Proposed reply evidence from Mr Senogles
15RSA has engaged Mr James Senogles, a civil engineer and construction consultant, to prepare a report in reply to that of Mr Griffith. Mr Senogles has sworn an affidavit saying that he needs to see the Documents to ascertain the chronology of manufacture and delivery of items fabricated off site and to assess the relationship between those activities to the on-site activities shown on VDM's construction program.
16RSA submits that Mr Senogles needs the Documents because Mr Griffith has expressly assumed that the cause of delay of each delayed event examined is one for which VDM is entitled to an extension of time. RSA submits that, because Mr Griffith has not identified all the documents that he examined in relation to delay events, it is not clear that Mr Griffith has examined all relevant delay events, and not just those delay events that favour VDM.
17RSA submits that without the Documents, it would not be able to test the assumptions made by, assess the methodology used by and challenge the opinions given by Mr Griffith.
18Mr Sonogles has stated that he would need "at least six weeks" from receipt of the Documents to complete his report.
19In cross-examination, Mr Senogles agreed that he could determine, from documents already available to him, when the key components arrived at the site and when they were installed.
20Mr Senogles said that the Documents sought would enable him to ascertain why there was delay in the arrival at the site of some components and gave the following evidence: -
"Q: Why do you need to know that to do your report?
A: Because in responding to the Hinds Blunden report which adopts a time impact method in his contemporaneous method of looking at delays, it looked at projected program forward not actual events. It looked at critical path, which is projected forward. That assessment is necessary to have a critical path program which covers all the work under the contract, not just on site works but off site works as well.
Q: Why to carry out that exercise do you need to know why the components arrived "late"?
A: Depending on whether the contemporaneous program of time impact analysis works. That would comprise a non-qualifying cause of delay which needs to be taken account of.
Q: Do you have any reason to suppose that the reason the components arrived was because of the actions or inactions of parties of this litigation, or something that happened with a third party, or don't you know?
A: I can't say why. I need the information to be able to assess that."
21Mr Hicks, who appeared for VDM, challenged Mr Senogles in relation to this evidence and put to him that he could determine whether there was any critical delay in respect of the Items from documents already to hand.
22Mr Senogles nonetheless maintained the position that he needed to see the Documents to formulate his response to Mr Griffith and said that the "programming task" he would undertake would be incomplete without the Documents.
23In my opinion, it is neither necessary, nor appropriate, for me to express any view about the correctness of Mr Senogles' contentions.
24I am satisfied that Mr Senogles genuinely holds the belief that the Documents are necessary for him to complete his report.
25In my opinion, that is sufficient to establish the relevance of the Documents and, in that sense, the necessity for their disclosure at this stage. It is necessary that the disclosure be made now so that RSA can serve this aspect of its evidence; such disclosure must thus be made before that evidence is served.