© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[1998] VSC 124
Supreme Court of Victoria
1998-11-02
Smith, J.
Original judgment source is linked above.
SALE OF LAND - apartments on proposed plan of subdivision - contract subject to contingent condition - implied term - "best endeavours" - reasonable endeavours - attempted rescission - default by rescinding party - election - estoppel SPECIFIC PERFORMANCE - impossibility - hardship to third persons.
(a) Ersoy Arif Contract. By contract of sale dated 26 November 1993 the defendant agreed to sell to the fourth named plaintiff Ersoy Arif unit 2 and parking unit 14 ("unit 2") to be constructed as part of a development at 347 Beaconsfield Parade St Kilda ("the land"). The purchase price was $205,000. A deposit was paid on 26 November 1993 of $10,250.00.
(b) Welham Contract. By contract of sale dated 22 January 1994 the defendant agreed to sell to the third named plaintiff Peter John Welham unit 10 and parking unit 31 ("unit 10") of the proposed development for a sum of $245,000.00. A deposit of $24,500 was paid on 22 January 1994 and 28 February 1994. The parking unit was later changed to unit 12.
(c) Letife Arif Contract. By contract of sale dated 3 February 1995, the defendant agreed to sell unit 12 and parking unit 22 ("unit 12") of the proposed development for the sum of $300,000.00 to the second named plaintiff Letife Arif for the sum of $300,000. The deposit of $20,000.00 was paid on 6 December 1994. In relation to that contract, the second named plaintiff nominated the fifth named plaintiff Sami Nominees Pty Ltd as substitute purchaser under the contract and on 11 October 1996 the defendant's solicitors agreed to such nomination subject to the provision of guarantee. The parking unit was changed to unit 19. It was common ground that at all material times Ersoy Arif acted as agent for his mother Latife Arif in relation to this contract.
(a) As the person seeking to have a plan registered he was obliged to prepare the plan, submit it to the Council for certification, obtain a statement of compliance from the Council and lodge the certified plan at the Office of Titles (S.5 (3) Sub-division Act 1988).
(b) The Council had the right to require payment of a sum representing a percentage of the site value of all the land in the sub-division that was to be used for residential purposes for public open space requirements. The percentage could not exceed 5 per cent (s.18 (1) Sub-Division Act 1988). The defendant was obliged to pay the public open space fee before the Council would issue its statement of compliance unless he and the Council agreed to payment after the issue of the statement of compliance (s.18 (1B) Sub-division Act 1988).
"2.1 This Contract is subject to and conditional upon the certification of the Plan of Subdivision (the "Plan") by the Council (the "Council") of the municipality within which the Property is situated and the registration by the Registrar of Titles of the Plan within twenty-four (24) months from the Day of Sale (the "Plan Registration Date").
2.2 The Vendor at its own cost must use its best endeavours to procure the certification and registration of the Plan by the Plan Registration Date.
2.3 Subject to Section 9AC of the Sale of Land Act 1962, the Vendor reserved the right to alter, amend or vary the plan in accordance with any requirement of the Vendor, the Council or the Registrar of Titles.
2.4 If any amendment to the Plan is made which restricts or limits the use of the lot or lots to which this contract relates, then the Purchaser may avoid this contract at any time before the Plan is registered unless the amendment results from any recommendation of a public authority or government department. The provisions of this condition and section 19 (1) of the Sale of Land Act 1962 do not apply in respect of the final location of an easement shown on the Plan.
2.5.1 If the Plan is not certified and registered by the Plan Registration Date then either the Vendor or the Purchaser may at any time after that date but before the Plan is registered rescind this contract by written notice to the other.
2.5.2 If either party rescinds this contract pursuant to this condition, then the Vendor must immediately return to the Purchaser the deposit less the amount of any occupation fees paid by the Purchaser.
