© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2019] NSWDC 796
District Court of NSW
2019-10-23
Original judgment source is linked above.
Introduction
Procedural background
Have the proceedings completed?
The stated case
The relevant law
Consideration
Particular 14
Particular 16
Particular 17(a)
Particular 17(b)
Particular 17(b)(ii)
Particular 17(b)(iii)&(iv)
Particular 17(b)(v)
Particular 17(b)(vi)
Causation
Conclusion
Orders
A. Particular 14 - Pleaded Risk
B. Particular 16 - Reduction of the depth of the water 5. Did I apply the correct legal principles as to the test in relation to whether a pleaded measure was reasonably practicable, when I found at [254] of the Judgment that the measure pleaded in [16] of the Amended Summons was not a reasonably practicable measure, in light of my findings that (references are to paragraph numbers in the Judgment): a. on 10 June 2014 Mr Patten believed that reducing the water level in the 8820 North sump was a matter of some urgency [98]; b. on 11 June 2014 Mr Chaplain believed the best option was to pump the water out of the 8820 North sump before attempting to unblock it [116]; c. Mr Chaplain, Mr Cownie and Mr McMillan agreed that there was a need to reduce the volume of water in the 8820 North sump before unblocking it and that they agreed that the best option would be for the water to be pumped out of the 8820 North sump and down the decline, if necessary [117]; d. Mr Cownie told to Mr Howard that the water level in the 8820 North sump was too high and needed to be pumped out [126]; e. Mr Cownie told Mr McMillan that they might have to put a pump in the 8820 North sump to get rid of the water [127]; f. the "Management of Underground Sumps" document (the Sump Procedure) required workers to reduce the volume of water in a sump before working in, around and under sumps [166]; g. The Sumps Procedure provided that a pump should be installed to reduce the water before attempting to unblock drain holes with high water [166]; h. reducing the depth of the water was a way of eliminating or minimising the pleaded risk [244]; i. the consensus of the evidence was that the water level should have been reduced by pumping water out of the sump before attempting to unblock the drain hole [244]; j. Mr McMillan may have required Mr Hern to reduce the water level as the first step of a JSA because that process had been discussed amongst supervisory staff [262]; k. pumping water out of the sump before attempting to unblock the drain hole would have dealt with the water in a controlled way, avoiding a subsequent hazard [244]; l. pumping water out of the sump before attempting to unblock the drain hole could have been done with the available pumps in the mine [245]; m. the placing pumps in sumps was a usual task and done often by service crews using an ITC and had been done by Mr Hern and Mr Booth on the night of the incident [246]; n. there was no cost to the defendant in reducing the water level in the sump before unblocking the drain hole [247]? 6.Did I apply the correct legal principles as to the test in relation to whether the measure pleaded in [16] of the Amended Summons was not a reasonably practicable measure, when I found at [249] of the Judgment that the pleaded measures would not eliminate the pleaded risk? 7.When I dealt with the measure pleaded in [16] of the Amended Summons and found at [249] of the Judgment that this measure would not have eliminated the pleaded risk, should I have found that the measure would have minimised the pleaded risk?
C. Particular 17(a) - Safe System of Work- JSA 8. Did I apply the correct legal principle as to the test in relation to whether a pleaded measure was reasonably practicable, when I found at [263] of the Judgment that the measure pleaded in 17 of the Amended Summons was not reasonably practicable, in that I did not consider the prosecution case that a JSA should have been prepared at the time of, or prior to, the blocking of the drain hole? 9. Did I apply the correct legal principles as to the test in relation to whether a pleaded measure was reasonably practicable, when I found at [263] of the Judgment that the measure pleaded in 17 of the Amended Summons was not a reasonably practicable measure, in light of my finding at [256] of the Judgment that it was common ground that JSA should have been prepared because the unblocking of the drain hole was a Non-Standard Job as defined in the JSA Procedure? 10. Was it open to me to find that that the measure pleaded in 17 of the Amended Summons was not a reasonably practicable measure, in light of my findings that (references are to paragraph numbers in the Judgment): o. it was common ground that a JSA should have been prepared because the unblocking of the drain hole was a Non-Standard Job as defined in the JSA Procedure [256]; p. the terms of the JSA procedure required workers to ensure that they conducted JSAs when required by the JSA Procedure and supervisors to ensure that workers conducted JSAs when required to do so by the JSA Procedure [257] q. the supervisor should have required one to have been completed [261]; r. the supervisor would have required the workers to complete a JSA if he had attended at the sump [261]; s. Mr McMillan may have required Mr Hern to reduce the water level as the first step of a JSA because that process had been discussed amongst supervisory staff [262]? 11. Did I apply the correct legal principles as to the test in relation to whether a pleaded measure was reasonably practicable, when I found at [263] of the Judgment that the measure pleaded in 17 of the Amended Summons was not a reasonably practicable measure, by not having regard to the matters set out in s.18 of the Act as to whether a measure is a reasonably practicable one?
