Subjective factors
33According to the prosecutor the defendant entered a plea of guilty to the amended charge after the fifth directions hearing. According to the court file the matter was on for plea/directions before Staff J on 17 December 2009, 19 February 2010, 22 March 2010, 19 April 2010, 15 June 2010, 29 June 2010, 10 August 2010 and 31 August 2010. It was not until 15 September 2010 that the defendant entered a plea of guilty to the amended charge. The delay appears to have arisen in part because of the defendant's application to consider the High Court judgment in Kirk v Industrial Relations Commission; Kirk Group Holdings Pty Ltd v WorkCover Authority of New South Wales (Inspector Childs) [2010] HCA 1 (3 February 2010); 239 CLR 531. This was followed by investigations undertaken by the defendant and representations made by way of a letter to the prosecutor followed by further exchanges of correspondence between the parties. During this period, Staff J expressed some concern that a significant period of time had elapsed. His Honour emphasised the delay on at least three occasions and on 31 August 2010 he advised the parties that if an agreed position was not reached the Court would enter a plea of not guilty on the next occasion.
34The prosecutor contended, apparently based on the number of directions hearings in this matter, that the discount to be awarded to the defendant reflecting the utilitarian value of the plea should be less than 20 per cent. According to the defendant, it pleaded guilty to an amended charge that was significantly different from the original charge. The defendant also sought to place reliance on the fact that, "this case has never been set down for hearing". These matters according to the defendant would justify a discount for the utilitarian value of the plea of 20 per cent.
35The Court was not invited to undertake a comparison between the original charge and the amended charge to which the defendant ultimately entered a plea of guilty. The defendant did not attempt to identify any of the "differences" between the two charges.
36In R v Stambolis [2006] NSWCCA 56; (2006) 160 A.Crim.R 510, Howie J considered whether pleas of guilty could be characterised as early pleas justifying a discount of 25 per cent. In that case, there was a delay of eight months between the accused person's arrest and the entering of the plea of guilty. In the unreported judgment at [11], (the reported judgment contains a typographical error omitting the word "not" from the third last line), his Honour said:
Frankly I do not understand how on the established principles it could be determined that the pleas of guilty for the offences for which the respondent was sentenced were early pleas and that they justified a discount of 25 per cent. There is no utility in a plea of guilty that has not been forthcoming. If the accused is not prepared to plea guilty until the Crown takes some course, then so be it. But if by withholding the plea the offender achieved the result he wanted, I do not understand why he should receive further favourable treatment on the basis that the plea of guilty had utilitarian value when it did not. Rarely, if ever, will the reason why the accused has withheld the plea of guilty be a relevant matter in determining the utilitarian discount. Where it has been used as a bargaining tool in order to achieve a favourable outcome from the Crown in respect of some other charge, I do not understand that this circumstance can excuse the delay or provides a basis for asserting that the plea was made at the first reasonable opportunity.
37Given that there has been some delay before the plea of guilty was entered in this matter without an appropriate explanation, I assess the utilitarian value of the plea at 20 per cent.
38The prosecutor submitted that the defendant, through Mr Lean, had attempted to assert that one of its employees was responsible for the failure to replace or repair the corroded guard rail. This, according to the prosecutor, exhibited a lack of contrition. In support of the submission the prosecutor relied on two paragraphs from Mr Lean's affidavit ([42] and [43]) in which he deposed that the defendant relied upon its tradespeople for the assessment of the structural integrity of the handrails. This, of itself, however, does not indicate a lack of contrition on the part of the defendant. More particularly, it does not amount, in its terms, to an attempt by the defendant to deflect its statutory responsibilities to its employees. The defendant has admitted, by its plea of guilty, that it failed to provide necessary information, instruction and training to its employees on appropriate methods of inspecting or testing the structural integrity of the guard rails.
39On the issue of contrition, the defendant authorised Mr Lean to make the following statement on its behalf to the Court:
Perilya Broken Hill accepts that it failed to provide its employees including Mr Ian Battams with appropriate information, instruction and training for the inspection and testing of handrails.
This failure meant that Mr Battams was not in a position to properly assess the safety of his workplace on 23 Level.
