Summary of relevant history of the proceedings
- In the hearing before the Tribunal member, the OC had sought Work Orders against Roxy to rectify alleged defects in building work and a Money Order for $11,101.75 for reimbursement of money spent by the OC to repair defects.
- On 22 April 2024 the Senior Member found some of the work was defective and made a Money Order for $6,149. A timetable was set for the parties to formulate an agreed draft Work Order reflecting the Tribunal member's findings in relation to each defect. The parties did not comply with that order.
- Roxy appealed from the Tribunal member's findings in relation to some of the defects. In the appeal, Roxy sought the following orders:
1. To set aside Order 2(a) made by the Tribunal on 22 April 2024 (which was the Order for the parties to formulate an agreed draft Work Order to reflect his findings); and
2. To replace Order 2(a) with a Money Order and a direction that within 28 days of the Order (or such other time as the parties may agree or the Tribunal may allow) the parties formulate an agreed draft Money Order to reflect the finding made in the Reasons.
- I found:
1. There had been an error in the exercise of the discretion in s 48O and an error in the application of s 48MA of the Home Building Act 1989 (NSW) (the "HBA"). when determining whether a Work Order or a Money Order should be made.
2. Some written submissions made by Roxy had not been taken into account by the Tribunal when deciding whether the Work Order could be made jointly and severally against both Roxy and the builder who was the second respondent to the proceedings.
- The parties agreed that, if an error was found, the matter should be remitted to the Tribunal to be redetermined.
- On 16 September 2024 I made the following Orders:
1. The decision of the Tribunal in proceedings 2021/00371562, on 22 April 2024 is set aside.
2. The matter is remitted to the Tribunal to be determined according to law.
3. I do not limit the lodgement of new evidence which might be relied upon.