© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2007] FCA 1319
Federal Court of Australia
2007-07-01
Besanko J
Original judgment source is linked above.
WHERE MADE: ADELAIDE (VIA VIDEO LINK TO SYDNEY AND ADELAIDE)
Note: Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules
NEW SOUTH WALES DISTRICT REGISTRY NSD 1346 OF 2007
PLACE: CANBERRA (VIA VIDEO LINK TO SYDNEY AND ADELAIDE)
REASONS FOR JUDGMENT 1 On 13 July 2007 Orrcon Operations Pty Ltd ("Orrcon") issued a proceeding in this Court against Capital Steel and Pipe Pty Ltd ("Capital Steel"), Mr Edward Studdy and Westpac Banking Corporation ("Westpac"). 2 Orrcon is a corporation duly registered under the Corporations Act 2001 (Cth) ("Corporations Act") and at all material times traded in the name and style of "Orrcon Operations Pty Ltd" ACN 094 103 090. At all material times, Orrcon engaged in the business of, inter alia, the manufacture of steel products within Australia. Capital Steel is also a corporation duly registered under the Corporations Act. At all material times it traded in the name and style "Capital Steel and Pipe Pty Ltd" ACN 095 843 039 and engaged in the business of, inter alia, trade in steel pipe. At all material times, Mr Studdy has been the sole director and shareholder of Capital Steel. Westpac is a company incorporated under the Bank of New South Wales Act 1850 (NSW) and is a corporation duly registered under the Corporations Act. At all material times, it engaged in the business of banking, including the provision of documentary letters of credit. 3 On 31 July 2007 the Commonwealth Bank of Australia ("Commonwealth Bank") applied to be added as a party to the proceeding. On that day, Branson J made an order that the Commonwealth Bank be joined as a fourth respondent to the application. 4 In its application Orrcon sought the following interlocutory relief against Capital Steel and Westpac:
"4. A mandatory injunction requiring the first respondent [Capital Steel] to countermand all demands made under the letter of credit. 5. An interim injunction restraining the first respondent, until further order of the court, from making any further demand under the letter of credit. 6. An interim injunction restraining the third respondent [Westpac], until further order of the court, from making any payment pursuant to the letter of credit. 7. In the alternative to paragraphs 4, 5 and 6 above, a freezing order pursuant to order 25A, rule 2 restraining the first respondent from disposing of or dealing with any proceeds received by the first respondent under the letter of credit until further order."
5 On 31 July 2007, Branson J also made an order that Orrcon's application for interlocutory relief be listed for hearing on 14 August 2007. The hearing proceeded before me on that day and continued on 15 and 16 August 2007. During the hearing, Orrcon reformulated its application for interlocutory relief, and it now seeks the following relief by way of interlocutory relief: "1. The First Respondent [Capital Steel] be restrained from making any further demand under the Letter of Credit. 2. Third Respondent [Westpac] be restrained from making any payment under the Letter of Credit. 3. The Fourth Respondent [Commonwealth Bank] be restrained, by itself its servants or agents, from calling up, making demand for, or otherwise seeking repayment of, all or any part of the outstanding balance of $12,814,164.85 (together with any interest accrued thereon) of the facility provided by the Fourth Respondent to the First Respondent in the letter of approval date 4 May 2007 from the Fourth Respondent to the First Respondent described as 'Special Project IDLC Amounts Relating to Orrcon - on temporary basis until project is completed' of $18,590,000.00 ('the Facility'). 4. The Fourth Respondent be restrained, by itself, its servants or agents, from exercising any of the securities held by it as security for the Facility, and in particular, the securities listed in the Schedule to the Approval letter dated 4 May 2007 as set out in page 29 to 30 of Exhibit PJG1 to the affidavit of Philip James Grainger sworn on 10 August 2007 in these proceedings. 5. Note that the above orders are not intended to restrain the Fourth Respondent from calling up, making demand for or otherwise seeking repayment of any other facility granted by the Fourth Respondent to the First Respondent, or from exercising any security in respect of any such facility. 6. Note that the Applicant gives to the Court the usual undertaking as to damages with respect to these orders. 7. Note that the usual undertaking as to damages is intended to include any loss caused to the Fourth Respondent by reason of its inability to call up, make demand for or otherwise seek repayment of the Facility or exercise its securities in relation to the Facility until the final hearing of this matter, regardless of the outcome of these proceedings upon a final hearing. 8. Note that the Applicant shall be at liberty to withdraw the undertaking provided by it to the Court as a term of obtaining interlocutory relief upon giving the First and Fourth Respondent 30 days notice in writing, in which event these interlocutory orders will be discharged upon the expiration of that 30 days." 6 I will refer to these orders as the "reformulated orders". The reformulated orders were opposed by Capital Steel and the Commonwealth Bank. Westpac appeared by a solicitor but did not seek to play a part in the hearing. 7 On 22 August 2007 I made an order that the application for interlocutory relief be dismissed. I said that I would deliver reasons and these are my reasons.
