311 Mr De Grazia did not adequately prove that the 20.42 blocks originally purchased by him were retaining wall blocks and therefore complied with the structural note. He testified that this was the case and he is generally a witness of credit. Ms Olsson's submission stated that it was obviously a retaining wall block from the way it had been used (no further reasoning was provided). Mr Zakos' evidence did not assist Mr De Grazia's position (he testified a different block again, the 20.01, could be used). Ultimately, these points do not overcome the doubt raised by the combination of Mr Solomon's testimony and the Boral brochure produced by him which showed the 20.42 was not a retaining wall block. Admittedly, that brochure was itself not entirely satisfactory as a piece of evidence, since it was undated (but relevantly Ms Olsson did not object to its tender, or deal with the matter in re-examination). Mr De Grazia's submission has not been made out. Therefore, he cannot establish that Mr Solomon's instruction was a variation and claim costs that were said to result from it. Accordingly, it is unnecessary to deal with those issues.
Storage of lights
312 Mr De Grazia's claim is for approximately $200 that he testified he was charged by Tangen lights for storage of the lights. On his version of events, this cost arose because Mr Solomon instructed him to purchase the lights in May 2002 or perhaps earlier and this was several months before they were expected to be required (he said the lights were actually installed in late 2003). Mr De Grazia said that an invoice had been issued but he had misplaced it.
313 The defendants' position was that the delivery and secure storage of all provisional sum work formed part of the contract works (which Mr De Grazia was obliged to provide) because Clause 17.01 of the specification instructed the Builder to 'allow to take delivery of all items and securely store until required'. Furthermore, the defendants contended that the Architect's instruction to order the lights was given in September 2002 not March 2002 as alleged. The minutes record that the plaintiff had not ordered the lights as at 2 September 2002. No invoice has ever been produced to substantiate the Builder's claim. This item was not raised at all during the "Variation settlement meeting" on 20 June 2003.
Decision
314 Mr De Grazia's claim in relation to this item was not adequately proven, there being no documentary evidence to support his testimony. Notwithstanding the general findings regarding credit, this claim is rejected.
Kinking the downpipes
315 This claim related to work which Mr De Grazia had undertaken after discussions with Mr Solomon in relation to the downpipe on both houses. Mr De Grazia said he had initially warned Mr Solomon that it was fiddly work, would cost money and delay the pouring of the concrete slab for several days. Mr De Grazia had, after considering the matter, told Mr Solomon that the desired work on the downpipes could be done. Mr De Grazia said Mr Solomon then told him to undertake the work if he could do it successfully. The work was then undertaken.
316 Mr De Grazia testified to a range of costs that were said to result from this work. This included a site diary entry of two plumbers working for eight hours to kink the down pipes, for both houses, $260 worth of extra material, and additionally a range of structural work that resulted from these changes (which created another two days work for a boilermaker) T:124.40-125.2. Mr De Grazia further testified that no other work could be carried out during this period (it was dependent on the concrete slab being pored). Accordingly, his claim included a charge for the hiring of scaffolding that was already on site.
317 Mr Roberts' final submission was that the work relied upon by Mr De Grazia formed part of the contract works. He pointed out that the complete supply and fix of all downpipes formed part of the contract works as per clause 13.10 of the contract specification. Mr Roberts contended that the kinking in question was concealed stormwater plumbing work which formed part of the contract works and is a common building practice. Mr Roberts further submitted that to the extent that the plaintiff relied on an instruction about changes to the rooflines, no such instruction had been identified. He emphasised that this item was not raised at all during the "Variation settlement meeting" on 20 June 2003. Even though the plumbing was not complete by that date, it was contended that the cost of that trade ought to have been known. Furthermore, Mr Roberts submitted that no invoice to the Builder from the plumbing sub contractor (or any other sub contractor) has ever been produced to substantiate the Builder's claim.
Decision
318 Mr De Grazia's claim in relation to this item was not adequately proven, there being no documentary evidence besides the site diary - such as invoices - to support his testimony. Notwithstanding the general findings regarding credit, this claim is rejected.
Roof pitch
319 This claim related to work that Mr De Grazia testified was undertaken to make the pitch to the roof higher on its low point. It was undertaken after a conversation Mr De Grazia recounted where Mr Forbes said the roof pitch had to be altered from the drawings to maintain the head height above the stairs. To undertake this work Mr Forbes had to re-mark out the roof pitch (essentially sketch it out) and reorder two or three pieces of timber. Mr De Grazia testified that there was other work being undertaken at this point (mainly carpentry) and the effect of the remedial work had been that a crane booking had to be rescheduled. He further testified that the overall delay caused to the whole project was three to four days.
