© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWCA 46
Court of Appeal (NSW)
2016-11-01
Meagher JA, Ward JA, Payne JA
Original judgment source is linked above.
ey Municipal Council v Hall (1987) 62 LGRA 1 Pathold No 176 Pty Ltd v Minister for Transport Services [2005] NSWLEC 184 Penrith City Council v Waste Management Authority (1990) 71 LGRA 376 People for the Plains Incorporated v Santos NSW (Eastern) Pty Limited [2016] NSWLEC 93 Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355; [1998] HCA 28 R v Australian Broadcasting Tribunal; Ex parte Hardiman (1980) 144 CLR 13; [1980] HCA 13 Sweetwater Action Group Inc v Minister for Planning [2011] NSWLEC 106 Tasmanian Conservation Trust Inc v Minister for Resources and Gunns Ltd [No 2] (1996) 65 FCR 25; (1996) 90 LGERA 106 Taylor v The Owners-Strata Plan No 11564 (2014) 253 CLR 531; [2014] HCA 9 Warringah Shire Council v Raffles [1979] 2 NSWLR 299 Texts Cited: NSW Legislative Assembly, Parliamentary Debates (Hansard), 30 April 1991 Category: Principal judgment Parties: People for the Plains Incorporated (INC 130 14 43) (Appellant) Santos NSW (Eastern) Pty Ltd (ACN 009 321 662) (First Respondent) Santos NSW Pty Ltd (ACN 094 269 780) (Second Respondent) Secretary, NSW Department of Industry (Third Respondent) EnergyAustralia Narrabri Gas Pty Ltd (ACN 147 609 729 (Fourth Respondent) Representation: Counsel: B Walker SC with J Johnson (Appellant) N Williams SC with M Astill and Ms M Ellicott (1st, 2nd and 4th Respondents) R Lancaster SC with P Herzfeld (3rd Respondent)
Solicitors: Environmental Defender's Office Ltd (Appellant) Ashurst Australia (1st, 2nd and 4th Respondents) Crown Solicitor's Office (Third Respondent) File Number(s): 2016/00259819 Publication restriction: Nil Decision under appeal Court or tribunal: Land and Environment Court of NSW Jurisdiction: Class 4 Citation: [2016] NSWLEC 93 Date of Decision: 1 August 2016 Before: Moore J File Number(s): 2016/165360 and 2016/165660
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This Headnote is not to be read as part of the judgment] This judgment relates to an appeal from a decision in the NSW Land and Environment Court. The first, second and fourth respondents (the Santos parties) hold and/or operate three petroleum titles under the Petroleum (Onshore) Act 1991 (NSW) (the PO Act): an exploration licence (PEL 238), a production lease (PPL 3) and an assessment lease (PAL 2). PAL 2 and PPL 3 are over land within the boundaries of, but excised from, the area originally comprising PEL 238. The Santos parties conduct extensive integrated petroleum explorations operations upon this land. The Leewood Produced Water Treatment and Beneficial Reuse Project (the Leewood Project) is the second phase of a project relating to the management of water produced in the course of the Santos parties' petroleum exploration operations. It is located within the area subject to PAL 2. The People for the Plains Incorporated (the appellant) challenged the validity of approvals that had been granted under the PO Act by delegates of the Secretary of the NSW Department of Industry (the third respondent). The appellant's complaint, in essence, was that the relevant approvals granted by the third respondent covered the treatment of water and brine produced not only on PAL 2, but also on land falling outside the boundaries of that particular petroleum title but subject to different petroleum titles (namely, PEL 238 and PPL 3). The appellant contended that development consent was required for such activity. The appellant commenced two sets of proceedings. First, the appellant brought judicial review proceedings, seeking a declaration that the approval granted 18 August 2015 was invalid and of no effect (as well as orders quashing the decision to grant the approval and its subsequent renewal in December 2015) (the Transferred Proceedings). Second, the appellant brought civil enforcement proceedings, seeking a declaration that the Leewood Project required development consent under the Environmental Planning and Assessment Act 1979 (NSW) (the EP&A Act) (The L & E Proceedings). The Transferred Proceedings and the L & E Proceedings were heard together. The primary judge dismissed both sets of proceedings. First, the primary judge held that the proper characterisation of the proposed facilities and their operation (up to and including the operation of the Leewood facility, but excluding certain Lucerne cropping activities) was that they were for the purpose of petroleum exploration prospecting and, adopting a purposive construction of s 33 of the PO Act, concluded that such development was permissible without development consent. On this basis, his Honour dismissed the Transferred Proceedings. Second, the primary judge held that the Lucerne cropping activity was a separate and distinct purpose (namely, commercial agricultural activity) and that this required no development consent pursuant to the Narrabri Local Environmental Plan 2012. On this basis, his Honour dismissed the L & E Proceedings. The appeal ultimately turned on the proper characterisation of the Leewood Project. Ground 1 concerned whether the Leewood Project was prospecting within the meaning of s 33 of the PO Act and undertaken for the purpose of petroleum exploration within the meaning of cl 6(d) of the State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) 2007 (NSW) (the Mining