2.5.3... The Purchaser shall not be entitled to any compensation from the Vendor in respect of any costs, fees or other expenses paid or incurred by the Purchaser in relation to or arising out of the transaction evidenced by this contract.
2.6 Until the Plan has been registered, the Purchaser must not lodge or cause or permit to be lodged on the Purchaser's behalf any caveat in the Land Titles Office in respect of the Purchaser's interest in the Property. The Purchaser shall indemnify and keep indemnified the Vendor against any loss or damage which the Vendor may incur or suffer as a consequence of any breach by the Purchaser of this condition."
"3.1 This sale is subject to and conditional upon the Vendor executing on or before the settlement date all design, building and construction works ("the works") for the development of the property substantially in accordance with the Architectural Plans copies of which are attached hereto. The Purchaser does hereby acknowledge that the Vendor shall at any time be entitled to make (without reference to the Purchaser) any minor alterations or variations that the Vendor may deem necessary to be made to the Architectural plans and / or the works. However, the Vendor agrees to notify the Purchaser in writing of any proposed changes to the Architectural plans or the works which directly, substantially and detrimentally effect the property hereby sold.
3.2 The Vendor agrees that as well as completing the works substantially in accordance with the said Architectural Plans it will complete such works in accordance with the specifications and standards required by the Council including the Standards published by the Standards Association of Australia (S.A.A.) and further in accordance with the Schedule of "Construction Details, Fittings and Finishes a copy of which is attached to this Contract.
3.3 The Vendor shall be deemed to have completed the works and discharged its obligations under Special Conditions 3.1 and 3.2 upon its producing to the Purchaser a Certificate of Occupancy issued by the City of St Kilda for the lot hereby sold.
3.4 The Vendor shall promptly attend to rectification of defects and other faults apparent in any part of the project works and notified in writing by the Purchaser to the Vendor during a period of fifty-two (52) weeks from the date of issue of the Certificate of Occupancy which are due to defective materials or faulty workmanship."
A special condition Cl 4 dealt with the handling of deposit monies. It provided the following:-
"4. The deposit moneys payable by the Purchaser shall be paid to the Vendor's solicitors, Messrs Phillips Fox, to be held on trust for the Purchaser until the registration of the Plan and then to be held as stakeholder pursuant to section 24 of the Sale of Land Act 1962. The deposit or any part of the deposit may be held in an interest bearing trust account established pursuant to section 49 (10 (a) of the Legal Profession Practice Act 1958. Any interest accruing on the deposit shall be paid to the party ultimately entitled to receive the deposit."
Payment of the residue of the purchase money was to be made on the later of
" (a) 10 days after the purchaser is notified of registration of the plan of sub-division pursuant to special condition 2. (b) 10 days after the purchaser is notified of the issue of a certificate of occupancy pursuant to special condition 3".
The Plan Registration Date for that contract expired for the first time on 26 November 1995. The defendant served a rescission notice on 1 March 1996. The dispute over that notice of rescission was resolved and the notice withdrawn. The parties agreed on 14 October 1996 to the contract continuing but there was no formal extension made of the Plan Registration Date. By letter dated 27 November, 1996, however, the solicitors for the defendant sought agreement to a new Plan Registration Date of 30 May 1997. Ersoy Arif through his solicitor agreed to that extension by letter dated 9 December 1996. The defendant sought a further extension on 26 May 1997 to 31 August 1997 and Mr Arif agreed to that date. No further extensions of the date were made. There was further communication between the parties but, by fax of 7 May 1998, the defendant's solicitors gave notice of rescission relying upon cl. 2.5.1 of the contract.
The Plan Registration Date for that contract expired on 22 January 1996. In 1995 Mr Welham agreed to an extension of the Plan Registration Date to 30 June 1996. Subsequently he was asked to further extend the time, and agreed to do so, to 30 August 1996, 15 November 1996, 15 February 1997, 30 May 1997, 30 June 1997 and 31 August 1997. In late 1997 there was some correspondence passing between solicitors concerning the Plan Registration Date which did not result in any further extension. The defendant gave notice of rescission in respect of this contract also by letter from his solicitors dated 7 May 1998, again relying on cl. 2.5.1 of the contract.
