[This Headnote is not to be read as part of the judgment]
This judgment relates to an appeal from a decision in the NSW Land and Environment Court.
The first, second and fourth respondents (the Santos parties) hold and/or operate three petroleum titles under the Petroleum (Onshore) Act 1991 (NSW) (the PO Act): an exploration licence (PEL 238), a production lease (PPL 3) and an assessment lease (PAL 2). PAL 2 and PPL 3 are over land within the boundaries of, but excised from, the area originally comprising PEL 238. The Santos parties conduct extensive integrated petroleum explorations operations upon this land.
The Leewood Produced Water Treatment and Beneficial Reuse Project (the Leewood Project) is the second phase of a project relating to the management of water produced in the course of the Santos parties' petroleum exploration operations. It is located within the area subject to PAL 2.
The People for the Plains Incorporated (the appellant) challenged the validity of approvals that had been granted under the PO Act by delegates of the Secretary of the NSW Department of Industry (the third respondent).
The appellant's complaint, in essence, was that the relevant approvals granted by the third respondent covered the treatment of water and brine produced not only on PAL 2, but also on land falling outside the boundaries of that particular petroleum title but subject to different petroleum titles (namely, PEL 238 and PPL 3). The appellant contended that development consent was required for such activity.
The appellant commenced two sets of proceedings. First, the appellant brought judicial review proceedings, seeking a declaration that the approval granted 18 August 2015 was invalid and of no effect (as well as orders quashing the decision to grant the approval and its subsequent renewal in December 2015) (the Transferred Proceedings). Second, the appellant brought civil enforcement proceedings, seeking a declaration that the Leewood Project required development consent under the Environmental Planning and Assessment Act 1979 (NSW) (the EP&A Act) (The L & E Proceedings). The Transferred Proceedings and the L & E Proceedings were heard together.
The primary judge dismissed both sets of proceedings. First, the primary judge held that the proper characterisation of the proposed facilities and their operation (up to and including the operation of the Leewood facility, but excluding certain Lucerne cropping activities) was that they were for the purpose of petroleum exploration prospecting and, adopting a purposive construction of s 33 of the PO Act, concluded that such development was permissible without development consent. On this basis, his Honour dismissed the Transferred Proceedings. Second, the primary judge held that the Lucerne cropping activity was a separate and distinct purpose (namely, commercial agricultural activity) and that this required no development consent pursuant to the Narrabri Local Environmental Plan 2012. On this basis, his Honour dismissed the L & E Proceedings.
The appeal ultimately turned on the proper characterisation of the Leewood Project. Ground 1 concerned whether the Leewood Project was prospecting within the meaning of s 33 of the PO Act and undertaken for the purpose of petroleum exploration within the meaning of cl 6(d) of the State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) 2007 (NSW) (the Mining SEPP). Ground 2 contended that cl 6(d) of the Mining SEPP did not apply by virtue of certain provisions of the State Environmental Planning Policy (Infrastructure) 2007 (NSW) (the Infrastructure SEPP) and that there was an inconsistency between the Infrastructure SEPP and the Mining SEPP. Ground 3 contended that delegates of the third respondent granted approval on the false basis that development consent was not required.
Held, dismissing the appeal:
As to ground 1(a):
(1) (at [142]; [143] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) in characterising the Leewood Project for the purposes of the relevant legislation and planning instruments, the primary judge erred in bifurcating the Leewood Project into separate parts. This led to a finding that did not address the correct question, namely, whether the Leewood Project, as a whole, was for prospecting within s 33 of the PO Act or development for the purpose of "petroleum exploration" within the meaning of cl 6(d) of the Mining SEPP.
(2) (at [144] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) however, nothing turns on this error as the Leewood Project is properly characterised as being for the purpose of petroleum exploration.
As to ground 1(b):
(3) (at [148] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) the imposition on the grant of PAL 2 of the condition that activities be conducted under an approved Petroleum Operations Plan and the requirement that such a plan deal with the treatment and beneficial reuse of produced water lead to the conclusion that the Leewood Project was proposed to be engaged in for the purpose of satisfying the condition on PAL 2 and therefore for the purpose of enabling the petroleum exploration and appraisal activities to be carried out.
(4) (at [149] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) this conclusion is not altered by the fact that the condition on PAL 2 could have been satisfied by other means.
As to ground 1(c) and 1(d):
(5) (at [156] (per Ward JA)) (Obiter) there is considerable force in the submission that the so-called purposive interpretation of s 33 of the PO Act adopted by the primary judge was not justified having regard to the principles outlined in Cooper Brooks (Wollongong) Pty Ltd v Federal Commissioner of Taxation (1981) 147 CLR 297; [1981] HCA 26.
As to ground 2:
(6) (at [185] (per Ward JA); [6] (per Meagher JA, agreeing); [201] (per Payne JA, agreeing)) the Leewood Project should be characterised as one which is for the treatment of produced water for the purposes of petroleum exploration and not waste or resource disposal or management. Accordingly, cl 6(d) of the Mining SEPP applied and the Leewood Project did not require development consent under Pt 4 Div 2 of the EP&A Act.
(7) (at [186] (per Ward JA); [6] (per Meagher JA, agreeing); [202]-[205] (per Payne JA, agreeing) to the extent that there is any relevant inconsistency between the Mining SEPP and the Infrastructure SEPP, the Mining SEPP would prevail.
(8) (at [187] (per Ward JA); [7] (per Meagher JA, agreeing); [206]-[208] (per Payne JA, agreeing)) the word "land" in cl 18 of the Mining SEPP should be read as the land on which the relevant (overall) development is taking place.
As to ground 3:
(9) (at [192] (per Ward JA); [1] (per Meagher JA, agreeing); [209] (per Payne JA, agreeing)) as development consent was not required for the Leewood Project, there can have been no failure by the decision-maker to take the relevant consideration that the Leewood Project required development consent.