Letter of Credit 8 The starting point is the Letter of Credit referred to in the interlocutory orders sought in the application and the reformulated orders. It was issued by Westpac on or about 22 December 2006 and relevantly provides: "To: COMMONWEALTH BANK OF AUSTRALIA SYDNEY … Form of Doc Credit IRREVOCABLE Doc Credit Number SD3BM872029 Date of Issue 061222 Applicable Rules UCPURR LATEST VERSION Expiry Date 070630 Place IN THE BENEFICIARY'S COUNTRY Applicant Orrcon Operations Pty Ltd Beneficiary CAPITAL STEEL AND PIPE PTY LTD … Amount Currency AUD Amount 19.337.670 … Available with/by ANY BANK BY NEGOTIATION Drafts at … 120 DAYS FROM BILL OF LADING DATE Drawee WESTPAC BANKING CORPORATION SYDNEY, AUSTRALIA Partial Shipments PARTIAL SHIPMENTS ARE ALLOWED … Latest Date of Ship 070620 Descript of Goods SPIRAL STEEL PIPE TO AS1579 … Documents required DOCUMENTS REQUIRED IN DUPLICATE UNLESS OTHERWISE STATED.
The applicant's claim 10 The following is a summary of Orrcon's claim as set out in its statement of claim. 11 Dong Bu Steel Co Limited ("Dongbu") is and was at all material times a Korean manufacturer of steel products including spiral steel pipes. As I understand it, Dongbu's parent company is and was at all material times Daewoo International Corp ("Daewoo") of Seoul, Korea. 12 In October 2006 Orrcon engaged in negotiations with the State of Queensland for the supply of steel pipe by Orrcon to the State of Queensland. The pipe was to be used in a project to be undertaken by the State of Queensland called the "South East Queensland Water Grid Projects" ("SEQ Water Grid Projects"). 13 In November 2006 Mr Studdy, for and on behalf of Capital Steel, engaged in negotiations with Orrcon for the supply of steel pipe by Capital Steel to Orrcon to be used in the SEQ Water Grid Projects. The steel pipe was to be manufactured by Dongbu. Orrcon alleges that it had various communications with Mr Studdy and Capital Steel between 27 October 2006 and 21 November 2006. Those communications consisted of electronic messages, specifications and telephone conversations. As a whole they are referred to in Orrcon's statement of claim as "the November conduct". One important aspect of the communications in the circumstances of Orrcon's claim is the reference to the yield strength (in terms of megapascals (MPa)) that the pipe was to meet. 14 Orrcon entered into a contract with Capital Steel "for the supply of 33,000 metres each of 960 mm and 1086 mm x 8 mm spiral steel pipe manufactured by Dongbu to AS1579 with 300 MPa yield strength and with mill test certificates". The communications alleged to make up the contract are set out in the statement of claim. It is not necessary to set them out in these reasons. At the time the contract was made, Capital Steel and Mr Studdy knew that the pipe to be supplied under the contract was being acquired by Orrcon for re-supply to the State of Queensland for the SEQ Water Grid Projects. 15 The terms of the contract between Orrcon and Capital Steel are said to be as follows: 1. The price of the pipe was AUD19,337,670 (exclusive of GST). 2. The pipe was to be delivered in five shipments ex-South Korea at the end of January, February, March, April and May 2007 to Port Kembla, Australia. 3. Payment was to be made 120 days from the provision of clean bills of lading. 4. Orrcon was to establish an irrevocable letter of credit for the contract price. 5. The pipe was to comply with the specifications and, in particular, certain minimum technical requirements. 6. If less than 50 per cent of the pipe length formed from any heat, coil or heat treat lot complied with all requirements of the specification, Orrcon was entitled to reject all the pipe from the affected heat, coil or heat treat lot. 7. Pipe quality and project delivery were of the essence. 16 As will become clear, Orrcon's right to reject pipe (term 6 [15] above) is important. 17 It is alleged by Orrcon that it was a term and condition of the contract that Capital Steel was not entitled to make a claim for payment under the letter of credit unless all of the pipe delivered complied with the specification and AS1579 in all respects. Orrcon alleges that such a term and condition arises as a matter of construction from the description and specification of the pipe to be delivered and the requirement that payment was not due unless the pipe was delivered. In the alternative, Orrcon alleges that such a term arises by implication and pleads the well-known factors for the implication of a contractual term (see Codelfa Construction Proprietary Limited v State Rail Authority of New South Wales (1982) 149 CLR 337 ("Codelfa"). 18 In December 2006 and in accordance with the specification, a pre-production meeting was convened at Dongbu's manufacturing plant in Korea for the purpose of reviewing the quality plan and manufacturing procedures to be followed during production of the pipe. The meeting was attended by representatives of Capital Steel, Dongbu and Orrcon. It is said that during the meeting the representatives of Orrcon were told of certain aspects of the manufacturing process which bore upon the minimum yield strength of the pipe and that Pohang Iron and Steel Company (otherwise referred to as "Posco") was to provide the raw material, hot rolled coil. There was discussion about the minimum yield strength of similar sized water pipes manufactured by Dongbu. There then followed communications between Capital Steel and Orrcon, and the upshot of those communications for present purposes was that Orrcon agreed to what it alleges were reduced minimum mechanical properties, the most important one of which was the proposed minimum for yield strength of the steel pipe of 270 MPa (aim 290 MPa). I note that Capital Steel asserts that a figure of 250 MPa was agreed, but it accepts that question is one for trial. 