24 The Minister's views were ultimately determinative of the outcome of the application. There was no obligation on the Minister to advise the Plaintiff of the Department's advice which was indecisive given the recognition that the underlying issue would fall to be determined one way or the other by the Minister's acceptance or rejection of the Department's advice to delete the 11 turbines. That there was no decisiveness on the part of the Minister is evident in the briefing note and the portion of the Director-General's report attached to the briefing note. The statement that "the project is not a critical infrastructure project" in the briefing note needs to be read in the context of the inconclusive analysis in the report and the fact that this is expressly stated to be a recommendation which the Minister may not necessarily agree to.
25 Contrary to the situation referred to by McHugh J in Lai Qin this is not a case where the Minister's conduct left the Plaintiff no reasonable alternative but to commence proceedings in December 2008. The decision of the Minister on 26 June 2009 occurred after receipt of the Director-General's EAR and briefing note and after subsequent additional inquiries by the Minister which were the product of the statutory process under Pt 3A. At the time proceedings were commenced the Third Defendant's submissions on the project had been received (in November 2008). The Director-General had not yet prepared his EAR. If the Plaintiff had awaited the outcome of the Pt 3A decision-making process it would have had no cause to commence proceedings in Class 4 of the Court's jurisdiction. It could have sought a merits review in Class 1 as it has now done by an application filed 11 August 2009.
26 These proceedings were commenced prematurely and as no interlocutory injunction was applied for or expedition sought, the process of assessing the project under Pt 3A continued. The undetermined issue is whether the project for which approval is sought has to be critical infrastructure at the time of lodgment with the Department and also at the time the Minister makes the decision. The briefing note and the Director-General's EAR prepared pursuant to s 75I were signed by the Director-General on 13 April 2009. The Minister did not sign until 26 June 2009. During April there was a second briefing note to the Minister concerning the Third Defendant's submissions that no turbines should be deleted. This resulted in consultation by the Minister with the relevant Commonwealth minister and another State minister concerning aviation safety issues around the Crookwell landing strip. No definitive decision as to the removal of turbines was made until 26 June 2009.
27 There was no reason for the Plaintiff to bring these proceedings so early in order to preserve the possibility of Class 1 proceedings. These proceedings could have been commenced once the Minister's decision was known. To commence the proceedings when the Plaintiff did was premature.
28 In relation to the application for indemnity costs, the Plaintiff must establish that the circumstances warrant the making of an order for the payment of costs on such a basis, per Sheppard J in Colgate Palmolive at 234. There was no unreasonable behaviour or misconduct by the Director-General and the Minister in filing the Points of Defence on 21 April 2009 or in any other aspect of the litigation to justify the award of costs on an indemnity basis.
Third and Fourth Defendants' submissions
29 The Plaintiff bears the onus of establishing that costs should not be paid by the party discontinuing the proceedings, per Bryson J in Australiawide Airlines Ltd v Aspiron Pty Ltd at [53] and Bitannia Pty Ltd v Parkline Constructions Pty Ltd [2009] NSWCA 32 at [54] (Hodgson JA with whom Tobias JA agreed). There is no attempt to discharge that onus in relation to the Third and Fourth Defendants. The Plaintiff should pay the Third and Fourth Defendants' costs. They are necessary parties to the litigation as their project is affected by the relief sought. Given the nature of the relief sought in relation to the environmental impact assessment of the project, the Plaintiff sat on its hands and did not seek to restrain the approval process by seeking interlocutory relief. It has now unilaterally abandoned its claim for final relief in relation to the invalidity of the EAR and consequential orders restraining the approval process. As outlined in the Third and Fourth Defendants' Amended Points of Defence filed 7 April 2009 at par 33, the Plaintiff also had the onus of demonstrating that its proceedings were not caught by s 75T, which prevents the commencement of proceedings challenging a critical infrastructure project under Pt 3A without having a Ministerial certificate. It has also abandoned any claim that it could commence proceedings.
30 The Plaintiff's claim that the project was not critical infrastructure has not been determined. The Third and Fourth Defendants' defence was that the project did come within the terms of the Ministerial declaration under s 75C that wind farms of a certain capacity were critical infrastructure. That issue has not been determined at a hearing and cannot be considered now in the costs hearing, per McHugh J in Lai Qin at 624-625.
31 There are five errors in the Plaintiff's submissions. Firstly, the Plaintiff was not successful. Secondly, the project lodged under Pt 3A is separate from the approval given by the Minister. The status of the approved project, being that project approved subject to conditions by the Minister, was never in issue in the proceedings. The Plaintiff cannot claim it has been successful in terms of the relief it sought as it did not challenge the approved project but rather the project for which approval was sought in the major project application. The issues raised by the Plaintiff's Points of Claim have never been tested at a hearing and have now been abandoned. The fact that the approved project may not be a critical infrastructure project by reason of the conditions of approval removing 11 of the original 84 turbines is irrelevant to this costs dispute.
32 Thirdly, there was no supervening event. The usual process for the assessment of Pt 3A projects proceeded in the absence of the Plaintiff seeking any interlocutory relief. Given that failure, or an application seeking expedition by the Plaintiff, the Minister's decision to issue an approval was not supervening in any way. It was simply the necessary statutory process proceeding. It was the Plaintiff's unreasonable conduct in commencing proceedings which has resulted in costs being incurred.
33 Fourthly, there are misconceptions in the reasons the Plaintiff commenced the proceedings when it did. It was not necessary to commence these proceedings prior to the Minister's decision in order to preserve an appeal right in Class 1. Any judicial review action could have awaited the Minister's decision.
34 Fifthly, there has been misconduct by the Plaintiff as considered by Lloyd J in Parkesbourne/Mummel Landscape Guardians Inc v Minister for Planning [2009] NSWLEC 101 concerning a notice to produce issued by the Plaintiff. He held it was oppressive and an abuse of process.
35 The Plaintiff has made no real attempt to displace the ordinary costs approach under r 42.19. There is no authority cited for the Plaintiff's proposition that the alleged misconduct in relation to the Points of Defence of the Minister and the Director-General could be a reason for r 42.19 being displaced. No positive reason has been given as to why r 42.19 should not apply, per Australiawide and Bitannia. The Minister's conditional approval of the project is no basis for displacing the usual costs discretion under r 42.19.