The Plan Registration Date for this contract was 3 February 1997. On 9 December 1996 the solicitors for the second named plaintiff agreed to the request of the defendant for an extension of the date to 30 May 1997. Further extension was sought by the defendant's solicitors by letter dated 26 May 1997 to 31 August 1997. By letter dated 19 June 1997, the solicitors for the second named plaintiff wrote to the defendant's solicitors agreeing to the extension sought. Thereafter again, the issue of Plan Registration Date was raised but not resolved. By fax of 7 May 1998 the defendant's solicitor gave notice of rescission relying on cl. 2.5.1 of the contract.
(a) confirmation of Telstra's consent to the issue of a statement of compliance by the Council;
(b) City Power's consent to the issue of a statement of compliance and
(c) payment of the Council's open space contribution.
By letter dated 24 September 1997 Telstra wrote to the City of Port Philip consenting to the issue of a statement of compliance. On 29 September 1997, City Power advised the defendant that the original statement of compliance had been sent to the wrong Council and that it would forward a copy to the City of Port Philip. On 29 October 1997 the defendant was advised by Mr Carlisle of the City of Port Philip that all requirements had been satisfied in relation to the plan of sub-division save and except for the payment of the Council's open space requirement of $26,000.00. On 6 November 1997, the defendant received from Esanda various cheques including a cheque for $26,000.00 made payable to the City of Port Philip to meet the open space requirement. The defendant instructed his solicitors to place the $26,000.00 cheque into their trust account where it remained until 8 May 1998. The defendant claims in his Affidavit of 1 July 1998 that he was under the belief that the plan of sub-division could not be registered until he had entered into a s. 163 agreement under the Building Act 1993 with the City of Port Philip and that that was not entered into until December 1997. He deposes that it has since been explained to him by Hugh MacCann of Phillips Fox, Solicitors, that that agreement was required for the grant of a certificate of occupancy and not for the registration of the plan of sub-division. I think that account of events is unlikely. But in any event, it would appear that, if absence of such an agreement was seen by the defendant as an obstacle to registration of the plan of sub-division, it had been removed by December 1997. All that then remained to enable certification and registration to take place thereafter was payment of the open space fee of $26,000.00, which sum was being held by his solicitors. On the 8th May 1998, the day after the purported rescission of the above three contracts, a cheque was drawn on the solicitor's trust account and delivered by the defendant to the City of Port Philip.
"3. In the event that the first defendant rescinds the contract of sale in respect of units 1, 6 or 10, 347 Beaconsfield Parade St. Kilda West prior to 20 May 1998 the plaintiff agrees to consent to the release of the deposit monies paid under the respective contracts to the respective purchasers under those contracts."
Unit 5 was re-financed with the Bank of Queensland on 26 June 1998. The proceeds of $494,351.00 were paid to Esanda.
(b) $75,000.00 to the fourth mortgagee the defendant's solicitors Hall and Willcox
(c) $150,000.00 to Mario Costa for his advance to pay the three sub contractor caveators
(d) $45,000 to Phillips Fox the solicitors acting in the conveyancing for the sales for the defendant and
(e) $50,000.00 to Otis Elevators to allow the lifts to continue operating.
The following securities were given to St. George in addition to the Esanda mortgage over the six units:
(a) A first registered mortgage over Mario Costa's family home
(b) A first registered mortgage over Mario Costa's holiday home
(c) A first registered mortgage over two units owned jointly by the defendant's wife and her brother.
(d) A mortgage or transfer of Mario Costa's life insurance policy
(e) A mortgage or transfer of the defendant's wife's life insurance policy
(f) Unlimited guarantees from the defendant, his wife, Mario Costa and a limited guarantee from the defendant's brother-in-law.