19 On 11 December 2006 Orrcon entered into a formal contract with the State of Queensland for the supply of pipe for the SEQ Water Grid Projects. It alleges that it did so relying on the November conduct and the representations at or about the time of the pre‑production meeting. Also relying on those matters it alleges that it instructed Westpac to issue an irrevocable import documentary credit number SD3BM872029 in the amount of AUD19,337,670 in favour of Capital Steel. That was done on 21 December 2006 and the letter of credit was said to contain the following terms: 1. Partial shipments were permitted. 2. Credit was payable within 120 days from the bill of lading date. 3. The latest date of shipment was 20 June 2007. 4. The date of expiry was 11 July 2007. 5. The documents required to be presented to Westpac were a full duplicate set of clean "on board" or "shipped", negotiable marine bill of lading to order blank endorsed marked "freight pre-paid" and commercial invoices. 6. The payment documents must be presented to Westpac within 21 days after issue of the transport document but within the validity of the letter of credit. 20 Orrcon instructed Westpac to amend the letter of credit to increase the document presentation period from 10 to 21 days and to extend the expiry date from 30 June 2007 to 11 July 2007. 21 On 22 February 2007, Orrcon sent Capital Steel a letter dated 5 February 2007 confirming the terms of the contract. 22 Three shipments of pipe were made by Capital Steel. Orrcon says the pipes delivered were defective in that they did not comply with the specification or AS1579. The particulars of non-compliance are that the pipe did not have the reduced minimum specified mechanical properties because the yield strength of the pipe was consistently less than specified. Orrcon also alleges that the yield strength of the coils from which the pipes were manufactured were significantly variable through each coil. Details of the shipments and the invoices rendered by Capital Steel as alleged by Orrcon are as follows: First shipment: On about 23 February 2007, Capital Steel shipped 500 lengths of each size of the pipe from Korea and on or about 9 March 2007 Capital Steel rendered tax invoice number 2371 for AUD4,305,632.10 (including GST) to Orrcon for purported delivery of the first shipment. Second shipment: On or about 14 March 2007, Capital Steel shipped 476 lengths of each size of the pipe from Korea and on or about 30 March 2007 Capital Steel rendered tax invoice number 2381 for AUD4,133,114.77 (including GST) to Orrcon for purported delivery of the second shipment. Third shipment: On or about 14 April 2007, Capital Steel shipped 501 lengths of each size of the pipe from Korea and on or about 18 April 2007 Capital Steel rendered tax invoice number 2424 for AUD4,346,689.83 (including GST) to Orrcon for purported delivery of the third shipment. 23 It is alleged that Capital Steel presented documents to Westpac purporting to draw on the letter of credit for each of the three shipments. The documents consisted of invoices, packing lists, original bills of lading and mill test certificates. It is not necessary for me to set out the details of the documents presented. On 14 March 2007, Capital Steel presented documents to Westpac purporting to draw on the letter of credit for the first shipment and on the same day and in reliance of the authenticity of the first shipment payment documents, Westpac issued Orrcon with a schedule of term drawing under documentary credit for AUD4,334,360.25 with a maturity date for payment to Capital Steel of 25 June 2007. On 10 April 2007, Capital Steel presented documents to Westpac purporting to draw on the letter of credit for the second shipment and on the same day and in reliance of the authenticity of the second shipment payment documents, Westpac issued Orrcon with a schedule of term drawing under documentary credit for AUD4,133,114.77 with a maturity date for payment to Capital Steel of 12 July 2007. The maturity dates in relation to the first and second schedules were extended to 24 August and 10 September 2007 respectively. On 9 May 2007, Capital Steel presented documents to Westpac purporting to draw on the letter of credit for the third shipment and, on the same day, in reliance on the authenticity of the third shipment payment documents, Westpac issued Orrcon with a schedule of term drawing under documentary credit for AUD4,346,689.83 with a maturity date to Capital Steel of 11 October 2007. 