Did the defendant fail to comply with their health and safety duty by failing to take the steps particularised in [7] of the Summons? (Element 3)
- The prosecutor is required to demonstrate the particular measures that should have been taken to prevent the risk identified: Kirk at [37].
- In order to find the defendant guilty of the offence I must be satisfied beyond reasonable doubt that it failed to comply with its health and safety duty in that it failed to take one of the reasonably practicable steps set out in the particulars of breach in 7-(d) of the Summons.
- The likelihood of the pleaded risk occurring was high if the control measures were not adopted. The potential consequences were catastrophic in that an electric shock was likely to cause death or serious injury because the upper power lines were carrying 33Kv. WGA had actual knowledge of the risk and the control measures that were required to alleviate the risk including the need to isolate the power when work was required to be performed on the window ledge. Mr Hassan had been provided with that information in writing through the provision of the Code of Practice and the System Guide as well as being provided with clear and unequivocal instruction from qualified persons about the control measures that were required to be implemented to avoid the risk.
- I will now turn to each of the particulars of breach.
7(a) The defendant should have prevented Mr Cullen undertaking the work of measuring and then installing angles on the external part of the windows in the absence of the supply of electrical power to the high voltage overhead power lines being isolated or de-energised.
- On 9 May 2014 Mr Leishman informed Mr Hassan in an email that the power to the 33Kv power line would have to be isolated to allow the encroachment of the SADs indicated to be necessary to complete the work at the site.
- On 12 May 2014 Mr Leishman sent to Mr Hassan the System Guide. It provided that the most effective control measure was to isolate the power supply under an Electrical Permit.
- On 22 May 2014 Mr Hassan acknowledged to Mr Leishman and Inspector Newton that the power would have to be isolated before undertaking the work that Mr Cullen was required to perform.
- On 5 June 2014 Mr Leishman advised Mr Hassan that the power would be isolated on 21 and 22 June 2014 and Mr Hassan sought a permit from Council to perform work at the site on Sunday 22 June 2014.
- The isolation of the power was required to eliminate the risk of electric shock because any worker on the window ledge was encroaching on the SAD required by the high voltage of the upper power line.
- On 18 June 2014 Mr Hassan was informed by Mr Leishman that the power could not be isolated on the following weekend or for the foreseeable future, because the building had been constructed too close to the upper power lines to allow the power to be turned back on if was turned off.
- Particular (a) then required WGA to prevent Mr Cullen from undertaking work on the window ledge.
- In this case, stopping work on the window ledge was the only way to eliminate the risk. That could have been effected by either:
1. not asking Mr Cullen to do the work unless and until the power was isolated; or
2. directing Mr Cullen not to work on the window ledge unless the power was isolated.
- The fact that the power could not be isolated does not in my view affect the reasonably practicability of this measure. That circumstance arose because of WGA's actions in constructing the building too close to the 33Kv power lines. Mr Leishman continued to try to find a solution to the problem that WGA had created. WGA should have delayed the work until a solution was found.
- Cessation of work can be a reasonably practicable measure, and whether it is or not is a question of fact: John Holland Pty Ltd v Industrial Court of New South Wales [2010] NSWCA 338 at [114].
- Taking into account the extent of the risk and the fact that the isolation of the power was a way of eliminating the risk, I find that the cost to WGA was not grossly disproportionate to the risk.
- I am satisfied beyond reasonable doubt that the prosecution has established particular (a).
7(b) The defendant should have prevented Mr Cullen working on the external area that was near or in close proximity to or in the vicinity of the overhead power lines by enforcing a no go zone.
- The concept of a no go zone is referred to in the Code of Practice. It is defined as "the area around overhead power lines into which no part or a person… may encroach without the approval of the network operator". The definition of "person" includes hand tools, equipment or any other material held by a person. The relevant distances are set out in the Code of Practice and are based on the voltage of the power line.
- On 6 March 2014 Inspector Newton issued prohibition notices to WGA for working within 3m of the lower power lines.
- On 9 May 2014 Mr Leishman informed Mr Hassan in writing that the SADs for the 33Kv power lines were 3m for workers and materials.
- On 22 May 2014 Inspector Newton issued an Improvement Notice requiring the delineation of a physical exclusion zone. Inspector Newton identified the areas where tape and signage should be installed. Mr Hassan told Inspector Newton that he was going to the hardware store to buy barrier tape and signage and later that he had done so.
- Mr Hassan did not tell Mr Cullen that the scaffolding or the window ledge was a no go zone.
- The tape and signage required to delineate the no go zone were inexpensive and readily available from the hardware store. What Mr Hassan said Inspector Newton was indicative of that and that the delineation of a no go zone was reasonably practicable. The particular also required Mr Hassan to enforce that no go zone. This could have been done simply and cost effectively by verbal instruction and intermittent supervision.
- I am satisfied beyond reasonable doubt that the prosecution has established particular (b).
7(c) The defendant should have installed and maintained physical barriers, in particular barrier tape, to prevent access by Mr Cullen to the external area and/or to prevent anything being held by Mr Cullen coming near or in close proximity to or in the vicinity of the overhead power lines.
- Particular (c) is closely related to particular (b) it requires the installation of barrier tape to delineate the no go zone.
- I will not repeat the evidence recited in relation to particular (b). The provision of barrier tape was a simple and inexpensive measure that would have minimised the pleaded risk.
- I am satisfied beyond reasonable doubt that the prosecution has established particular (c).
7(d) The defendant should have installed and maintained signs at the premises warning that there was danger, to keep clear of or beware of overhead power lines and which prohibited work near or in close proximity to or in the vicinity of them.
- Particular (d) is also closely related to particulars (b) and (c) and I will not repeat the relevant evidence that I have set out.
- Mr Hassan accepted that he was required to install signage and he told Inspector Newton that he was going to do so and that he had in fact done so. The signage was not present on the day of the incident.
- The installation of signage was a simple and inexpensive measure that would have minimised the pleaded risk.
- I am satisfied beyond reasonable doubt that the prosecution have established particular (d).