Rescission - The Construction of Clause 2 Of The Contracts
*clauses 2.1 and 3.1 should be categorised as contingent conditions.
*up to the contract Plan Registration Date and any agreed extension of it the defendant was obliged to use his best endeavours to procure certification and registration.
*there was no breach of that obligation prior to 31 August 1997, the last agreed date of extension for the Plan Registration Date.
The parties disagree on the question of the rights and obligations of the parties after the expiration of the agreed Plan Registration Date.
(a) the defendant promises to use his best endeavours to procure the certification and registration of the plan by the Plan Registration Date;
(b) those best endeavours must be directed to enabling and not preventing the occurrence of certification and registration within two years of the date of the contract or within the time as extended by agreeement.
They submit that, because the three clauses should be read together, the requirement to use best endeavours should be construed as an absolute obligation and not an obligation limited to a particular date. They argue that this is consistent with the proper construction of the contract and reflects what the law would have implied in any event. They rely on passages from Perri v. Coolangatta Investment Pty Ltd [1982] HCA 29; (1982) 149 CLR 537. In Perri, the High Court considered the application of a special condition in a contract for the sale of land. The condition provided that the contract was "subject to purchasers completing the sale of their property at Lilly Pilly". The vendor purported to rescind the contract on 10 August 1978. The purchasers did not complete the sale of the Lilly Pilly property until 13 June 1979. The plaintiffs rely on the following passages from the judgments of Gibbs C.J. and Mason J. In discussing the operation of the special condition, Gibbs C.J.(at 561) said
"The condition in the present case was not a condition precedent to the formation of the binding contract. It is clear that a binding contract came into existence immediately upon signature, and that the parties to it were from that moment subject to certain obligations. For example, the appellants became liable to pay a deposit. Further, there was implied a promise by the appellants that they would do all that was reasonable to find a buyer for the Lilly Pilly property and to complete a sale to him. "
A little later His Honour went on to comment (at 543)
"Special condition 6 did not fix any time within which the sale of the property at Lilly Pilly was to be completed, nor did it fix a date for completion of the sale. In Aberfoyle Plantations Ltd v. Cheng ... it was said that in such a case the condition must be fulfilled within a reasonable time. This statement is clearly correct; it is entirely consistent with the principle that "An implication of a reasonable time when none is expressly limited is, in general, to be made unless there are indications to the contrary".
"The conclusion to be drawn then is that the clause expresses a condition which is precedent to the appellants' duty to perform the contract, non fulfilment of which entitles them to terminate the contract, rather than as a condition precedent to the formation of the contract. Instead of saying that the condition contains a promissory element I shall prefer to say that the promise is the subject of an implied term which is associated with the condition, but perhaps not forming part of it."
"It (the vendor) seems to be sufficiently protected by relying on its rights to insist on completion of the contract within a reasonable time and by taking such action as it may in that event. Even so, the fact that the clause draws no distinction between the parties and is not expressed to condition only the purchasers' obligation to complete, together with their implied obligation to make all reasonable efforts to sell the Lilly Pilly property, provide strong ground for thinking that the respondent as well as the appellants had a right to terminate on the non-fulfilment of the condition."
"As the contract does not fix a time for completion it would accord with the general principle to say the completion must take place within a reasonable time. In this case what is a reasonable time for completion needs to be measured with special condition 6 in mind. The clause does not specify a time within which the Lilly Pilly property is to be sold. Accordingly it contemplates that there should be such a sale within a reasonable time.:
"The interests of both parties in resolving their respective contingent obligations under the contract require that a limit be placed upon the time during which the contingencies should occur. As there is no reason why a different implication as to time should be made in respect of a contingent condition from the implication made in respect of a promissory condition, a reasonable time is implied in the absence of implications to the contrary: see Reid v. Moreland Timber Co Pty Ltd [(1946) [1946] HCA 48; 73 CLR 1 at 13]."