24 Orrcon alleges that conduct by Capital Steel in November 2006 and at the meeting in December was misleading or deceptive or likely to mislead or deceive in contravention of s 52 of the Trade Practices Act 1974 (Cth) ("TPA"). It alleges that Capital Steel knew or ought to have known that Dongbu intended to source its hot rolled coil from Tangshan Iron and Steel Co Limited ("Tangshan") rather than Posco. It alleges that the pipes delivered by Capital Steel were defective and did not comply with the specification or AS1579. Further, or in the alternative, Orrcon alleges that the first, second and third purported drawings down on the Westpac letter of credit (or any one of them) was conduct by Capital Steel that was misleading or deceptive or likely to mislead or deceive in contravention of s 52 of the TPA. It is unnecessary for me to set out the details of this plea. It is sufficient to say that it relates to the accuracy of the mill test certificates in terms of the pipe actually delivered. Orrcon alleges that Mr Studdy aided, abetted, counselled or procured Capital Steel's contravention of s 52 and was directly or indirectly, knowingly concerned in or party to that contravention within the meaning of s 75B of the Trade Practices Act. 25 Orrcon makes a further plea which is important in terms of its present claim for interlocutory relief. It is a plea of unconscionable conduct within s 51AA of the Trade Practices Act 1974 (Cth) and it is in the following terms: "42. Further and in the alternative, by its knowing failure to deliver pipe that complied with the specification and AS1579 in breach of its obligations under the contract but nevertheless making and seeking to rely on the first, second and third purported drawings down on the letter of credit is particularised in paragraphs 31, 33 and 37 above, in circumstances where it lacks the financial capacity to repay those drawings down, Capital Steel has engaged and is engaging in unconscionable conduct within the meaning of s 51AA of the Trade Practices Act 1974 (Cth)." 26 A good deal of the argument before me focused on whether Orrcon had established a serious question to be tried in terms of that plea. 27 Orrcon also alleges that by reason of the delivery of defective pipe, the failure to deliver the pipe on time or at all and the making of the first, second and third purported drawings down on the Westpac letter of credit, Capital Steel had breached its contract with Orrcon. Those breaches were such that Orrcon was entitled to terminate the contract which it did by letter dated 12 July 2007. 28 Orrcon alleges that it has suffered loss and damages as a result and it claims the following: "1. Orrcon has been unable to supply the pipe under the head contract and thereby Orrcon has lost profits of AUD9,376,781. 2. Orrcon has incurred additional costs of AUD2,682,453.14 comprising: (a) testing costs of AUD1,297,770.02; (b) handling costs of AUD647,807.54; (c) transportation costs of AUD657,134.70; (d) travelling costs of AUD79,740.88." 29 In terms of final relief, Orrcon claims various declarations, injunctions and damages. Importantly, it claims a mandatory injunction requiring Capital Steel to countermand the drawing requests it has made pursuant to the Westpac letter of credit and to consent to the cancellation of the Westpac letter of credit. It also seeks an injunction restraining Capital Steel from making any further demands on Westpac pursuant to the Westpac letter of credit and an injunction permanently restraining Westpac from making payments to Capital Steel pursuant to the Westpac letter of credit.
The Commonwealth Bank 30 The Commonwealth Bank was joined as a party to the proceeding and is the fourth respondent. It is convenient at this point to outline briefly the basis upon which it claims an interest in the proceeding. 31 The Commonwealth Bank has been the principal banker to Capital Steel since approximately October 2005. Among the various facilities that it has extended to Capital Steel is a trade finance facility for the purpose of supporting Capital Steel's international trade and related domestic transactions. 32 It seems that on 14 March, 10 April and 9 May 2007, Westpac informed the Commonwealth Bank in the latter's capacity as advising bank that the Westpac letter of credit drawings had been accepted in respect of the subject amounts and informed the Commonwealth Bank that it would remit those respective amounts at the respective maturity dates. The maturity dates have been extended by the consent of all parties and no moneys have as yet been remitted by Westpac, as the maturity dates have not yet arrived. However, the Commonwealth Bank has advanced discounted amounts to Capital Steel on the faith of the communications it received from Westpac and those amounts have been used to pay Dongbu or its holding company. The Commonwealth Bank asserts, and this does not appear to be in dispute, that if Westpac does not make payment under the Westpac letter of credit it may need to protect its position by making a demand on Capital Steel. It appears that Capital Steel would not have the funds to meet that demand. The Commonwealth Bank applied to be joined because it had an interest in whether or not interlocutory relief was granted and because it wished to be in a position to "address the Court on the broader issue of policy considerations relating to the integrity of the letters of credit". 33 Mr Phillip Grainger is an employee of the Commonwealth Bank. He is a manager, trade - services, sales. He was involved in the provision of a facility to Capital Steel in relation to the pipe to be purchased by it and to be supplied by it to Orrcon. At the request of Capital Steel the Commonwealth Bank issued letters of credit in favour of Daewoo. Mr Grainger relied on the Westpac letter of credit and decided that it was unnecessary for Capital Steel to provide further security for the facility which it then sought. Had Mr Grainger thought that there was any risk that Westpac would not pay out in accordance with the Westpac letter of credit, he would not have authorised the granting of a facility to Capital Steel without first obtaining further tangible security. Mr Grainger gave evidence as to the importance of the integrity of the letters of credit being preserved. 