In Australia this has been treated as settled law: see Masters v Cameron ; Godecke v Kirwan and Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd ." (References omitted).
35 In my view the present agreement was one that constituted more than an agreement to agree, in so far as it provided for the parties to enter into the formal building contract which was referred to in the tender and acceptance documents.
36 That contract was identified as the current form of Housing Industry Association Plain Language Building Contract and there was no suggestion that the parties had in contemplation further negotiations in relation to any of its terms. The tender was both comprehensive, and on its face, complete, in relation to the price, which was an inclusive price encompassing the preparation of plans and specifications, the submissions of plans to the relevant authorities, the procurement of a survey as well as of engineering designs and certificates, and the construction of a "Sovereign" home and garage with the variations and finishes that were specified in the tender documents. There was no allocation of costs between these items.
37 I consider the case to be one that, in relation to the construction aspect, fell within the second limb of Masters v Cameron, being one where the parties had agreed on all of the terms of their bargain and intended no departure from, or addition to, their terms, but had made the performance of the building work conditional upon execution of the formal HIA contract. In that regard it was of a similar nature to that which came before the Court of Appeal in Randwick City Council v Nancor Trading Co Pty Limited [2002] NSWCA 108.
38 If I am in error in that regard then, in my view, it fell, at least, in the so-called "fourth category" of the Masters v Cameron cases, in so far as the building phase was concerned. That category was conveniently described by Stein JA in Nancor Trading at para 37, thus:
"That is, that a legally binding preliminary agreement has been concluded but the parties expect to make a further agreement which, by consent, might include further terms. However, in the interim the parties are to be bound by what they have agreed. See Sinclair Scott & Co v Naughton , Baulkham Hills Private Hospital Pty Limited v G R Securities Pty Ltd . More recently see Handley JA in Brunninghausen v Glavanics , with whom Priestley JA and I agreed." (References omitted).
39 Upon either formulation, the agreement would have allowed for variations to be made and costed in accordance with the HIA Plain Language Contract in relation to any additional work that might have become necessary to construct the home in accordance with Council or Sydney Water requirements, or in accordance with any additional changes desired by the Doyles.
40 It was submitted by Provincial that as the contract constituted by the tender and acceptance documents did not conform to the requirements of the Home Building Act 1989, as set out in s 7, that this was a further indication that the parties did not, as at 20 July 1999, enter into a contract to do any residential building work. In that regard it pointed to the somewhat draconian provisions of s 10 which, in the absence of a s 7 compliant contract, would have prevented it from making any claim for damages, or from enforcing any other remedy in respect of any breach of the contract by the Doyles, although preserving its liability to them for any breach on its part, and would also have exposed it to prosecution (s 7A).
41 As I understand the submission, which was advanced in this respect, it was to the effect that such were the potential consequences for Provincial, that it should not be lightly inferred to have conveyed an objective intention to be bound immediately to a contract to build the relevant home, that was not compliant with the Act, particularly since the documents envisaged the subsequent execution of a formal contract that would comply.
42 I am not persuaded that this submission has any validity. The intention of the parties is, in my view, to be determined by reference to the documents which were proffered and signed. Upon their face the agreement included an obligation "to build" the relevant residential building, once the necessary approval and other requirements were satisfied, as well as an obligation to supply the preliminary services identified.
43 As I read the relevant legislation, which I have set out earlier, the jurisdiction of the Tribunal is not enlivened by, nor does it depend simply upon, the existence between the parties of a contract to construct a dwelling. Rather, for the Tribunal to have jurisdiction, there must be a claim which is of the kind referred to in s 84 that is a claim which arises from "a supply of building goods or services".
44 As I have also noted earlier, residential building work means, relevantly "any work involved in…the construction of a dwelling".
45 Since, it is by reference to the nature of the claim, and the services supplied that the question of jurisdiction is to be determined, rather than the nature of the contract between the parties, it is necessary to focus upon the precise basis of the claim which the Doyles brought. That claim was originally particularised in the following terms:
"The respondent caused the applicants significant distress and financial loss amounting to approximately $41,500.00 by:
1. Failing to meet the requirements of money paid by the applicants for the preparation of Council approved building plans;
2. Failing to exercise proper care in the preparation and submission of plans to Strathfield Council.
3. Failing to exercise proper care in their advice to the applicants concerning projected commencement dates;
4. Failing to exercise proper care and due diligence in responding to the Council's requirement.
The Applicant's loss was made up of:
1. $3000 paid to the respondent for Council approved plans;
2. Loss of rent caused by 3. above amounting to approximately $8,500;
3. Additional building costs cased by the GST of approx $30,000 caused by 2. and 4. above."
46 An amended claim was lodged, on 10 September 2001, in the following terms:
" APPLICANTS AMENDED CLAIM
1. The applicant entered a contract with the respondent to build a residence at 43 Bareena Street Strathfield, in June 1999. It was a term of the contract that the respondent would prepare plans and specifications for the Council and Sydney Water;
3. It was an implied term of the contract that the respondent would prepare the plans and specifications for the Council and Sydney Water in a competent manner, and within a reasonable time, and do all things necessary to have the plans approved by the Local Authority, within a reasonable time;
4. It was an express term of the contract that the Applicants would sign a further contract namely the Housing Industry Association edition eleven agreement, as soon as formal building approval was obtained from Council;
5. The respondent failed to prepare the plans and specifications in a competent manner, or within a reasonable time, or to do all things necessary to have the plans approved by the Local Authority within a reasonable time;
6. As a result, the Applicants terminated the building contract;
7. The applicants have suffered loss and damage as a result, and claim that there has been a complete failure of consideration under the contract, or alternatively claim damages for breach of the contract."
47 The particulars supplied of the financial loss included claims for: