Penalty interest - cross appeal
53 Miller Street's second head of loss is the difference between the normal interest payable on the CBA loan and the default interest it had charged between 1 March 2005 and April 2006. It amounted to $190,396.02. The basis of the claim is that the liquidator had acted unreasonably in refusing to transfer the Trust property to Miller Street on or about 8 March, thus delaying the restructure of the loan. It is said that, had this delay not occurred, Miller Street would not have incurred the penalty interest. The primary judge disposed of this claim at [19] as follows:
Although the liquidator's delay in finalising the liquidation was both inordinate and inexcusable, it did not delay the restructure of the loans. Nor did the liquidator act unreasonably while negotiating the terms of the bank guarantee.
54 His Honour had earlier made the following findings of fact:
· in Mr Tayles' letter of 1 March 2005, in which he informed the liquidator of the change in trustee, he said that solicitors were preparing documentation for the transfer of the Trust property from Taycorp to Miller Street
· for practical reasons the liquidator could not transfer the Trust property: it was mortgaged to the CBA to secure loans totalling approximately $2.5 million, the winding up order was an event of default under the loans, so that the debts to the CBA were due and payable
· the CBA had agreed to restructure the facilities conditional on removal of the liquidator, provision of financial information about the borrowers, satisfactory valuations of the Trust property, and copies of the leases
· in these circumstances the liquidator could hardly give up the Trust property without seeing the CBA paid out
· it was not until about 18 August 2005 that the CBA decided to restructure the loans, and not until 26 August 2005 that it informed the liquidator that it consented to the transfer of the Trust property to Miller Street
· it was only at that point (ie 26 August) that the liquidator could consider a transfer of the Trust property
· on 15 September 2005 an order was made permitting Mr Tayles to execute transfers of the Trust property on behalf of Taycorp
· the order was made in anticipation of the provision by Miller Street of a bank guarantee in favour of the liquidator covering his costs and expenses and any liabilities of Taycorp
· in October and November 2005 there were negotiations between the liquidator and Mr Tayles about the terms of the bank guarantee
· on 13 December 2005 orders were made approving the transfer of the Trust property upon Miller Street undertaking to provide the liquidator with a bank guarantee of $225,000
· the bank guarantee was provided on 12 January 2006, but the transfers could still not be made because the CBA had not finalised the restructure of the loans
· it was not until May or June 2006 that the new facilities were in place and the transfers could be, and were, effected.
55 Although Miller Street disagreed with the primary judge's ultimate conclusion set out at [53], the above findings were not challenged.
56 Miller Street contends that the primary judge did not give any reasons for his conclusion that the liquidator's conduct did not delay the restructure of the loans. We do not agree. Although the passage from his Honour's reasons we have set out at [53] is brief, it is preceded by ten paragraphs from which we have taken the presently relevant factual findings. These findings provide the basis for the conclusion that the delay in the restructuring of the loans was not due to the liquidator's conduct.
57 Although Miller Street did not challenge the findings set out at [54] it contended that the evidence to which it drew our attention showed that it was the liquidator's refusal to transfer the Trust property which delayed the restructure of the loans. Although this will involve some repetition of matters already recorded, it is convenient to summarise that evidence:
(a) On 13 January 2005 the CBA wrote to Mr Tayles advising that it was "prepared to consider" an application by his companies to restructure the facilities. The offer was conditional on the removal of the liquidator, the provision of financial statements and fresh valuations of various properties. This letter was provided to the liquidator.
(b) On 8 March 2005 Mr Tayles' barrister proposed to the liquidator that the transfers be executed, with the liquidator retaining "a sufficient amount of trust receipts (say $100,000) to protect all creditors' claims".
(c) On 24 March 2005 the CBA informed Mr Tayles that it would not consider transferring Taycorp's trust debts to Miller Street until an updated valuation of various properties was completed, the liquidator confirmed that the assets and income of the Trust would be transferred to Miller Street, and current leases of the Trust property were provided.
(d) On 20 May 2005 updated valuations of the Trust property were provided: $1.9 million for each of the two levels.
(e) On 25 May 2005 the liquidator was provided with formal evidence that the Trust property had been acquired by Taycorp as trustee for the Trust.
(f) On 7 June 2005 Mr Tayles' barrister requested the liquidator to execute transfers immediately so as not to cause Miller Street further loss. (The liquidator declined to do so on the ground that Taycorp's indemnity depended on a release from Mr Tayles in respect of debts he had paid on its behalf.)
(g) On 6 July 2005 the CBA informed Mr Tayles that it was waiting for the liquidator to transfer the Trust property before it could complete Mr Tayles' application for a loan to Miller Street to repay the debt of Taycorp and another company.