34 Mr Grainger gave details of the process whereby the Commonwealth Bank granted a temporary increase in the trade finance facility it provided to Capital Steel. In the context of that increase, on 2 January 2007 Mr Studdy, for and on behalf of Capital Steel, signed what is referred to as a request for assignment of proceeds. The key clause in the document signed by Mr Studdy on that day is as follows: "Capital Steel and Pipe Pty Limited being the beneficiary of Irrevocable Documentary Credit No: SD3BM872029 established by Westpac Banking Corporation, Sydney, dated 22 December 2006, which documentary credit is held by the Commonwealth Bank of Australia (CBA), Trade Services, Level 3, 120 Pitt Street, Sydney, hereby irrevocably authorises the CBA, upon their receipt of clear proceeds from drawings under the documentary credit to apply the funds in the consideration of any amount that may be payable (or having already been paid) with regard to the documentary credit(s) that Capital Steel and Pipe Pty Limited seeks to have established in favour of Daewoo International Corp and/or Dongbu Steel Co Limited, of Korea." 35 That document was said to have been given in response to a condition of the facility provided by the Commonwealth Bank to Capital Steel to the effect that Capital Steel was to sign a letter "assigning proceeds of the Westpac letters of credit (issued by Orrcon in favour of Capital Steel and Pipe Pty Ltd) to the CBA". 36 On 9 January 2007, the Commonwealth Bank issued an import documentary letter of credit (IDLC No 3523722255) in favour of the supplier of the first shipment of steel, namely Daewoo International Corp of Seoul, Korea, ("Daewoo") in the sum of USD1,922,915. A condition of the Commonwealth Bank's approval to the issue of the documentary letter of credit in favour of Daewoo was the prior receipt or advice of the Westpac documentary letter of credit from Orrcon in favour of Capital Steel. Mr Grainger states that had it not been for the receipt of the Westpac letter of credit, he would not have authorised the issue of the letter of credit in favour of Capital Steel's Korean supplier. The Commonwealth Bank has paid Daewoo under the letter of credit. The Commonwealth Bank has forwarded to Westpac the documents required under the Westpac letter of credit. That was done on 8 March 2007. On 13 March 2007 the Commonwealth Bank was advised by Westpac that it had received acceptance from Orrcon of an amended amount of AUD4,334,360.25. On 16 March 2007, Westpac confirmed in writing that at maturity it would remit the relevant amount to the Commonwealth Bank. A similar process occurred in relation to the second and third shipments. Details are set out below ([74]-[82]). 37 Mr Grainger gave evidence to the effect that if the Court granted the relief sought by Orrcon and restrained payment by Westpac of the amounts payable under the Westpac letter of credit then the Commonwealth Bank would have an unsecured loan exposure to Capital Steel of approximately AUD13,000,000. Although the Commonwealth Bank has security securing the indebtedness of Capital Steel, that would not be sufficient to secure payment of such an amount. If interlocutory relief is granted, the Commonwealth Bank may consider taking control of Capital Steel and taking such other steps as may be available to it to minimise its exposure by realising such tangible security as it holds. 38 Although this is an interlocutory application, it must be said that by and large the evidence of Mr Grainger as set out above was not challenged by Orrcon. In any event, most of the matters asserted by the Commonwealth Bank are established by the documents put before me. 39 It was the evidence of the Commonwealth Bank which appears to have prompted Orrcon to put forward the reformulated orders (see [5] above). The third and fourth orders are designed to prevent prejudice to Capital Steel resulting from the first and second orders. The seventh order is designed to prevent prejudice to the Commonwealth Bank because it is intended to provide that any loss suffered by the Bank will be paid by Orrcon irrespective of whether or not Orrcon is successful in the proceeding. I will discuss these matters in detail in the context of the balance of convenience.
Issues on the application for interlocutory relief 40 The test for the grant of an interlocutory injunction was most recently considered by the High Court in Australian Broadcasting Corporation v O'Neill (2006) 80 ALJR 1672. I refer to the observations of Gleeson CJ and Crennan J at 1682-1683 [19] and Gummow and Hayne JJ at 1691-1692 [65]-[72]. 41 Capital Steel submits that Orrcon has not established that there is a serious question to be tried that the steel pipe Capital Steel supplied under the contract was defective in the sense that it did not comply with the terms of the contract between it and Orrcon. If a serious question to be tried is not established in relation to that matter then, it is submitted by Capital Steel, Orrcon's case falls away. Further, or in the alternative, Capital Steel submits that Orrcon has not established that there is a serious question to be tried that relief would be granted restraining payment under the letter of credit. The focus of the argument here was that there was not a serious question to be tried that Capital Steel has been guilty of unconscionable conduct within s 51AA of the TPA. Further, or in the alternative, Capital Steel submits that the balance of convenience favours refusing the interlocutory relief sought by Orrcon.