"In the absence of waiver of the stipulation, the obligations to complete remained contingent upon the completion of the sale of the Lilly Pilly property. Of course, the purchaser had the carriage of the sale of their Lilly Pilly property, and the stipulation imported an obligation upon them to do all that was reasonable on their part in order that a sale of that property might be completed...But that was the extent of their promissory obligation under the stipulation. Their obligation was not to complete a sale of their Lilly Pilly property but to do all that was reasonably to be done to that end. "
"In the confusion of the promissory and contingent effects of the stipulation lie the seeds of difficulty in this case. The risk of confusion is great, because completion of the sale is the usual consequence of taking reasonable steps to that end. But there is a real distinction between the completion of a sale and the steps taken to achieve it, and the observance of a distinction goes far towards avoiding the difficulty. This is not a case where the purchasers promise that a condition precedent to the obligation to complete will be fulfilled. Where such a promise is made, whether by the vendor or purchaser, specific performance may be decreed against the promissor without waiting for fulfilment of the condition. But where the occurrence of an event upon which the obligations to complete are contingent is not promised, the mere non-occurrence of the event is no breach of contract, and the court will not decree completion of the contract absolutely. In such a case, a decree must be limited to the performance of any promise affecting the occurrence of the contingency, and further performance decreed only subject to the contingency:..."
The defendant argues that damages do not lie for non-fulfilment of such a condition, such conditions simply terminate obligations or prevent obligations from arising when the events referred to in them do no occur. There being no promissory element, substantial compliance is not a relevant consideration. The condition is either complied with or it is not (Tricontinental Corp Ltd v. H.D.F.I. Limited (1990) 21 N.S.W.L.R.689). There being no promissory element, issues of whether "time is of the essence" and whether time requirements are essential are of no relevance. In particular, he argues that neither party has promised under cl. 2.1 on its own or in combination with any other clause that the plan of sub-division will be registered prior to the Plan Registration Date.
"We think it is clear that it was not intended by the parties to this contract that the vendor's right should depend upon the will or whim of the purchaser irrespective of what his conduct might be, ..."
"the reason for this rule of construction is to be found in a rule of law designed to prevent a party to a contract from availing himself of his own action or inaction to defeat his contract. As a result of this rule two consequences flow. First, if the event occurs through the action or inaction of one party, the contract is voidable at the option of the other; secondly, if the event is brought about by factors beyond the control of either party, then the contract is voidable at the option of either..."
Amongst other authorities, the Full Court relied upon New Zealand Shipping Company v. Société Des Ateliers et Chantiers De France [1919] A.C.1. There the Lord Chancellor stated (at 6)
"It is a principle of law that no one can in such case take advantage of the existence of the state of things which he himself produced. "
The plaintiffs submit that whether one implies an obligation upon the vendor to use either best or reasonable endeavours, when the vendor received the money to pay the open space requirement fee, he was in a position to perform the last step required to obtain certification from the council. By his inaction, he contrived to create a situation in which that did not occur. It is put that in those circumstances the contract was voidable at the option of the purchasers but was not voidable at the option of the vendor. To permit the latter would be to allow the vendor to avail himself of his own inaction to defeat the contract. Accepting the foregoing as an accurate statement of the law, the defendant by his inaction has, in my view, deprived himself of the right to rescind the contract.
"Thank you for you letter dated 16 October 1997 (received on 21 October 1997)
I have been instructed by my client that he had never requested an extension of the Plan Registration Date to 31 December 1997. Accordingly the Plan Registration Date as agreed between the parties is still 31 August 1997.
With respect to the balcony, I have been instructed that your client was made aware by the selling agent, Greg Norris, that the land value of the balcony would form part of the costs and that your client has been made aware of the approximate costs, reflected in our letter dated 19 August 1997. I have also been instructed to point out that the following costs have not been passed to your client.
