Scozza v JIH Building Design Pty Ltd
[2023] NSWCATAP 172
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2023-06-19
Source
Original judgment source is linked above.
Judgment (12 paragraphs)
The application before the Tribunal
- It is appropriate to summarise the application before the Tribunal.
- By application filed 4 January 2023, the appellant sought an order that the respondent pay her $14,030.00, being reimbursement in respect of:
- the cost of the respondent's feasibility report, $1,925.00;
- the cost of the respondent's concept drawings, $2,530.00;
- the costs of an arborist report, $1,925.00;
- the costs of a surveyor's report, $1,650; and
- rental expenses, $6,000.00.
- The appellant said that she was entitled to those orders for the following reasons: After having engaged JIH Building Design to do a feasibility study on the block on 19/11/2021 JIH was further engaged to draw concept stage drawings and explore the possibility of council approval for a granny flat with a garage underneath. The decision to further invest in drawings and reports was based on Jason Harbs professional opinion that the desired approval would be likely and within budget. Further to this the process taken was decided upon for its ability to deliver a very prompt indication of the parameters of the build after having discussed with Jason our needs. On 06/07/2022 $2530.00 was transferred to JIH after having been advised this cost in response to an email on 29/06/2022 requesting "as per my conversation with Jason of last week could we please organise a pre concept design for the purpose of a pre DA meeting. It is for the granny flat with garage underneath" As advised by JIH the preparation of this matter required the engagement of other professionals to prepare accompanying reports. In organising and requesting these reports it was reiterated on numerous occasions that there was an urgency and time cost (rental cost) associated with this matter and it was my understanding that the professionals selected were engaged giving consideration to that performance outcome among others. These reports were organised and paid for before having to pursue JIH for progress on getting the matter to a pre DA meeting as originally planned noting that it had already been considerably delayed by this point. After considerable follow up the matter was scheduled for a pre DA meeting in late August. In the lead up to this I had attempted to clarify the procedure, the expectations of me at the meeting and if I would be required to participate in any way beyond spectating. This continued right up until one hour before the scheduled meeting as I had not had response from Jason Harb. It was eventually confirmed by Emily form JIH that I would not be required to do anything however I would be welcomed to ask questions. Upon attending the meeting I believe there were three individuals from council also in attendance. After some awkward 10 minutes or so of waiting for Jason Harb to attend it was decided that my "professional would not likely be attending and the matter was discussed between ourselves with me blindly asking questions with limited understanding of the process, requirements or otherwise. By conclusion of the meeting it was my understanding that reports, details and elements for consideration were missing from the submission. I am somewhat confident that the plan was submitted without the required garage and that there were some driveway and or parking issues that meant that the garage would never likely be approved and a bushfire requirement that meant the secondary dwelling would never likely be approved. I do not believe that JIH building design provided a service with due care and skill within a reasonable timeframe. As a result of these actions and advice I have incurred costs of $12105.00 for an exercise was futile. A breakdown of the claim is as follows: … (Typographical and other errors as in original)