© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2022] NSWCATCD 30
NCAT Consumer and Commercial
2022-11-10
Original judgment source is linked above.
REASONS FOR DECISION
The owner's case as stated in final written submissions
The contractor's case as stated in final written submissions
Was Mr Rosasqui a joint contracting party?
Did Mr Rosasqui have authority to act as agent for the contractor?
Some authorities
The agreements reached with the owner
Direct payments to subcontractors
Liquidated damages
Extensions of time
Has practical completion been achieved and if so, when?
Incomplete works
Reports
Determination of the claims.
Less amounts paid by the Owner for progress payments I to 4 $370,500.00 Amounts paid by Owner to subcontractors $207,471.38 Add back amounts reimbursed to Owner by Mr Rosasqui $64,749.26 Less Net amount paid direct to the Contractor's subcontractor $142,722.12 Less 10% margin on amounts paid directly to the Contractor's subcontractors $14,272.21 Add back further reimbursement received from Mr Rosasqui for the Contractor $10,000.00 Balance contract price $41,715.67 Date for commencement of Works 3 Dec 2018 Due date for completion of Works 1 July 2019 Date of practical completion 11 Jan 2021 Rate for liquidated damages per day $103.00 and $309.00 on and from 5.5.2020 0 557 days Total days for which liquidated damages is calculated 306 days @ $103 251 days @$309
EOTs allowed Nil Liquidated damages (refer to above) $109,077.00 Cost of report prepared by Russell Haddock Nil Cost for report prepared by Grahame McCulloch Nil Water meter connection $265.00 Modification to development consent $685.00 Subtotal $110,027.00 less $41,715.67 Total Amount found $68,311.33
Costs
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 21 March 2022
Project 4301 Pty Ltd
Buildcarp Constructions Pty Ltd
[1990] HCA 32
(1990) 170 CLR 146
(1973) 131 CLR 60
(1975) 133 CLR 72
(2004) 218 CLR 451
(1993) 32 NSWLR 50
(2013) 87 NSWLR 284