* Architectural Fees (including attending site meetings with the agent and your client and meetings with the Town Planning Officers for the City of Port Philip, obtaining the necessary approvals and co-ordinating erection and installation, glazing alterations and other associated building work).
* Surveyors Fees (including necessary alterations to Plan of Sub-division).
My client has advised the $5,000.00 sum for the land value of the balcony offered by your client is grossly disproportionate to its worth.
Mr Etna has instructed he has already proceeded with the construction of the balcony in good faith. In light of the fact that the changes were requested by your client and that we have only recently received a response to our letter of 19 August 1997, my client intends to recover all relevant costs from your client, should your client elect not to continue with the balcony. This includes costs associated with preparing a further Plan of Sub-division, distributing copies to all purchasers and lodging the same at the Land Titles Office.
I am awaiting my client's instructions regarding the size of the main bedroom and the estimated completion date, and will advise you as soon as this is received. "
The letter reveals, it is said, that the defendant was asserting rights relying on the contract and thus the letter also affirmed the contract.
"We are instructed that should we not receive your clients written confirmation within 7 days of the date hereof, our client proposes to bring proceedings in the Supreme Court of Victoria seeking:
1. an injunction to prevent the sale of the property to another person;
2. an order for specific performance of the sale of the property to our client pursuant to Contract of Sale;
3. damages together with interest and costs arising out of the breach by the vendor of his obligations under the contract for sale;
By letter dated 6 March 1998 Phillips Fox replied on behalf of the defendant. After referring to events of 1996, the letter concluded:
"Accordingly all other conditions of the contract of sale remain applicable, including a special condition regarding registration of the plan of sub-division.
My client also instructs that he always has and continues to apply his best endeavours to obtain certification and registration of the sub-division."
By letter dated 25 February 1998 the solicitors for second named plaintiff Letife Arif wrote to the defendant's then solicitors seeking confirmation that he would complete the transaction with her. The letter was in a similar form to that written on behalf of Ersoy Arif referred to above. By letter dated 6 March 1998, the solicitors for the defendant responded as follows:
My client instructs that he always has and continues to apply his best endeavours to obtain certification and registration of the plan of sub-division." (exhibit EA30)
It is put that those letters communicated and in themselves, constituted an election to affirm the contract as opposed to rescinding the contract.
"The point is that where the right to rescind is a continuing one, it is not so readily concluded that the party entitled to rescind has abandoned that right completely as opposed to taking no action to exercise the right at the time in question"
"we do not read that passage from his Honour's judgment [Mason, J. in Sargent v. ASL Developments Ltd] as implying that a party to a contract who is aware either of the right to rescind or of facts giving rise to a right to rescind will necessarily be held to have elected to affirm a contract if he or she acts on the basis that the contract remains on foot. Such an implication is at odds with the notion of being confronted with the necessity of making a choice. In the present case it cannot truly be said that Immer was confronted with the necessity of making a choice at the time the letter in question was written even less that it was abandoning for all time its rights under cl. 7 of the deed."
"It was obvious that at no time prior to Immer's notice of rescission on 25 August had it elected to affirm the contract without the Trust's being able to complete the transfer".
"In a context where the Council had not, in fact, approved the transfer and where the stage had not been reached where Immer was required to make an election either to rescind the contract or to abandon the right to rescind, the forwarding of the documents for settlement did not constitute an election to affirm the contract regardless of whether the council had or had not approved".
In the present case, once the funds had been received, there was nothing further in the nature of a contingent event that could occur to prevent completion. The vendor was in complete control of the situation. It is put that in the present case once the monies had been received there was nothing further that needed to be done by any third party over whom the vendor had no control and thus it could not be argued that having been given a continuing right to rescind he was entitled to reserve his position while performing other obligations under the contract because of any uncertainty as to what other non-parties to the contract might do which might prevent the completion of the contract.