(h) On 11 August 2005 the CBA told the liquidator that Mr Tayles had sought a restructure of the loans and that it was waiting for advice from the liquidator that title to the Trust property had been transferred to Miller Street.
(i) On 17 August 2005 Mr Tayles' barrister made a further request that the liquidator transfer the Trust property forthwith, and offered a charge "over the assets of the Tayles Discretionary Trust No 3 (including the 2 floors of the North Sydney building)" in favour of Taycorp and the liquidator, "to better secure the company's and the liquidator's right of indemnity" against the Trust's assets.
(j) On 18 August 2005 the CBA informed Mr Tayles' barrister that it consented to the transfer of the Trust property to Miller Street.
(k) On 24 August 2005 the liquidator informed Mr Tayles' barrister that he intended to seek directions from the Supreme Court of New South Wales as to whether he was obliged to transfer the Trust property.
(l) On 26 August 2005 the CBA informed the liquidator that it consented to the transfers to Miller Street.
(m) A CBA file note of 18 October 2005 of a meeting between its officers and Mr Tayles, his accountant and legal adviser records that:
· "the Court" had determined that Miller Street needed to provide a bank guarantee of $150,000 to the liquidator "so that his position was not diminished". The $150,000 was "to ensure there are sufficient funds to meet all the liquidator's costs"
· the CBA agreed to consider providing such a guarantee.
(n) On 10 January 2006 the CBA provided Taycorp with a bank guarantee for $225,000 pursuant to an order made by the primary judge on 13 December 2005 approving the execution by Mr Tayles of transfers of the Trust property to Miller Street.
58 In its written submissions Miller Street claimed that the liquidator acted unreasonably in refusing to transfer the Trust property on or about 8 March 2005. In oral submissions counsel proposed two alternative dates in June and August 2005.
59 In order to deal with Miller Street's submissions, we have reviewed the evidence to make up our own minds about the facts, nevertheless according proper weight to the primary judge's views. See Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd (2001) 117 FCR 424. Although there is some overlap between the facts found by the primary judge and those recorded at [57], Miller Street draws attention to some that were not referred to by his Honour. Our consideration of the whole of the evidence, and in particular Miller Street's additional facts, does not disclose error on the primary judge's part in concluding that the liquidator's refusal to execute the transfers by, or soon after, any of the dates propounded by Miller Street did not delay the restructure of the loans.
60 The file note referred to in 57, recording the proceedings at the meeting on 18 October 2005, deserves particular mention. On 16 October, two days before that meeting, the liquidator's solicitor informed Mr Tayles' barrister that he had prepared a brief for counsel to seek directions from the Supreme Court of New South Wales as to whether the liquidator was obliged to transfer the Trust property to Miller Street. He said the application would be filed "early next week", and the duty judge would be asked to deal with it as a matter of urgency. With this background, we have inferred that the order in 57 was made by the Supreme Court of New South Wales, which was the Court that appointed the liquidator. There is no order of this Court that fits the description given at the meeting by Mr Tayles' barrister. The only other Court that is at all likely to have been approached is the Supreme Court of Victoria, which is referred to in the letter of 16 October 2005 as the Court to which an application by Miller Street might be made. Nothing turns on whether the order was that of the New South Wales or the Victorian Court.
61 Although our attention was not drawn to a formal court order, the file note was of a meeting at which Mr Tayles, his accountant and barrister were present, the barrister reported that "they had been to Court" and described the order made, Miller Street's counsel relied on the file note before us, and did not suggest that any part of it was incorrect or unreliable. Accordingly we accept the summary of the Court order it contains. In our view it vindicates the liquidator's stand that he was entitled to the protection of the Court's directions, (whether the Supreme Court of New South Wales or the Supreme Court of Victoria), before being obliged to transfer the Trust property.
62 Once the position is reached that as at the end of August 2005 the liquidator was not, in a Supreme Court's view, required to transfer the Trust property without a bank guarantee, the claim that he was in default as at 8 March, June or August 2005 must fail. Thereafter, as the primary judge pointed out, there were negotiations about the terms of the bank guarantee (October and November 2005) which culminated in the order of 13 December 2005. That order approving the transfer upon Miller Street's undertaking to provide the liquidator with the protection of a bank guarantee is a further indication that he was not obliged at any earlier date to transfer the Trust property without such protection. The primary judge found that the liquidator did not act unreasonably while negotiating the terms of the guarantee. Miller Street has not attacked this finding. In any event, the provision of the bank guarantee in January 2006 was not the end of the story, because the Bank had not finalised the restructure of the loans. That did not happen until May or June 2006.
63 Miller Street's cross-appeal to recover the penalty interest must be dismissed.