completion has not been achieved in accordance with the requirements of the Contract.
Accordingly, the Principal's Representative gives the Contractor a Punchlist identifying the Punchlist A Items that must be completed and Punchlist B Items that the Principal's Representative considers require rectification or completion by the Contractor (see Annexure [A] for Punchlist A Items and Punchlist B Items).
The Principal's Representative further advises that Practical Completion has not been achieved for the following reasons:
1 all Units are not fully complete with no defects remaining to be rectified which could in any way affect the ability of the Principal to complete the Sales Contracts;
2 the Contractor has not complied with clause 36 of the Contract;
3 the Contractor has not provided to the Principal all Completion Documents which, in the opinion of the Principal's Representative, are essential for the immediate use, operation, occupation and maintenance of the Works (see Annexure B for outstanding Completion Documents), and
4 all rubbish, debris, wrappings, containers and residual materials resulting from the Works have not been removed from the Site;
Further, the Principal's Representative refers to its Notice - Defects Inspection & Punchlist - Clause 44.6(b) dated 4 September 2017 which sets out a number of Punchlist A Items which required rectification by the Contractor and which remain outstanding.
Punchlist A items (all previously raised under separate cover):
- Eastern façade rectification (re; jointing, render, workmanship, windows)
- Automatic irrigation installation to all garden beds
- Basement storage cages installation
- Roof Top Pergola - workmanship, finishing & sagging issues
- Roof Top Pool - sharp step edges, compliance & safety concerns
- Lift - Compliance re weather protection (warranties, longevity, maintenance)
In accordance with clause 44.6(d), the Contactor is required to rectify all Punchlist A items and complete all outstanding works detailed in this letter for the purposes of achieving Practical Completion under the Contract.
Terms capitalised but not otherwise defined in this letter have the same meaning as set out in the Contract.
The Principal reserves all its rights under the Contract and at law.
…
It is to be noted that the list of Punchlist A items above does not include the sixth (kitchen sink) and seventh (unit 102) items in the similar list in the 4 September 2017 letter above at [35].
37 Attached to this letter at Annexure A was a document headed "Punchlist A items & Punchlist B items" (bold in original) as follows:
Notes:
- Attached documents are noted as 'A' or 'B' to reflect the above Punch list category
- Punchlist A items are reasonably requested for completion by 14 Nov 2017
- Punch list B items are reasonably requested for completion by 28 Nov 2017
- In addition to the attached Punchlist items;
o the Landscaping has significant areas in poor condition, dying &/or in need of immediate maintenance. Given the living nature of this item, immediate repair is required by 31 Oct 2017 to avoid replacement of large areas of the Works.
…
38 There followed two reports by Better Building Group Qld Pty Ltd (BBG) - one prepared on 5 October 2017 listing 203 items and the other prepared on 19 October 2017 listing 250 items. The top of each of those reports contained the handwritten notation "A - Entire report Punchlist A due to the volume of defects impacting occupation". As well, there were attached an email dated 15 October 2017 and several lists variously dated 25 August 2017, 15 September 2017, 5 October 2017, 9 October 2017, 15 October 2017 and 20 October 2017, some of which were marked "A" and others "B".
39 Notwithstanding the contents of the letter above, two days later, on 26 October 2017, Mr Thornton, as Principal's Representative and Managing Director of Lincoln, sent a letter to Mr Kirkwood notifying him that he had decided to issue the Certificate of Practical Completion as follows:
We refer to the following correspondence:
o letter from the Principal's Representative to the Contractor dated 4 September 2017 (ref Notice - Defects Inspection & Punchlist);
o letter from the Contractor to the Principal's Representative dated 19 October 2017 (ref Lincoln on the Park - Design and Construct Contract - Certificate of Practical Completion - Formal Request); and
o letter from the Principal's Representative to the Contractor dated 24 October 2017 (ref Certificate of Practical Completion - Rejection of Formal Request).
In accordance with clause 44.6(f)(i) of the Contract and notwithstanding that Practical Completion has not been achieved by the Contractor under the Contract, the Principal's Representative in its absolute discretion hereby issues to the Contractor the Certificate of Practical Completion. The Date of Practical Completion is 26 October 2017.
In accordance with clause 44.6(f)(i), the Principal's Representative advises the Contractor that there are a number of Defects (including Punchlist A Items) which the Con tractor is required to rectify. These Defects are set out in Annexure A and include the incomplete and defective works that were notified by the Principal's Representative to the Contractor on 24 October 2017 and 4 September 2017.