"(1). The plaintiff assumed that a particular legal relationship then existed between the plaintiff and the defendant or expected that a particular legal relationship would exist between them and, in the latter case, the defendant would not be free to withdraw from the expected legal relationship;
(2). The defendant has induced the plaintiff to adopt an assumption or expectation;
(3). The plaintiff acts or abstains from acting in reliance on the assumption or expectation;
(5) The plaintiff's action or inaction will occasion detriment if the assumption or exception is not fulfilled;
(6) The defendant has failed to act to avoid that detriment whether by fulfilling that assumption or expectation or otherwise."
Issues - Specific performance, ready, willing and able
1. That the defendant realise other units at market value, such units to be specified.
2. An order for the application of the net proceeds of sale of the other properties to the debt owed to St George so far as the land sold was not already encumbered in favour of St George or anyone else.
"If Catani Gardens requested that a discharge be provided in respect of a sale for the price for a particular unit in the referable rescinded contract instead of substantially the market value of the subject unit I would not authorise St George to provide such discharge without the consent of each of the guarantors, in my opinion to do so may expose St George to claims from the guarantor."
It emerged in the course of his cross examination, however, that a number of critical documents had not been referred to by him before expressing this view.
(A) The guarantees
Guarantees were executed by the defendant, his wife Vitina Costa, Mario Costa and Johnny Costa. In the guarantees the following clause appeared:
"5.2.1 the obligations and liabilities of a guarantor and the rights of St George under this agreement continue in respect of all money which is or becomes guaranteed money and are not affected by:
(d) St George taking, varying, wholly or partially discharging or otherwise dealing with or losing or impairing any security for guaranteed money; . . .
(o) Anything else which might at law or in equity have the effect of prejudicing or discharging the guarantors liability under this agreement.
The plaintiffs rely on these provisions:
(B) The deed of cross collaterilisation."
"5.5 The said Frank Etna appoints the Lender, its directors, secretaries and general manager for the time being of the lender, severally his true and lawful attorney for the purpose of completing contracts with the purchasers of the units known as 2, 10, 12, 14, 17 and 19 at Beaconsfield Parade West St Kilda in the event of default under any Facility or if Frank Etna is ordered by the Supreme Court to settle the sales, and notwithstanding that the units are not offered for sale by the Lender in its capacity as mortgagee. The borrower and the guarantors consent to the power and authority given pursuant to this clause.
5.6 Notwithstanding the generality of Clause 5.6 (sic.) the Lender shall be entitled to, and the borrower and guarantors consent to, the lender effecting settlement of the sales of:
unit 2 of the property to Ersoy Arif pursuant to a contract of sale dated 26 November 1993 for the sum of $205,000.00;
unit 10 of the property to Peter John Welham pursuant to a contract of sale dated 22 January 1994 for the sum of $225,000.00;
unit 12 of the property to Letife Arif pursuant to a contract of sale dated 2 February 1995 for the sum of $300,000.00;
in accordance with the terms of those contracts of sale ("the contract of sales for units 2, 10, and 12") notwithstanding that Frank Etna has served notice of rescission on the respective purchasers in relation to the contracts of sale for units 2, 10 and 12.
"The lender, its directors, employees and agents from all claims, causes of action, proceedings and any costs and expenses in relation to the decision of the lender to provide, or not to provide, partial discharges of the mortgage in relation to any units at 347 Beaconsfield Parade to any purchasers of the units in that development ("the property") and as against all claims by any mortgagees or chargees of the property as a result of the lender proceeding to effect the sale of units 2, 10 and 12 and associated car park units at the property pursuant to the Contracts of Sale for units 2, 10 and 12 and associated car park units, and the borrower and the guarantors shall keep the lender, its directors, employees and agents indemnified against any such claims or purchases of the units at the Property detailed herein, and claims for damages or otherwise by any mortgagees or chargees of the Property resulting from the Lender proceeding to effect the sale of units 2, 10 and 12 and associated car park units pursuant to the contracts of sale of units 2, 10 and 12."
