Redline Contracting Pty Ltd v MCC Mining
[2012] FCA 1157
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2012-10-15
Before
Siopis J
Catchwords
- PRACTICE AND PROCEDURE - discovery - whether an order for "general discovery" required the parties to give discovery in accordance with the Peruvian Guano test.
Source
Original judgment source is linked above.
Catchwords
Judgment (3 paragraphs)
REASONS FOR JUDGMENT 1 This is an interlocutory application whereby the applicant, Redline Contracting Pty Ltd (Redline), seeks a number of programming orders. The application arises out of two related issues in respect of which the parties disagree.
the reply 2 The first issue arises from Redline's objection to MCC Mining (Western Australia) Pty Ltd (MCC Mining)'s reply to its defence to cross-claim. The background is as follows. 3 On 20 June 2012, the Court, as part of a number of directions made that day, ordered that by 20 July 2012, MCC Mining file and serve its reply to Redline's defence to cross-claim. MCC Mining did not comply with the order. Redline's solicitors complained in correspondence to MCC Mining's solicitors about MCC Mining's failure to comply with that order. Eventually, after Redline had relisted the matter to come back to the Court on 28 August 2012, to deal with MCC Mining's failure to comply with the Court's order, MCC Mining agreed to a consent order (which was made on 24 August 2012) whereby it was to file and serve its reply by 4 September 2012. 4 The reply which MCC Mining filed and served on 24 August 2012 comprised one sentence to the effect that it joined issue with every paragraph in the defence to the cross-claim, save insofar as any paragraph contained an admission. Senior counsel for Redline submitted that this approach to pleading was unacceptable because it was at odds with the modern approach of the Court which was to require the parties to identify what was truly in issue well before trial. 5 This Court has particularly in recent times, been astute to take steps to require that parties to litigation identify, at an early stage, those issues which are truly in issue between the parties, whether by way of the pleading process, or by some other means during the interlocutory stages. This approach is reflected in s 37N of the Federal Court of Australia Act 1976 (Cth) and also in the Practice Direction CM1 issued by the Chief Justice. The object of this approach is to see that, so far as is possible, litigation is conducted speedily and inexpensively; and also, by reducing interlocutory disputes and adjournments, to assist the Court in disposing of matters as efficiently as possible. 6 Mr Collins, counsel for MCC Mining, contended that Redline's criticism of the reply was not warranted. This was because, contended Mr Collins, it was always open to Redline to do nothing in response to the Court's order to file and serve a reply, and simply to rely on the implied joinder of issues provided for in r 16.11 of the Federal Court Rules 2011. I do not accept that contention. First, once the Court had ordered that MCC Mining was to file a reply by a certain date, then it should have complied with that order, or alternatively, sought an amendment to the order. Secondly, the complexities of the pleadings in this case would have rendered such a course of conduct inconsistent with the Court's approach to the early identification of issues referred to above. 7 The defence to the cross-claim to which MCC Mining replied comprised 75 paragraphs and pleaded a number of facts and matters which were within the knowledge of MCC Mining. In my view, MCC Mining's bare joinder of issues reply did not contribute to identifying what was truly in issue between the parties. Thus, for example, it is not apparent from its reply to paragraph 39 of Redline's defence to cross-claim, whether MCC Mining is putting in issue Redline's version as to the effect of the letter or as to the authority of the author to make the statement. 8 The submission by senior counsel for Redline is to be upheld. Not only did MCC Mining fail to comply with the Court's order to file and serve a reply to the defence of cross-claim by 20 July 2012, but when MCC Mining did finally file a reply, the pleading did not comply with the requirements of the Federal Court Act, the Rules and the Practice Direction. 9 Accordingly, I will strike out that pleading, but I will give MCC Mining an opportunity to file a further reply in due course.