320 Mr Roberts' submission was that the roof pitch set-out adjustment occurred prior to any actual building work in the subject area. It was of a very minor degree and was resolved on the same day that the Architect received the pitching angle query from Mr Forbes. Mr Roberts submitted that Photos 65, 66, 70, 71, 74, 75, 76, 77 & 78 showed the roof framing in place by Saturday 3 August 2002. Mr Roberts further submitted that no additional materials (timbers, nails etc) were required due to this adjustment as it was an adjustment of documented timber members. Mr Roberts pointed out that by 20 June 2003 all roof carpentry was complete and the cost of that trade ought to have been known. This item was not raised at all during the "Variation settlement meeting" on 20 June 2003.
Decision
321 Under cross-examination, Mr Forbes, the site foreman who dealt directly with this issue, agreed with Mr Roberts proposition that an initial roof set-out was carried out, there was an issue that arose, Mr Forbes spoke to Mr Solomon and it was resolved on site, after which the building of the roof commenced T:591.1-8. Mr Forbes gave evidence in chief that the construction of the roof was delayed for at least a day and a half while this issue was dealt with T:510.50-511.2. This was broadly consistent with Mr Roberts' position that the issue was resolved on the same day that it arose. In contrast, Mr De Grazia gave evidence that this issue delayed the project for three to four days. Mr De Grazia testified that it was necessary to change a crane booking, but no other evidence was produced regarding this issue (Mr Forbes did not address it in his testimony). Having regard to all of the circumstances, the plaintiff is awarded delay costs of one day in relation to this issue.
Splay the balconies
322 Mr De Grazia testified that he built the balconies according to the drawings but they were subsequently changed when the angle of the roof pitch was changed. He further testified that these changes were undertaken upon instructions from Mr Solomon. Mr De Grazia testified that his claim reflected the costs and delays associated with undertaking these changes. He recounted a conversation where he told Mr Solomon this work would result in extra costs and Mr Solomon had said it would be cleaned up in a 'wash up' at the end of the job.
323 Mr Roberts submitted that this claim turned on the contractual requirement in clause 7.11 of the specification, that the Builder was required to consult with the Architect prior to construction of the splayed balconies: "method of fixing boards to frame must not pierce membrane. Discuss with Architect prior to construction." Mr Roberts contended that the method of weatherproofing the splayed balconies was discussed between Mr De Grazia and Mr Solomon and a proposal by Mr De Grazia was accepted Mr by Solomon (who confirmed this with a drawing and a memorandum).
324 In cross-examination Mr De Grazia conceded that he had the relevant details for the construction of the balustrades (which related to the balconies) by June or at least 7 August 2002. 403.40. Mr Roberts submitted photos 74 to 78 show that - despite this issue being resolved in June -the relevant work only commenced around mid November 2002. In cross-examination Mr De Grazia rejected this suggestion, contending that the balcony was built three times for different reasons.
325 Mr Roberts further submitted that by 20 June 2003 balconies 3 and 3A were complete and the cost of that trade ought to have been known. This item was not raised at all during the "Variation settlement meeting" on 20 June 2003.
Decision
326 Mr De Grazia's evidence of the balconies having to rebuilt - causing a variation and a delay cost - is broadly consistent with that of Mr Forbes' (who gave evidence of two carpenters having to work for one day to reframe the balcony T:513.10-27). Mr De Grazia testified that he had put this claim together by referring to timesheets and other work that was carried out. Mr Roberts' submissions in relation to this issue focused on the fact that Specification Clause 7.11 required the Builder to consult the Architect prior to construction of the splayed balconies and despite a discussion and alleged agreement between the parties in June 2002, photographs taken by Mr Solomon were said to show that the relevant work was only undertaken in around mid-November 2002 (and therefore was not critical). Due to the evidentiary problems with Mr Solomon's photographs, they cannot be accepted as evidence of the progress of the works at their purported dates (as Mr Roberts' attempted to use them). Without the photographs, this issue turns on findings of credit and accordingly Mr De Grazia's claim is accepted.
Deletion of pantry stack
327 Mr De Grazia testified that this claim related to work involving the lifting of a drainage stack by 15mm and lifting up the whole ceiling by 15mm. He further testified that Mr Solomon instructed him to do this work, and when the work was undertaken the plumbing was in place and the ceiling frame was in place, although the actual plasterboard was not. The work was performed by the plasterboard contractor and the plumber, and Mr De Grazia had calculated his claim based on timesheets and notes made at the time.
328 Mr Roberts basic position was that this item represented a deletion from the contract works. Mr De Grazia rejected this suggestion in cross-examination. Under cross-examination, Mr De Grazia maintained that he had received an overall variation from his plumber in relation to the project and he knew it included this item from a discussion with the plumber. Mr De Grazia conceded he did not have a document from the plumber, and had instead made an estimate of 30 hours work from his diary records. Mr Roberts suggested this was a variation that Mr De Grazia had compiled in 2005 which did not reflect what had happened on site. Mr De Grazia rejected this suggestion.