The Contractor is required to rectify the Defects within the corresponding time frames specified in Annexure A. In the event that the Contractor is either unwilling or unable to rectify the relevant Defects in the time required by this Certificate of Practical Completion, the Principal reserves all its rights under the Contract and at law, including its rights under clause 44.6(f)(i) to rectify such Defects itself and to reduce the Contract Sum by the cost of rectifying those Defects.
…
40 With one insignificant exception, the documents annexed to this letter were identical to those annexed to the 24 October 2017 letter above at [36]. The exception was that the notes at the beginning of the annexures included the six Punchlist A Items whereas they had been listed in the body of the earlier letter.
41 On 8 November 2017, Mr Wentao Gao of CRCG sent an email to Mr Mark Gaskin-Harris of Devcorp in which he agreed to undertake certain defects in the Lincoln on the Park building, but disputed CRCG's liability for others as follows:
…
Please find attached an update on our internal tracking sheet for internal defects in the apartments and lobbies. Please also find attached our Basement defect tracking sheet. As mentioned yesterday we are working to close out any defects outstanding (that we do not dispute). We are also working through the basement defects provided by BBG and will notify of any defects we dispute In the coming days.
We have sufficient site resources to manage the defects that are not in dispute. We currently have 1 site manager , 1 foreman, 1 site engineer, 1 administrator and any required labour to complete defects not in dispute.
In response to the Defects raised in the Practical Completion dated the 26 October 2017 we dispute pursuant to clause 56.1. Consider this correspondence a Notice of Dispute.
In reference to the alleged Defects in your correspondence of the of the 24 October 2017 - "Certificate of Practical Completion - Rejection of Formal Request".
We have marked up your correspondence with paragraph numbers "Mark-up of Correspondence dated 24 October" and provide the following details as to why we dispute these Defects:
Para 3 - Refer items 16 to 19 below which relates to the Principal's Annexure A;
Para 4 - We dispute this statement - we have closed out all 3rd party defects by A Plus Property Inspections as at the 24 October 2017 which are representing the Principal for defect inspections of the
Internals of each unit as documented at this date other than minor items that are contained in the attached Outstanding Defects - Lincoln on the Park tracking register. We note that 26 units have settled successfully on the 27 October 2017. These
items are not affecting the ability for the Principal to settle units. Further have settled since this date;
Para 5 - We dispute this statement - we have issued all warranties that we are reasonably aware via drop box, USB and hardcopy as at COB 25/10. (drop box link attached)
…
Para 6 - We dispute this statement - As per paragraph 5 above;
Para 7 - We dispute this statement - The Site was cleaned and all rubbish removed by 27th October 2017;
Para 8 - Refer to our dispute of the item 9 to 14 below;
Para 9 - We dispute this statement - Eastern Façade is within tolerances and any rectification works are purely cosmetic and has no effect on the functionality of the building;
Para 10 - We dispute this statement - We previously responded via letter dated 11/9/17 disputing this item and have had no response to date;
Para 11 - We dispute this statement - We previously responded via letter dated 12/9/17 disputing this item and have had no response to date;
Para 12 - We dispute this statement - The Workmanship, Finishing & Sagging issues have now been rectified to within tolerances and have no effect on the functionality of the building;
Para 13 - We dispute this statement - We have form 16 and form 11 for the pool so it has been deemed safe and has been installed strictly in accordance with Devcorps design;
Para 14 - We dispute this statement - We have form 16 and form 11 for the Lift and the Lift contractor has inspected the final product and installation and the Lift contractor
Has provided all warranties;
Para 15 - We dispute this statement as per the reasons stated above and below;
Para 16 - These documents have never been provided nominated as punch list category 'A' or 'B'. Notwithstanding we have attended to any defects that
were provided in these documents that we consider are defective and have not disputed.
Para 17 - All Punchlist 'A' items that are not disputed above and below will be completed by this date;
Para 18 - All Punchlist 'B' items that are not disputed above and below will be completed by this date;
Para 19 - We dispute this statement - the Principal has taken over these works - refer attached email 26 September 2017.
In summary we dispute the statements as set out above we do class the items disputed as defects.
A copy of this Notice will be hand delivered to the Principal's Office.
