Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd
[2016] NSWSC 770
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2016-05-03
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
Judgment
- HIS HONOUR: These proceedings are concerned with the validity of a determination made on 15 February 2016 (the Determination) by the second defendant, Mr Doron Rivlin (the Adjudicator), of an adjudication under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Security of Payment Act). The Determination was made following an application by the first defendant, Shade Systems Pty Ltd (Shade Systems), for adjudication of a payment claim served by Shade Systems on the plaintiff, Probuild Constructions (Aust) Pty Ltd (Probuild). The payment claim was made under an agreement entered into on 14 October 2014 between Probuild, as head contractor, and Shade Systems, as subcontractor, whereby Shade Systems agreed to supply and install external louvers to the façade of an apartment complex situated in Chatswood NSW (the Subcontract).
- By the Determination, the Adjudicator determined that Probuild owed the amount of $277,755.03 (including GST) to Shade Systems by way of progress payment under the Subcontract. The Adjudicator determined that the due date for payment was 12 February 2016 and that the rate of interest under s 101 of the Civil Procedure Act 2005 (NSW) applies. The Adjudicator also determined that Probuild must pay 100% of the adjudication fees.
- By summons filed in the Technology and Construction List on 29 February 2016, Probuild claimed an order under s 69 of the Supreme Court Act 1970 (NSW) (the Supreme Court Act) quashing the Determination. The primary basis upon which Probuild seeks relief is its contention that, in making the Determination, the Adjudicator committed jurisdictional error in that he denied Probuild procedural fairness. Alternatively, Probuild contends that the Determination involved an error of law on the face of the record, having regard to the basis on which the Adjudicator rejected Probuild's claim that it is entitled to liquidated damages from Shade Systems. Shade Systems does not accept that there was a denial of procedural fairness and says that, if there was, relief should be refused. Shade Systems also denies that there was an error of law and contends that, in any event, judicial review is not available for error of law on the face of the record. Before dealing with the issues in the proceedings, it is desirable to say something about the scheme of the Security of Payment Act