A serious question to be tried in relation to the allegation that the pipe was defective 42 Orrcon relied on evidence from Dr Graham Powell who is a research metallurgist. He has prepared a report dated July 2007 and a supplementary report dated August 2007. Orrcon also relied on evidence from Dr John Field who is a statistical consultant. He has prepared a report dated 9 August 2007 and a supplementary report dated 12 August 2007. Orrcon also relied on evidence from Mr Victor Konstantinoff who holds a Bachelor of Science degree and is the branch operations manager employed by ETRS Pty Ltd ("ETRS"). 43 The evidence before me is to the effect that ETRS is a specialist testing laboratory that specialises in providing non-destructive inspection and testing, metallurgical testing and analysis, failure investigation and condition assessment. Tensile testing of materials, including steel, is a common procedure undertaken by ETRS and the provision of that service is one of ETRS's key capabilities. 44 On 26 March 2007, Orrcon engaged ETRS to conduct testing on samples of steel pipe provided to it. ETRS conducted tests on the samples provided by Orrcon to ETRS in May 2007. The testing was of transverse pieces of the sample pipes. Mr Konstantinoff identified the test reports produced by ETRS. 45 I allowed brief cross-examination of Mr Konstantinoff by Capital Steel. It transpires that ETRS also performed tests on samples of steel pipe provided by Orrcon throughout April 2007. It seems that ETRS misunderstood its instructions and in April carried out tests of longitudinal pieces of the sample pipes rather than transverse pieces. 46 Dr Powell was provided with the ETRS test reports dated May 2007. He was not provided with the test reports dated April 2007. I allowed brief cross-examination of Dr Powell. It was put to him by counsel for Capital Steel that he would need to "withdraw" the conclusion reached in his report until such time as he had had the opportunity to consider the test reports carried out in April 2007. He did not agree with that proposition. He said that longitudinal results yield stress results that are always larger than the transverse results. He said that the transverse results are critical. He referred to the change in the microstructure of the steel and what happens in the rolling of the steel from the slab to the coil and the effect the rolling has on the segregation in the coil. The transverse results are lower than the longitudinal results. Dr Powell agreed that he did not consider whether the samples were statistically representative. 47 Dr John Field was given the results of the sample tests carried out by ETRS. Based on the results of the sample tests, he was asked to estimate the proportion of the overall number of pipes which did not comply with the contractual provision as to unit strength. He expressed a conclusion as follows: "Subject to the reservations about the representativeness of the sample expressed in the previous section, it can be stated with 95 per cent confidence that at least 62.5 per cent of the pipes delivered had yield strength below 270 MPa. Thus, the delivery does not meet a minimum yield strength specification of 270 MPa." 48 Dr Field was questioned by counsel for Capital Steel on whether the sample he relied on for the purposes of drawing a conclusion as to yield strength between pipes within a coil was sufficient. He agreed that had he been given certain information as to variations between pipes within a coil, he might have concluded that it was not safe to assume that the testing which took place predominantly from the middle of the coil was in fact representative of yield strength of the entire coil. 49 Capital Steel submitted that the reservations expressed by Dr Field were such that Orrcon had not established a serious question to be tried that the pipes delivered to it by Capital Steel did not comply with the contract. I do not agree. In my opinion Capital Steel's challenges to the expert evidence put forward by Orrcon are matters to be determined at trial. There appear to be some difficult factual issues which can only be properly determined at trial. In my opinion, the evidence put forward by Orrcon establishes that there is a serious question to be tried that the pipes delivered by Capital Steel to Orrcon did not meet the terms of the contract alleged by Orrcon.
A serious question to be tried in relation to the allegation of unconscionable conduct 50 Section 51AA of the TPA provides as follows: "(1) A corporation must not, in trade or commerce, engage in conduct that is unconscionable within the meaning of the unwritten law, from time to time, of the State and Territories. (2) This section does not apply to conduct that is prohibited by s 51AB or s 51 AC." 51 Orrcon submits, and Capital Steel denies, that there is a serious question to be tried that Capital Steel, in trade or commerce, engaged in conduct that was unconscionable within the meaning of the unwritten law, from time to time, of the State or Territories and that it is entitled to injunctive relief against Capital Steel, Westpac and the Commonwealth Bank under ss 80 and 87 of the TPA. The factual elements of Orrcon's plea of unconscionable conduct which is set out in [25] above are as follows: 1. Capital Steel's knowing failure to deliver steel pipe that complied with the specification and AS1579 in breach of its obligations under the contract; and 2. Capital Steel making and seeking to rely on the first, second and third purported drawings down on the letter of credit; and 3. Capital Steel doing those things in circumstances where it lacked the financial capacity to repay those drawings down. 52 Orrcon submits that as a matter of law a category of unconscionable conduct (relevant to this case) is the insistence on the strict application of legal rights in circumstances where to do so is regarded, on the facts of the particular case, to be harsh or oppressive. 53 Orrcon's plea of conscionable conduct within s 51AA of the TPA raises four issues. They are as follows: 1. What is the relationship between the autonomy principle and unconscionable conduct within s 51AA of the TPA? 2. Is it arguable as a matter of law that the facts as pleaded by Orrcon, if established, constitute unconscionable conduct within s 51AA? 3. Is there a serious question to be tried that Orrcon will establish the facts it alleges amount to unconscionable conduct and, in particular, factual elements 1 and 3 in [51] above? 4. Is there a serious question to be tried to the effect that, assuming unconscionable conduct of the type pleaded is established by Orrcon, relief in the nature of injunctions will be granted restraining Capital Steel from making any further demand under the Westpac letter of credit and Westpac from making any payment under the Westpac letter of credit having regard to the interest of the Commonwealth Bank. 54 I will address each of these questions in turn.