"These three units [the units in question in these proceedings] are currently valued at $1,135.00 K however contracts entered into "off the plan" only total $750.00K. These properties will be funded in the name of Catani Gardens Investments Pty Ltd against a transfer/assignment of the current mortgage held by Esanda. Deposits for the sale of these three units are held in Trust by Phillips Fox solicitors and should legal action be unsuccessful settlement will proceed and funds of $750.00K will be received. In view of this dispute we have included this amount in our security calculations rather than the higher figure given by the professional valuation."
In another document, headed "General Remarks, Catani Gardens Investments Pty Ltd," containing an analysis and recommendation from the Senior Manager, Andrew Currie, it is stated, (p.4)
"The Costas are aware of the short fall [of the rental stream as against interest and fees]. The medium term objective is to sell all units by the end of 1998. In the interim, servicing will be supplemented by income generated by the Costas core business. The Bank will open an account in the name of Catani Gardens Investments Pty Ltd. The Costas have been made aware of the monthly commitments required to enable servicing of this debt and have undertaken to ensure that sufficient funds are held in an account to enable payment of monthly interest. "
In the course of cross examination, Mr Gall conceded that consent appeared to have already been given by the guarantors to the settlement of the contracts in question and the bank had been directly authorised by them to effect settlement. He also agreed that the bank had obtained indemnities from the guarantors to protect itself in respect of any claims that might arise out of settlement of those contracts. Further, he agreed that it appeared that the potential claims by guarantors referred to in his affidavit had already been covered by the deed because they had the consent of the guarantors. He agreed that in fact the bank cannot be exposed to any such claims by the guarantors. He said that if those documents had been brought to his attention he would not have sworn the above paragraph as it is drawn. He said he was not prepared to adhere to that paragraph. Put to him that, if the court determined that the rescission notices were invalid, the bank, as agent for Frank Etna, would effect settlement of the contracts of sale at contract prices, he replied:
"If that was what my solicitor tells me to do, yes."
I note that there has been no argument advanced on behalf of the defendant to suggest that there would be any basis upon which the lawyers for St George would advise against a discharge of the mortgage.
"Hardships of persons entirely unconnected with the property are immaterial. But I do not think that rule excludes the case of third persons so connected with the defendant that, by reason of some legal or moral duty which he owes them, it would be "highly unreasonable" for the court actively to prevent the defendant from discharging his duty. The circumstances of such a case might, in my opinion, be properly weighed for the purpose of determining the discretion of the courts."
For the purpose of resolving these questions, it is not necessary to reach a conclusion as to whether it would be proper to consider hardship to third persons in this case. The matter in my view can be resolved on the assumption that such a consideration is relevant.
"Specific performance is not a remedy which should lightly be refused when the plaintiff has established the existence of a contract capable of specific performance which the defendant has refused to complete. `It is well established that the Court cannot judicially exercise its discretion by refusing a remedy in a case of the appropriate class unless some sound and recognised reason is shown'. . . . It would be necessary for the defendant to prove that a hardship amounting to an injustice would be inflicted on him by holding him to his bargain and that it would not be reasonable to do so."
The plaintiffs also refer to ANZ Executors v. Humes[1990] VicRp 54; [1990] V.R 615 at 635 and following. The plaintiffs submit that, assuming it be relevant to consider hardship, in this case the hardship pointed to by the defendant must be balanced against any hardship which the plaintiff would suffer if specific performance is refused. The evidence adduced for the defendant, it is said, points to the likelihood that the plaintiffs would not receive damages if compelled to pursue that remedy.
I certify that this and the 46 preceding pages are a true copy of the reasons for judgment of Smith J. the Supreme Court of Victoria delivered on 2 November 1998.
Parissis
Etna [1998] VSC 124
(1982) 149 CLR 537
(1974) 131 CLR 634
(1924) 35 CLR 222