SEPP). Ground 2 contended that cl 6(d) of the Mining SEPP did not apply by virtue of certain provisions of the State Environmental Planning Policy (Infrastructure) 2007 (NSW) (the Infrastructure SEPP) and that there was an inconsistency between the Infrastructure SEPP and the Mining SEPP. Ground 3 contended that delegates of the third respondent granted approval on the false basis that development consent was not required. Held, dismissing the appeal: As to ground 1(a): (1) (at [142]; [143] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) in characterising the Leewood Project for the purposes of the relevant legislation and planning instruments, the primary judge erred in bifurcating the Leewood Project into separate parts. This led to a finding that did not address the correct question, namely, whether the Leewood Project, as a whole, was for prospecting within s 33 of the PO Act or development for the purpose of "petroleum exploration" within the meaning of cl 6(d) of the Mining SEPP. (2) (at [144] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) however, nothing turns on this error as the Leewood Project is properly characterised as being for the purpose of petroleum exploration. As to ground 1(b): (3) (at [148] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) the imposition on the grant of PAL 2 of the condition that activities be conducted under an approved Petroleum Operations Plan and the requirement that such a plan deal with the treatment and beneficial reuse of produced water lead to the conclusion that the Leewood Project was proposed to be engaged in for the purpose of satisfying the condition on PAL 2 and therefore for the purpose of enabling the petroleum exploration and appraisal activities to be carried out. (4) (at [149] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) this conclusion is not altered by the fact that the condition on PAL 2 could have been satisfied by other means. As to ground 1(c) and 1(d): (5) (at [156] (per Ward JA)) (Obiter) there is considerable force in the submission that the so-called purposive interpretation of s 33 of the PO Act adopted by the primary judge was not justified having regard to the principles outlined in Cooper Brooks (Wollongong) Pty Ltd v Federal Commissioner of Taxation (1981) 147 CLR 297; [1981] HCA 26. As to ground 2: (6) (at [185] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) the Leewood Project should be characterised as one which is for the treatment of produced water for the purposes of petroleum exploration and not waste or resource disposal or management. Accordingly, cl 6(d) of the Mining SEPP applied and the Leewood Project did not require development consent under Pt 4 Div 2 of the EP&A Act. (7) (at [186] (per Ward JA); [6] (per Meagher JA, agreeing); [202]-[205] (per Payne JA, agreeing) to the extent that there is any relevant inconsistency between the Mining SEPP and the Infrastructure SEPP, the Mining SEPP would prevail. (8) (at [187] (per Ward JA); [7] (per Meagher JA, agreeing); [206]-[208] (per Payne JA, agreeing)) the word "land" in cl 18 of the Mining SEPP should be read as the land on which the relevant (overall) development is taking place. As to ground 3: (9) (at [192] (per Ward JA); [1] (per Meagher JA, agreeing); [209] (per Payne JA, agreeing)) as development consent was not required for the Leewood Project, there can have been no failure by the decision-maker to take the relevant consideration that the Leewood Project required development consent.
Judgment
Current proceedings
Petroleum (Onshore) Act 1991 (NSW)
Environmental Planning Instruments
Mining SEPP
Infrastructure SEPP
Chronology
Primary judgment
Ground 1 - finding that the Leewood Project was "prospecting" and for the purpose of "petroleum exploration" under cl 6 of the Mining SEPP
Ground 1(a) of the appeal - "splitting" the Leewood Project (Santos parties' notice of contention grounds 2, 3, 6)
Ground 1(b) of the appeal - proper characterisation of the purpose of the Leewood Project
Santos notice of contention ground 2 - proper construction of PO Act and characterisation
Ground 1(c) of the appeal (Santos parties' notice of contention ground 5) - treatment of water from PPL 3
Ground 1(d) (Santos parties' notice of contention grounds 2 and 4) - interpretation of s 33 of the PO Act.
Third respondent's notice of contention grounds 1-2 - proper construction of PO Act
Determination - Ground 1 of the grounds of appeal
Ground 2
Ground 2(a) of appeal (Santos parties' notice of contention ground 9) - Infrastructure SEPP prevails
Ground 2(b) (Santos notice of contention ground 8) - failure to apply cl 18
Third respondent's notice of contention - grounds 3-5
Determination as to ground 2
Ground 3 of the appeal (Santos' notice of contention 10)
Determination as to ground 3
Santos parties' Notice of Contention ground 1 - Proper Construction of the PO Act
Determination as to ground 1 of the Santos parties' notice of contention
Conclusion
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 14 March 2017
People for the Plains Incorporated
Santos NSW
[2007] NSWCA 343
(2011) 180 LGERA 343
(2011) 182 LGERA 370
(1997) 95 LGERA 294
(2007) 151 LGERA 400
(1981) 147 CLR 297
(2015) 207 LGERA 397
(2003) 123 LGERA 312
(1983) 155 CLR 211
(2002) 123 LGERA 207
(1998) 194 CLR 355
(1980) 144 CLR 13
(1996) 65 FCR 25
(1996) 90 LGERA 106
(2014) 253 CLR 531
(1964) 110 CLR 529
[1980] HCA 13