Again, it is trite law that in contract (4), with which alone the instant appeal is directly concerned, the parties to it, the seller and the confirming bank, 'deal in documents and not in goods,' as article 8 of the Uniform Customs puts it. If, on their face, the documents presented to the confirming bank by the seller conform with the requirements of the credit as notified to him by the confirming bank, that bank is under a contractual obligation to the seller to honour the credit, notwithstanding that the bank has knowledge that the seller at the time of presentation of the conforming documents is alleged by the buyer to have, and in fact has already, committed a breach of his contract with the buyer for the sale of the goods to which the documents appear on their face to relate, that would have entitled the buyer to treat the contract of sale as rescinded and to reject the goods and refuse to pay the seller the purchase price. The whole commercial purpose for which the system of confirmed irrevocable documentary credits has been developed in international trade is to give to the seller an assured right to be paid before he parts with control of the goods that does not permit of any dispute with the buyer as to the performance of the contract of sale being used as a ground for non-payment or reduction or deferment of payment." 57 Lord Diplock said that there was one established exception to the general statement of principle as to the contractual obligations of the confirming bank to the seller and that was where the seller, "for the purpose of drawing on the credit, fraudulently presents to the confirming bank's documents that contain, expressly or by implication, material representations of fact that to his knowledge are untrue" (at 183). Capital Steel accepts that there are two other exceptions and they are breach of a negative stipulation and unconscionable conduct within s 51AA of the TPA. That concession by Capital Steel appears to be correct having regard to the authorities. 58 In view of Capital Steel's concession, the real issue in this case is whether Orrcon has established a serious question to be tried that Capital Steel has been guilty of unconscionable conduct.
A serious question to be tried in relation to other allegations 97 Before leaving the issue of whether there is a serious question to be tried, I should mention that in the course of submissions Orrcon suggested that the breach of a negative stipulation exception to the autonomy principle may be relevant. Orrcon alleged in its statement of claim that it was a term and condition of the contract that Capital Steel was not entitled to make a claim for payment under the Westpac letter of credit unless all of the pipe delivered complied with the specification and AS1579 in all respects. The Westpac letter of credit refers only to AS1579 and that Australian Standard does not refer to the minimum yield strength alleged by Orrcon. I agree with the submission of Capital Steel that none of the documents which are alleged to form the steel contract contain the words pleaded and, accordingly, there is no express term to the effect alleged. Nor do I think it can be said that there is a serious question to be tried that there was an implied term to that effect, having regard to the factors referred to in Codelfa. 98 There was also a suggestion in Orrcon's written submissions that the presentation of mill test certificates to Westpac was misleading or deceptive conduct and that a contravention of s 52 of the TPA may be sufficient to found interlocutory relief. That submission was not developed in any detail by Orrcon and it is difficult to see how it could succeed in light of the fact that, among other things, mill test certificates are not necessary documents under the Westpac letter of credit.
The balance of convenience 99 I will consider first the balance of convenience having regard to the interlocutory orders as sought in the application. I will then consider the balance of convenience having regard to the reformulated orders. 100 Of the four orders sought by Orrcon the freezing order (that is, paragraph 7) was not pressed at the hearing. The first injunction sought is a mandatory injunction. A mandatory interlocutory injunction is rarely granted because usually an interlocutory injunction is ordered to preserve the status quo not to alter it (Meagher, Gummow and Lehane, Equity Doctrine and Remedies, 4th ed at 788). The second injunction prohibiting Capital Steel from making any further demand under the Westpac letter of credit is probably misconceived because Capital Steel is not required to take any further action under the Westpac letter of credit. Absent a court order Westpac is under an irrevocable and unconditional obligation to pay the stated amounts on the stated dates without any further action on the part of Capital Steel. The third injunction prohibiting Westpac from making any payment under the Westpac letter of credit would probably lead to Orrcon amending its Statement of Claim to claim a declaration that it is not bound to pay Capital Steel the price under the contract (or a substantial part of it) and Capital Steel bringing a claim for the payment of the price. 101 Although there was no specific evidence before me as to Orrcon's financial position, the suggestion was that Orrcon has substantial financial resources. There was evidence before me that Capital Steel would not have the financial resources to pay a substantial amount to Orrcon. Orrcon submits that payment now under the Westpac letter of credit would leave it with no effective remedy against Capital Steel. It would have paid the price under the contract but any set-off or cross claim it has against Capital Steel would be of no real value because of Capital Steel's financial position and the fact that the moneys under the Westpac letter of credit would have been paid to the Commonwealth Bank. On the face of it that is a weighty consideration in favour of Orrcon. However, as against that consideration there are a number of matters suggesting that interlocutory relief should not be granted. 