Since Mr Battams incident Perilya Broken Hill has investigated best practice for the inspection and testing of handrails. Perilya Broken Hill identified that there was no defined testing equipment or methodology available. As a result Perilya Broken Hill has developed a process and equipment which delivers the requirements of the Australian Standards for the testing of handrails and stanchions. Perilya Broken Hill is in the process of sharing this learning.
Perilya Broken Hill deeply regrets its breach of the Occupational Health and Safety Act and the injuries sustained by Mr Battams as a result of this breach.
40The statement, which was unchallenged, meets with the requirements of s 21A(3)(i) of the Crimes (Sentencing Procedure) Act 1999 (CSPA). It is evidence of contrition expressed by the defendant and will be taken into account in mitigation of penalty.
41The defendant has a previous conviction and is disentitled therefore to leniency normally extended to an offender who is not adversely recorded.
42The defendant also co-operated with the authorities during the course of the investigation into the offence.
43After the incident, the defendant directed John Andrew Braes, its surface maintenance superintendent, to investigate and identify a system which would allow it to test guard rails in accordance with Australian Standard 1657-1992 Fixed platforms, walkways, stairways and ladders - Design construction and installation (the Standard). One reason for this, according to Mr Braes, was that the defendant's current methodology for the inspection and testing of guard rails (identified by him as "visual, aural and hitting") was inadequate because the degree of corrosion was not able to be determined if the corrosion was occurring from the inside.
44The defendant engaged Rosetta Stone Operations Pty Ltd, an engineering design firm, to design a handrail tester that would comply with the requirements of the Standard. Rosetta Stone drafted design drawings and the defendant commissioned Nejaim's Steel Supplies to manufacture a prototype frame. The defendant purchased hydraulic testing equipment and assembled it to the frame. Rosetta Stone was engaged to develop a chart which would allow operators to operate the handrail tester in accordance with the Standard. Shortly after, a pilot programme for the handrail tester was commenced for the defendant's surface operations. The programme ran for several months and test results were recorded and submitted to the defendant for review. A number of issues were identified during the period and various adjustments were made. Upon completion of the pilot programme, the handrail tester was introduced to the underground environment and two handrail testers are currently in use at the mine, both on the surface and underground. The following methodology is employed during the testing process:
(1) the location to be tested is identified and then each set of handrails (a set being the length of handrail between two stanchions) is numbered consecutively to assist recording of data;
(2) each stanchion is tested by applying a horizontal pressure equivalent to 550 Newtons of force for a duration of 60 seconds. If a deflection is recorded, the stanchion is replaced (AS 1657 does not provide a tolerance for deflection of stanchions);
(3) to test the set of handrails, the length of the handrail between the two stanchions is measured. The chart is then used to identify the appropriate pressure (force) that was required to be applied to the handrail both vertically and horizontally;
(4) a measurement is also taken of any pre-existing distance (deflection) from vertical in between the Handrail Tester and the handrail prior to the application of pressure, this is required to determine whether there is any deflection remaining after the test is conducted;
(5) the Handrail Tester is then used to apply the required pressure to the handrail and that pressure is held for 60 seconds, with the operator using a stopwatch to record the time;
(6) the pressure is then released and a new measurement is taken of the distance between the handrail and the Handrail Tester. Any difference between the original measurement and this measurement is recorded as "deflection". If the deflection is greater than the allowed amount according to the chart, the handrail is determined to be no longer compliant with AS 1657. The area is then bunted off, a work order is generated and the handrails are replaced.
45The defendant entered the handrail tester in the NSW Minerals Industry 2010 Regional Occupational Health and Safety Forum Innovations Awards and on 4 November 2010 it was named as the winner of the award for its device, called the Handrail and Stanchion Testing Device.
46This achievement illustrates the defendant's commitment and dedication to ensuring safety at the mine. It will be taken into account, together with the other subjective and objective factors in mitigation of penalty.
47The defendant also instituted a number of other post-incident improvements specifically to the plant on Level 23 which are designed to improve the environment and minimise the effects of the process water. The defendant's systems of underground communication has also been improved since the incident. The improvements are set out in Mr Lean's affidavit and will also be taken into account in mitigation of penalty.