Roxy Pacific Killara Pty Ltd v The Owners - Strata Plan 10053
[2024] NSWCATAP 177
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2024-08-28
Source
Original judgment source is linked above.
Judgment (15 paragraphs)
REASONS FOR DECISION
- This Appeal relates to a residential apartment development of 43 units in two separate buildings in Killara, NSW.
- The Owners Corporation (OC) commenced proceedings in this Tribunal by filing a Home Building Application on 15 December 2021. That application joined Roxy Pacific Killara (Roxy) as the first Respondent and Southwest Builders Pty Ltd (Southwest) as the second Respondent. Roxy was the developer of the apartment complex and it engaged Southwest to build it.
- In its Application, the OC claimed there were defects in the construction of the buildings and relied on warranties and remedies provided by the Home Building Act 1989 (NSW) (HBA). The OC asked for: 1. Work Orders directing Roxy and Southwest to rectify or cause the rectification of a large number of defects in the work; and 2. A Money Order for damages of $11,101.75 for expenses incurred by the OC in maintaining or repairing defects in plumbing work and elevators.
- In its Reply to the claim, Roxy said, inter alia, that any defects had been caused by Southwest. As the statutory warranties were being enforced against Southwest, they could not also be enforced against Roxy. However, if Roxy was found liable, it claimed contribution and indemnity from Southwest, and, said that, as Roxy was not a licensed builder, a Money Order rather than a Work Order was the appropriate remedy.
- Southwest did not participate in the case management of the proceedings leading up to the hearing, nor did it appear at the three day hearing in May 2023.
- There were six volumes of evidence before the Senior Member. It included lay and expert evidence and 11 Joint Scott Schedules referrable to each field of expertise covering a large range of defects.
- The Senior Member's decision was delivered on 22 April 2024. He found some of the work was defective in breach of the statutory warranties contained in the HBA. The effect of the Orders he made were: 1. Roxy and Southwest were jointly and severally liable to pay the OC $6,149. 2. Within 28 days the parties were to: 1. Formulate an agreed draft Work Order to reflect his findings in a form which could be entered as an Order. 2. Identify any areas of disagreement or any omissions/errors in his Reasons other than the findings made on liability. 3. Notify the Tribunal if the parties agreed to the making of a Money Order in respect of any items in lieu of the Work Order. 4. Advise the Registry if a further hearing was required to deal with any aspect of the Orders. 1. Costs were reserved pending the completion of the above Orders.