Factual background
7 Westlink was incorporated on 2 September 2008. Mr Craig Doyle has been its sole director since incorporation. Westlink acquired a parcel of land in Adare, Queensland (Land), on or about 5 January 2009, and obtained a development approval for the purpose of constructing an open-cycle gas turbine power station.
8 In March 2017, Westlink contracted with Capital Partners Australia Pty Ltd as trustee for the Australian Clean Power Trust to sell the land to the Trust (Contract). Capital Partners, as trustee, became the registered owner of the Land on 18 April 2017.
9 On completion, Capital Partners gave Westlink a mortgage of the Land, under special condition 13.1(a) of the Contract, to secure performance of Capital Partners' post-completion obligations (Mortgage). Westlink and Capital Partners subsequently entered into a Tripartite Deed with Solstice Development Services (SDS) Pty Ltd, concerning the development of the project.
10 By the terms of the Contract, Capital Partners was obligated to make payments to Westlink upon attaining certain milestones in respect of the Project which was defined in special condition 1 as "the development and construction of a gas fired power station on the Land in stages after obtaining all Approvals (including the Development Approval) and Project Agreements".
11 Special condition 14.1 of the Contract provides for five tranches of payments by Capital Partners to Westlink:
(a) $2.5 million when [Capital Partners] enters into a Tolling Agreement;
(b) $3.1 million on achievement of Stage 1 FID [financial investment decision as defined];
(c) $70,000.00 per megawatt for any electricity generation capacity exceeding 100 megawatts in Stage 1 (if applicable) on achievement of Stage 1 FID;
(d) $70,000.00 per megawatt for any electricity generation capacity exceeding the megawatt capacity of Stage 1 but capped at 200 megawatts on achievement of Stage 2 FID; and
(e) an annual amount for every Financial Year based on [Capital Partners'] Final Accounts equal to 10% of cash returns earned by [Capital Partners] or a successor in title on an ongoing basis over and above a 12% unlevered post tax internal rate of return hurdle for electricity generation capacity exceeding 200 megawatts.
12 It is apparent that pursuit of the Project was necessary for Westlink to have the opportunity to obtain the benefit of special condition 14.1. The first step was to make a "Tolling Agreement" as defined in special condition 1.
13 It is also relevant that the payment liabilities of Capital Partners under special condition 14.1 of the Contract are prospective or contingent. Those prospective or contingent liabilities are defined as "Secured Moneys" under the Mortgage, which by clause 6 required Capital Partners to "ensure that the Secured Moneys are paid … as required by the Transaction Document [which was defined to mean, inter alia, the Contract]". Accordingly, Westlink contends that Capital Partners was required to do all things necessary to enable Westlink to have the benefit of special condition 14.1, which included pursuit of the Project. If the Project was not pursued, the obligation to pay Westlink under special condition 14.1 would not mature into a present monetary obligation.
14 On 19 December 2017, Westlink (by Mr Doyle) and Capital Partners agreed to vary the payments required of Capital Partners under special condition 14.1 of the Contract (the First Variation). The First Variation provided for:
(a) an immediate payment of $250,000 by Capital Partners to Westlink; and
(b) a reduction in the amount payable under special condition 14.1(a) from $2.5 million to $2.1 million.
15 In November 2018, Quinbrook became the new trustee of the Trust. Simultaneously, the Land was transferred, subject to the Mortgage, to Perpetual Corporate Trust Ltd as a custodian trustee. By s 63(1) of the Land Title Act 1994 (Qld), Perpetual became liable to comply with the terms of the Mortgage, including by performance of clause 6 of the Mortgage.
16 Westlink contends that if clause 6 of the Mortgage was breached by Quinbrook and Perpetual, Westlink would suffer loss, because Westlink would not receive the benefit of special clause 14.1 coming to pass. This would amount to "Loss", meaning "loss, damage, cost, expense or liability" as defined in clause 1.1 of the Mortgage. Clause 21.1 of the Mortgage requires Perpetual to indemnify Westlink for any "Loss" incurred "as a direct or indirect result… of any act or omission of [Perpetual]". "Event of Default" is defined under the Mortgage as a failure to pay or repay any amount due under, inter alia, the Contract, including a failure by Perpetual to indemnify Westlink under clause 21.1. Clause 14.1 of the Mortgage provides that it becomes enforceable on the occurrence of an "Event of Default".
17 On 2 November 2018, Westlink, Quinbrook, SDS and Perpetual also entered into a "Deed of Transfer of Tripartite Deed", by which Perpetual assumed Capital Partners' obligations under the Mortgage and the Tripartite Deed.
