3581/2007 OZY HOMEWARES PTY LIMITED -v- WESGORDON PTY LIMITED
EX TEMPORE JUDGMENT
1 HIS HONOUR: This is an application under s 459G of the Corporations Act 2001 (Cth) to set aside a statutory demand.
2 As is now frequently the case, the application is in the context of the operation of the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act").
3 The statutory demand is dated 21 June 2007 and claims $48,737.79 being the amount of a summary judgment ("the judgment") which the defendant ("Wesgordon") obtained against the plaintiff ("Ozy") in the Local Court at Sutherland, New South Wales on 20 June 2007. Ozy has appealed the judgment. I was informed from the Bar table that a stay of the judgment is proposed to be sought tomorrow in the Local Court.
4 The judgment amount is the sum of two claims, $39,389.35 and $7,863.35, arising respectively out of separate building contracts between Ozy and Wesgordon in relation to work done by the Wesgordon firstly at Salamander Bay and secondly at Charlestown Square.
5 The learned Magistrate applied s 15 of the Act in giving judgment.
6 Under s 15(2) of the Act, Wesgordon was entitled to recover the claimed amounts from Ozy as a debt due to it because it had served a payment claim as provided for in s 13 of the Act in respect of them and Ozy had not responded as provided for in s 14(4) of the Act.
7 The object of the Act, as set out in s 3, is to ensure that a person, in this case Wesgordon, is entitled to receive a progress payment by way of a statutory entitlement regardless of whether the relevant construction contract makes provision for progress payments.
8 Section 15(4)(b) of the Act precluded Ozy from bringing any cross-claim against Wesgordon in those proceedings or from raising any defence in relation to matters arising under the construction contracts in respect of which the claims were made and judgment given.
9 Because of this preclusion, s 32(3) of the Act provides, in effect, that in any proceedings before a court in relation to any matter arising under a construction contract, the court must allow for any payment which has been made in consequence of the operation of the Act and may make such orders for the restitution of any amount so paid.
10 This ensures that the payer ultimately has the opportunity of restoring the balance given that it has had to pay before any dispute on the contract has been ventilated with the payee.
11 In this application, the plaintiff relied on the affidavit evidence of its director Mr David Tonkin.
12 As to the Salamander Bay claim, Mr Tonkin's evidence was that the defendant rendered an invoice dated 10 February 2005 which he says was rendered before the work was completed when the agreement was that the work would only be paid for if that was done to the reasonable satisfaction of a third party, Stockland. He says the work was not completed and he says that Ozy itself ended up having to complete the work after Wesgordon failed to do so.
13 In relation to the Charlestown Square work Mr Tonkin says that the claim is for variations which were not agreed.