102 The most important consideration is the fact that Orrcon gave the Westpac letter of credit. It agreed to the issuing of an irrevocable letter of credit and that it would be governed by the UCP rules. The UCP rules make it clear that the letter of credit transaction is quite separate from the underlying sale of goods transaction. Orrcon had dealt with Capital Steel in the past and it had the choice whether it would ask Westpac to issue the letter of credit. The letter of credit was in fact designed to give Capital Steel the security of knowing that it would be paid the price for the goods and avoid the difficulty of not being paid because Orrcon asserts that the goods delivered do not comply with the contract. Furthermore, Orrcon instructed Westpac to accept the necessary documents under the letter of credit. 103 Another important consideration is the prejudice caused to Capital Steel and the Commonwealth Bank if an injunction restraining Westpac from making any payment under the Westpac letter of credit is made. Capital Steel presently owes the Commonwealth Bank over $12,000,000 and, absent payment under the Westpac letter of credit, it does not have the resources to meet that liability. The Commonwealth Bank may well take action against Capital Steel and guarantors and mortgagors under the securities it holds. It may place Capital Steel into receivership. It may prove very difficult later to unravel action taken or to restore the status quo should that be the appropriate course. 104 As far as the Commonwealth Bank is concerned it is an innocent party and Orrcon did not contend otherwise. It advanced substantial money on the faith of the Westpac letter of credit. If Westpac is restrained from paying moneys under the Westpac letter of credit then the Commonwealth Bank will or may be involved in expensive and time-consuming action in order to protect its position as best it can. 105 Two other matters should be mentioned. They are not of critical significance in terms of the balance of convenience, but at the same time they are not irrelevant. First, Orrcon has the steel pipes which were the subject of the three shipments. It was asserted that the contract between Orrcon and the State of Queensland had been, or was likely to be, terminated. On the evidence it is not possible for me to make any findings, even on a serious question to be tried basis, on that issue. Even if I assume that Orrcon's case on that issue is correct, Orrcon has the steel pipes. They may have no value, some value or considerable value. On the evidence I simply do not know. Secondly, Capital Steel has delivered goods to Orrcon pursuant to unrelated transactions. It has not been paid by Orrcon and it asserts that Orrcon owes it in the region of $1,400,000-$1,500,000. Orrcon has not provided an explanation for not paying for the goods at least as far as the particular transactions are concerned. Those facts have been established on a serious question to be tried basis. Those two matters although, as I have said, far from being of critical significance in terms of the balance of convenience, show that Orrcon's loss, if interlocutory relief is refused, may not be as great as it suggests. 106 As far as the interlocutory orders as originally formulated are concerned, the balance of convenience clearly favours the refusal of those orders sought. 107 The reformulated orders are an attempt by Orrcon to overcome the prejudice to Capital Steel and the Commonwealth Bank if Westpac is restrained from making any payments under the Westpac letter of credit. The claim for a mandatory injunction is not pursued. The prejudice to Capital Steel is dealt with by prohibiting the Commonwealth Bank from claiming its debt from Capital Steel and from taking any action under its securities in relation to that debt. The prejudice to the Commonwealth Bank is dealt with by Orrcon's undertaking to pay damages. This undertaking was initially proffered in the usual terms, but counsel for the Commonwealth Bank pointed out that his client was an innocent party and irrespective of whether or not Orrcon is successful may suffer substantial loss by way of a diminution in the value of the securities between the interlocutory orders and trial. It would seem that submission led Orrcon to amend its reformulated orders by adding the words, "regardless of the outcome of these proceedings upon a final hearing". 108 Capital Steel submits that the Court did not have the power to make orders against the Commonwealth Bank and it referred to Australian Broadcasting Authority v Lenah Game Meats Pty Limited (2001) 208 CLR 199, Cardile v LED Builders Pty Limited (1999) 198 CLR 380, s 23 Federal Court of Australia Act 1976 (Cth) and O 25A r 5(5) of the Federal Court Rules. I do not need to consider that question. On any view, the reformulated orders involve a substantial interference in the commercial relationship between Capital Steel and the Commonwealth Bank. Even if the orders cover all contingencies in terms of possible loss to the Commonwealth Bank, and I am not completely satisfied that is the case, there will be time and expense involved in establishing any loss which may be suffered. Although the reformulated orders go some way towards addressing the prejudice to Capital Steel and the Commonwealth Bank if interlocutory injunctions are granted, the balance of convenience still favours the refusal of relief.
Conclusion 109 It was for these reasons that on 22 August 2007 I dismissed Orrcon's application for interlocutory relief. I certify that the preceding one hundred and nine (109) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Besanko.
Counsel for the Applicant: Mr F M Douglas QC and Mr R J Cheney
Solicitor for the Applicant: Fisher Jeffries
Counsel for the First and Second Respondents: Mr A G Bell SC with Mr A J McInerney and Mr D Barnett
Solicitor for the First and Second Respondents: Foulsham & Geddes
Solicitor for the Third Respondent Minter Ellison
Counsel for the Fourth Respondent Mr R G Forster SC with Mr P J Dowdy
Solicitor for the Fourth Respondent John O'Sullivan
Date of Hearing: 14, 15 and 16 August 2007
Date of Judgment: 29 August 2007
Orrcon Operations Pty Ltd
Capital Steel & Pipe Pty Limited
(2001) 208 CLR 199
(2006) 80 ALJR 1672
(2000) 96 FCR 491
(2002) 117 FCR 301
(1999) 198 CLR 380
(1983) 153 CLR 438
(1982) 149 CLR 337
(1983) 152 CLR 406
(1988) 165 CLR 489
(2003) 217 CLR 315
(1998) 194 CLR 457
(1988) 194 CLR 395