Samimi v Seyedabadi; Seyedabadi v Samimi
[2013] NSWCA 279
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2013-08-26
Before
McColl JA, Coll JA
Source
Original judgment source is linked above.
Judgment (16 paragraphs)
Judgment 1McCOLL JA: On 4 March 2013 Coorey DCJ gave judgment in the District Court dismissing a claim by Ali Seyedabadi (the "owner") to recover damages for breach of contract, breach of statutory warranties and for negligence from Kamran Samimi (the "builder"): Seyedabadi v Samimi; Samimi v Seyedabadi (District Court of New South Wales, Coorey DCJ, 4 March 2013, unreported). The dispute arose in respect of the construction by the builder of a duplex at Naremburn on behalf of the owner (the "works") pursuant, originally, to a contract made in August 2002. The primary judge also dismissed the builder's cross-claim to recover from the owner $338,809.60 said to be due under a cost plus contract in respect of the building works. 2There are two applications before the Court. The first in point of time is the owner's notice of motion filed on 13 August 2013 seeking an extension of time in which to file and serve a notice of cross-appeal pursuant to Uniform Civil Procedure Rules ("UCPR") 51.17(2)(b)(ii). The second is the builder's notice of motion filed on 14 August 2013 seeking a freezing order in respect of the owner's assets pursuant to UCPR 25.14.
Background 3The relationship between the parties commenced with the execution of a fixed price contract pursuant to which the works were to be completed for $575,000. By August 2004 relations had deteriorated such that the builder left the site. 4The owner asserted at trial that the fixed price contract remained in force, that the builder's departure from the site constituted repudiation and that he was entitled to damages in respect of defective works, delay and the costs of retaining a second builder to complete the works. However the builder cross-claimed alleging that the fixed price contract was "cancelled" in November 2003 and that the parties agreed that the works would continue on a costs plus basis. He sought to recover sums he alleged were due, but unpaid, under that contract. 5The trial commenced on 25 November 2009 and lasted for 37 hearing days, including 10 days of legal argument and submissions. The liability judgement was given on 4 March 2013 on which occasion verdict and judgment was entered in favour of the builder on the owner's claim and the builder's cross claim was dismissed (the "liability judgment"). On 18 July 2013 the primary judge ordered the owner to pay ninety per cent of the costs of the proceedings (the "costs judgment"). I was not provided with a copy of the costs judgment, and, it appears from the owner's affidavit of 13 August 2013 that reasons for that judgment may not yet have been provided to the parties. 6The judgment is 125 pages long. Large sections of the parties' (particularly the builder's) submissions are reproduced. At times the debate before me proceeded as if the primary judge's recounting of the submissions indicated his Honour had accepted them. The nature of the present applications is such that I should not engage in a detailed analysis of the reasons, however his Honour's dispositive findings are, I may reasonably assume, those matters which appear under the heading to that effect at Red Book 113. On that assumption, his Honour's findings are, relevantly, as follows. 7First, the primary judge accepted the builder's contention that, in November 2003 the fixed price contract was superseded by a "costs plus" basis contract: Red 61, 116, 117, 123, 136-137, 183. His Honour described this issue as "the major dispute between the parties": Red 136. 8In reaching that conclusion, his Honour rejected the submission the owner advanced that the fixed price contract was not "cancelled" because milestone progress payments only consistent with its continuance were made. His Honour rejected that submission because he found (Red 115, 132) that the owner and the builder had conspired to deceive the owner's Bank by the builder issuing false invoices to "enable the [owner] to pretend to the bank that he needed money for a progress or stage payment". The builder gave evidence of that conspiracy under the protection of a certificate issued pursuant to s 128 of the Evidence Act 1995. 9Secondly, the primary judge rejected the owner's submission that the builder was not entitled to leave the site in August 2004. This appears to be because his Honour accepted the builder's submission that by that date, he had completed the work he had contracted to perform and the works remaining were what were called "finishing works" which the builder was not contractually obliged to complete: Red 116. 10Unsurprisingly in light of the conspiracy finding, the primary judge had "serious doubts" about the credibility of both parties: Red 116, 132. This led him to find that it was "impossible to know how many 'fake' invoices" the parties produced to deceive the Bank so that, in turn, it was "impossible to know the true financial position between the parties": Red 116. However, his Honour thought it unlikely the builder would have left the site in August 2004 if the owner had not owed him money and, on the basis that by that stage the parties were operating on a "costs plus" basis, he concluded he could not "say that the [builder] was not entitled to leave the site in August 2004": Red 117. 11Thirdly, the primary judge found that "there is no reason why the ... builder is liable to pay the [owner] any money if the parties were operating on a 'costs plus' basis only": Red 117. The precise basis of that conclusion is not, with respect, readily apparent to one unfamiliar with the interstices of the facts, issues and reasons. 12In another passage of his reasons dealing with the parties' credibility, the primary judge found that the owner "was prepared to resort to almost anything to achieve a result": Red 132. The builder did not fare much better. His Honour took into account in relation to his credibility, the conspiracy finding, the fact that the builder's claim escalated from "about $60,000" to "around $400,000" and, too, his concession in cross-examination "that he was prepared to say whatever he wanted to say 'even knowing that it wasn't true'": Red 134. His Honour also had "real doubt about the reliability of the [builder's] invoices" as there was almost nothing to connect them to work on the site and, too, the fact that some "appear[ed] five years after the commencement of the dispute": Red 134. 13Fourthly, the primary judge rejected the owner's case that he had overpaid the builder and, too, all claims the owner made for defective work as set out in a Scott Schedule: Red 139, 142 - 179, 184. 14Fifthly, the primary judge rejected the builder's cross-claim because of doubts about the reliability of the builder's invoices, a conclusion that it was tolerably apparent was connected to his Honour's lack of confidence in the builder's claim having regard to the fact that its quantum escalated from "about $60,000" to "around $400,000" (a finding the builder seeks to challenge on appeal): Red 180. His Honour accepted the owner's submission that there was "nothing in the items in the invoice itself [sic, as in original] that can be related to specific work on the site" (Red 180) and that when cross-examined "about invoices that he claimed that he had paid, [the builder] could not substantiate any of the items that he was taken to": Red 181. 15In a summary of his conclusions the primary judge reiterated that he could place no reliance on either parties' financial records, that, in any event, there were no written records relating to aspects of the dealings between the owner and the builder and, in relation to the owner's claim in relation to work undertaken by a second builder he engaged to complete the works, that there were no defective works and that the builder was not responsible for the costs of finishing works: Red 183 - 184. He gave judgment for the builder on the owner's claim and dismissed the cross-claim.