18 In or about November 2018, the Federal Government announced a new scheme known as the Underwriting New Generation Investments Program (UNGI). The relevance of UNGI to the Project was not in evidence. It is nevertheless apparent from a letter dated 13 June 2023 from the solicitors for the applicants to the solicitors for the Receivers (13 June Letter) that Quinbrook and Mr Doyle communicated about UNGI on several occasions during November 2018. In early 2019, Quinbrook corresponded with Mr Doyle to provide updates on the Project which included Quinbrook's expression of interest in UNGI. Further correspondence was exchanged between Quinbrook and the Federal Government regarding UNGI in April and May of 2019. There appears to have been broader correspondence between Quinbrook, Mr Doyle, "and others" concerning negotiations and discussions with the Federal and State Governments and the Queensland Opposition throughout June to December 2019, and then between Quinbrook, the Federal Government, CS Energy and Mr Doyle regarding draft term sheets for the Project's participation in UNGI throughout the months of January to September 2020.
19 It appears that initial agreement between Quinbrook and the Federal Government regarding the Project's participation in UNGI was reached on 13 November 2013, and negotiations continued until May 2021. It appears an impasse was arrived at in the latter half of 2021.
20 A Second Variation of special condition 14.1 of the Contract was agreed between Quinbrook (by Mr Scaysbrook) and Westlink (by Mr Doyle), on or about 8 April 2020. The Second Variation provided:
(a) for payment of $400,000 by Quinbrook to Westlink in instalments of:
(i) $100,000 payable within 24 hours of countersigning the letter;
(ii) $100,000 payable within 72 hours of receiving a countersigned term sheet from the Federal Government; and
(iii) $200,000 payable within 72 hours of receiving a binding agreement with the Federal Government; and
(b) for a reduction in the amount payable under special condition 14.1(a):
(i) from $2.1 million to $1.88 million, upon payment of the first $100,000 instalment;
(ii) from $1.88 million to $1.66 million, upon payment of the second $100,000 instalment; and
(iii) from $1.66 million to $1.34 million, upon payment of the $200,000 instalment.
21 A Third Variation to special condition 14.1 of the Contract was agreed between Quinbrook (by Mr Scaysbrook) and Westlink (by Mr Doyle), on or about 11 February 2021. The Third Variation provided for a payment to Westlink of $200,000 in return for:
(a) a reduction in the amount payable under special condition 14.1(a) from $1.88 million to $1.44 million;
(b) the deletion of special condition 14.1(e); and
(c) the second $100,000 instalment and the $200,000 instalment under the Second Variation being rendered null and void.
22 On 25 May 2022, Starkorp Pty Ltd, a secured creditor of Westlink, exercised its rights under a general security deed and appointed the Receivers as receivers of all of the property of Westlink. By letter dated 8 July 2022, the Receivers requested that Quinbrook provide copies of quarterly updates of the Project between 16 March 2017 and 30 June 2022, and marketing information for the Project. Mr Restall refused to provide the requested information.
23 On 22 August 2022, the Receivers sent a draft statement of claim to the applicants' solicitors. The draft claim sought declarations that: Perpetual failed to comply with clause 6 of the Mortgage; Westlink suffered "Loss" as a result; Perpetual is required to, but has not, indemnified Westlink pursuant to clause 21.1 of the Mortgage; and that an "Event of Default" occurred. In alleging that Perpetual did not comply with clause 6 of the Mortgage, the claim alleges that the Project has not been pursued. The Receivers sought to investigate, by examination, whether such allegation could be proven.
24 Accordingly, by an originating process lodged on 9 December 2022, the Receivers applied for:
(a) a summons pursuant to s 596A of the Corporations Act to issue to Mr Doyle;
(b) summonses pursuant to s 596B of the Corporations Act to issue to Messrs Scaybrook and Restall; and
(c) an order for Quinbrook to produce books and records pursuant to s 597(9) of the Corporations Act.
25 On 30 January 2023, a Registrar of this Court made orders granting the Receivers' application and the Summonses were issued on 1 February 2023. The Receivers served the Summonses on 7 February 2023.
26 On 17 February 2023, the applicants' solicitors sent two letters to the Receivers' solicitors. The first letter contended there was no basis, of which they were aware, for any claim against Quinbrook to support orders for public examination or the production of documents and noted their concern regarding the proper basis for the issue of the Summonses. The second letter contended that the scope of the Summonses was oppressive.
27 The applicants' solicitors sent the Receivers' solicitors the 13 June Letter, which recorded their concern that Westlink had no cause of action against Quinbrook and invited the Receivers to discontinue the proposed examination process. The letter outlined that Quinbrook had taken steps and expended amounts in progressing the Project.
28 The Receivers objected to paragraphs 4 and 5 of the Affidavit of Brian Graham Restall filed 10 July 2023, to which this letter was annexed, to the extent that those paragraphs sought to establish the truth of the matters in the letter to contend that Perpetual and Quinbrook have been taking reasonable steps since November 2018 to progress the Project. No objection was taken to the Affidavit of Christopher John Connor filed on 6 July 2023 to which the same letter was annexed. The objection to those paragraphs was rightly taken, the content being irrelevant to the question to be decided by an application to set aside summonses for examination: s 56(2) of the Evidence Act 1995 (Cth).
29 The applicants now bring this interlocutory application to set aside or review the issuing of the Summonses.