329 Mr Roberts further submitted that Mr Solomon's instruction occurred prior to any overhead plumbing work. Mr Roberts contended that by 20 June 2003 all concealed plumbing work in the kitchen and living areas was complete and the cost of that trade ought to have been known. This item was not raised at all during the "Variation settlement meeting" on 20 June 2003. No invoice from the plumbing sub contractor to the Builder has ever been produced to substantiate the Builder's claim. The Architect was entitled to reject the claim.
Decision
330 Mr De Grazia's claim in relation to this item was not adequately proven, with all of the documentary evidence relied upon generated by him or ASBS (he made his claim by referring to timesheets and notes made at the time). Notwithstanding the general findings regarding credit, this claim is rejected.
Louvres
331 Mr De Grazia testified that this claim related to work that had been done to accommodate the louvres which Mr Solomon decided not to proceed with (due to the price in the quote that Mr Solomon received for that item). Mr De Grazia further testified that various work had been done, including drilling, fixing channels in place to take the louvres, and electrical wiring had been provided. Mr De Grazia testified that once the decision not to proceed with louvres was taken the wiring had to be terminated, and some weatherboards where the wiring was penetrating had to be replaced.
332 Mr Roberts submitted that under specification clause 14.16 electrical installation of Aerobrise louvres was included in contract sum (that is, the electrical service is not included in the provisional sum for the louvres). Mr Roberts submitted that the plaintiff had said that a junction box was needed and that weatherboards needed to be replaced, and this evidence was not consistent with that of Mr Forbes. Mr Forbes testified that there was not very much work involved, saying that the wiring was already installed and all that was required was to cap off the wiring to make it safe T:525.210-28. Mr Roberts contended that the weatherboards had not been installed by the date of the instruction (contrary to Mr De Grazia's testimony).
Decision
333 There is a discrepancy between the evidence of Mr De Grazia regarding the significance of the work required to cap off the electrical wiring and that of Mr Forbes. Additionally, Mr De Grazia did not refer to any documentary evidence to substantiate this claim (the only documents relied upon were letters to Mr Solomon stating the claimed costs). Moreover, Mr De Grazia's 2005 claim in relation to this item was for three times the amount claimed in 2003, and there was no explanation of this difference (it may be that in 2005 Mr De Grazia had a better opportunity to calculate the claim). Mr De Grazia could have explained the actual costs of this claim by reference to timesheets or invoices for the trades and materials he stated in his 2005 letter were used. Mr De Grazia's claim in relation to this item is rejected.
Sunhoods
334 Mr De Grazia's claim for this item was based on two factors: firstly that there had been insufficient detail provided which had caused delay in having the sunhoods fabricated (and caused consequent delays on the whole project) and secondly that the sunhood Mr Solomon specified was more expensive than Mr De Grazia had allowed for. Mr De Grazia testified that he had been instructed by Mr Solomon to attend the Teachers Federation College (Mr Solomon wanted the type of sunhoods appearing on that building) however Mr De Grazia maintained that even after attending, he still required specifications from Mr Solomon.
335 Mr Roberts drew on Mr De Grazia's concession that he had for some time the documents provided to Hi-Light to obtain the quote, submitting Mr De Grazia could have got a quote much earlier from Hi-Light. Mr De Grazia further conceded that he could have got a quote and presented this to the Architect to confirm whether this was what Mr Solomon was after.
336 Mr Roberts noted that the Architect's memo of 27 November 2002 provided that the sunhoods were to remain as specified. In cross-examination, Mr De Grazia contended that the actual sunhoods installed were different, although he conceded it was entirely normal for Mr Solomon to have approved the actual sunhoods on shop drawings. Mr Roberts emphasised that some minor information concerning fixing height and location was provided to the Builder and they were installation issues rather than fabrication issues. Furthermore, Mr Zakos conceded that the sunhoods were fully specified.
Decision
337 Mr De Grazia's claim in examination in chief that he should be allowed a variation because the sunhood specified was more expensive than he had allowed for, is rejected because he did not provide any evidence of what this difference was (his letter to Mr Solomon claiming the sunhood variation did not mention this issue). Mr De Grazia's claim for the costs of having to attend the Teachers Federation College to understand the sunhood specification is allowed (it is relevant that Mr Roberts did not suggest this was unnecessary T:418.6-21). Mr De Grazia's claim for ten days delay costs to perform work related to the sunhoods is rejected since his concessions under cross-examination established that he could have acted differently and this may well have reduced any such delay T:415.42- 417.47.