(Errors and typography in original)
42 Four days after CRCG was placed into voluntary administration, Lincoln terminated the Lincoln contract by letter dated 20 November 2017 under cll 52.11(a)(v)(A) and 52.3(a)(vi), reserving its rights under cl 52.10. On the same day, Lincoln called on the bank guarantees mentioned earlier (at [32]) and subsequently received the sum of $2,150,000.
43 In lodging its Proofs of Debt in the administration, Lincoln followed the same pattern as that described for the other two projects above. Its original Proof of Debt was lodged on 24 November 2017. That was followed by two amended Proofs of Debt - one on 23 April 2018 and the other on 24 August 2018. Its original claim was for $4,016,201.55, particularised as follows:
44 In the period before Lincoln's first amended Proof of Debt was lodged, it obtained two assessments relating to the estimated costs of rectifying the defects in the Lincoln on the Park Project - one by Gleeds Australia (East) Pty Ltd (Gleeds) on 20 November 2017 and the other by BBG on 29 March and 4 April 2018. A later report was prepared by Mitchell Brandtman on 19 April 2020 estimating the value of the trade warranties that were not provided for the Project.
45 The first amended Proof of Debt on 23 April 2018 was in the sum of $2,627,116.44. This claim took into account the $2,150,000 that Lincoln had received from calling on the guarantees provided by CRCG, as the following letter from Macpherson Kelley to Clayton Utz of the same date explained:
Defects report claim: $1,276,721.00
In or about late August or early September 2017, as the scaffolding for the Lincoln on the Park building works was being removed, it became apparent that several critical defects were present in the Lincoln on the Park works. On 4 September 2017, Murray Thornton of Lincoln sent a letter to [CRCG] outlining these defects and calling for their immediate rectification. A copy of that letter is attached.
On 26 October 2017, in accordance with 44.6(f)(i) of the Lincoln Agreement, Lincoln:
(a) Issued [CRCG] with a certificate of practical completion (PC Certificate); and
(b) Notified the Company, by way of a comprehensive defect report compiled by [BBG] (BBG Report), of a large number of Punchlist A and B defective items present in the building.
A copy of the certificate of practical completion and the BBG Report is attached.
On 20 November 2017, on the basis of the BBG Report and a further inspection of the defects by [Gleeds], Lincoln received a preliminary defects rectification estimate from Gleeds (Gleeds Report). The Gleeds Report calculated the cost of rectification in respect of the defects identified in the works to be $1,276,721.00. A copy of the Gleeds Report is attached.
In the premises, Lincoln has a claim against [CRCG] for the cost of rectification of the defects identified in the BBG Report and the Gleeds report in the sum of $1,276.271.00 (Lincoln Defects).
Further defects: $1,295,260.00
Subsequent to the receipt of the Gleeds Report, the following further defects have been identified in the works:
1. Air Conditioning installation defects; and
2. Defective balcony tiling; and
3. Water ingress into fire stairs.
Please find attached:
1. A report from [BBG] … dated 29 March 2018 estimating that the cost to rectify the Air conditioning installation defects and defective balcony tiling amounts to $1,260,260.00 (excluding GST); and
2. A further report from BBG dated 4 April 2018 estimating that the cost to rectify the water ingress into the fire stairs amounts to $35,000.00 (excluding GST).
The total cost to rectify the above defects therefore amounts to $1,295,260.00.
Warranties: $2,205,135.44
Clause 44.8 of the Lincoln Agreement relevantly required that upon practical completion being reached, [CRCG] was to provide to Lincoln all Completion Documents, being "those operation and maintenance manuals, as built design documents, warranties and other documents described as such in the Principal's Project Requirements …" (emphasis added).
Clause 15.8 of the Principal's Project Requirements for Lincoln on the Park relevantly required that the Contractor provide to the Principal warranties for the works to be performed as set out in the below table.
Item Warranty period
Glazing Manufacturer's warranty
Roof sheeting 7 years workmanship, materials to manufacturer's warranty
Waterproofing 7 years workmanship, materials to manufacturer's warranty
Carpet Manufacturer's warranty
Landscaping 12 weeks maintenance, weeding and watering
Electrical 7 years workmanship, materials to manufacturer's warranty
Mechanical 7 years workmanship, materials to manufacturer's warranty
Fire systems 7 years workmanship, materials to manufacturer's warranty
Hydraulics 7 years workmanship, materials to manufacturer's warranty
Lift services 7 years workmanship, materials to manufacturer's warranty
12 months' maintenance included
Pool 7 years workmanship, materials to manufacturer's warranty
Other Manufacturer's warranty