D. Particular 17(b) - Safe System of Work- SWP 12. Did I apply the correct legal principles as to the test in relation to whether a pleaded measure was reasonably practicable, when I found at [263] and [285] of the Judgment that the measurement pleaded in 17 of the Amended Summons was not a reasonably practicable measure, by not having regard to the matters set out in s.18 of the Act as to whether a measure is a reasonably practicable one? 13. Did I apply the correct legal principles as to the test in relation to whether the preparation of a safe work procedure for the blocking and unblocking of sump drains was a reasonably practicable measure in light of my findings at [166] - [170] of the Judgment as to the development of the Sump Procedure?
E. Particular 17(b)(i) - Adequate work procedure- Requirement for a Risk Assessment before blocking drain holes 14. Was it open to me to find at [279] of the Judgment that the element of the measure pleaded in 17(i) of the Amended Summons was not reasonably practicable, in circumstances where I did not consider or adequately consider whether it was reasonably practicable for a risk assessment to be undertaken at the time the decision was made to block the drain hole? 15. Did I apply the correct legal principles as to the test in relation to whether the element of the measure pleaded in 17(i) of the Amended Summons was reasonably practicable, when I found at [279] of the Judgment that I was not satisfied that had a prospective risk assessment been undertaken that it would have identified the matters that led to the accumulation of a large volume of water in the sump? 16. Did I apply the correct legal principles as to the test in relation to whether the element of the measure pleaded in 17(i) of the Amended Summon was reasonably practicable, when I found at [279] of the Judgment that it was not a reasonably practicable measure, by not having regard to the matters set out in s.18 of the Act as to whether a measure is a reasonably practicable one?
F. Particular 17(b)(ii) - Adequate work procedure- Requirement for a Risk Assessment before unblocking drain holes 17. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(ii) of the Amended Summons was a reasonably practicable measure in that in my consideration of this element at [280] of the Judgment I focused on whether this element of a work procedure, had it been applied on the day of the Incident, would have led to a different outcome in relation to the Incident, rather than whether it was an element of a work procedure that was reasonably practicable for the defendant to implement prior to the date of the Incident? 18. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(ii) of the Amended Summons was a reasonably practicable measure when I dealt with the issue of whether this element of a work procedure would have led to a different outcome rather than eliminated or reduced the pleaded risk? 19. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(ii) of the Amended Summons was a reasonably practicable measure, in light of my finding at [256] of the Judgment that it was common ground that a form of risk assessment (JSA) should have been prepared because the unblocking of the drain hole was a Non-Standard Job as defined in the JSA Procedure? 20. Was it open to me to find that that the measure pleaded in 17(ii) of the Amended Summons was not an element of a reasonably practicable measure, in light of my findings that (references are to paragraph numbers in the Judgment): t. it was common ground that a JSA should have been prepared because the unblocking of the drain hole was a Non-Standard Job as defined in the JSA Procedure [256]; u. the terms of the JSA procedure required workers to ensure that they conducted JSAs when required by the JSA Procedure and supervisors to ensure that workers conducted JSAs when required to do so by the JSA Procedure [257]; v. the supervisor should have required one to have been completed [261]; w. the supervisor would have required the workers to complete a JSA if he had attended at the sump [261]; x. Mr McMillan may have required Mr Hern to reduce the water level as the first step of a JSA because that process had been discussed amongst supervisory staff [262]?
G. Particular 17(b)(iii) - Adequate work procedure- reduction of the volume of water 21. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(iii) of the Amended Summons was reasonably practicable in that in my consideration of this element at [281] of the Judgment I focused on whether this element of a work procedure, could have been implemented on the day of the Incident, rather than whether it was an element of a work procedure that was reasonably practicable for the defendant to have implemented prior to the date of the Incident?
H. Particular 17(b)(iv) - Adequate work procedure- installation of pump to reduce the water level 22. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(iv) of the Amended Summons was a reasonably practicable measure in that in my consideration of this element at [281] of the Judgment I focused on whether this element of a work procedure, could have been implemented on the day of the Incident, rather than whether it was an element of a work procedure that was reasonably practicable for the defendant to have implemented prior to the date of the Incident?
I. Particular 17(b)(v) - Adequate work procedure- prohibition on workers entering sumps 23. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(v) of the Amended Summons was a reasonably practicable measure in that in my consideration of this element at [282] of the Judgment I focused on whether it was foreseeable on the day of the Incident that workers would enter the water, rather than whether it was an element of a work procedure that was reasonably practicable for the defendant to have implemented prior to the date of the Incident?
J. Particular 17(b)(vi) - Adequate work procedure- using integrated tool carrier 24. Did I apply the correct legal principle as to the test in relation to whether the element of the measure pleaded in 17(vi) of the Amended Summons was a reasonably practicable measure in that in my consideration of this element at [283] of the Judgment I focused on the fact that the element of the work procedure was already part of an existing procedure, rather than whether it was an element of a work procedure that was reasonably practicable for the defendant to have implemented prior to the date of the Incident?
K. Element 4 - Causation 25. Did I apply the correct legal principle as to the test in relation to whether the failure on the part of the defendant to implement any or all pleaded measures in [16] and [17] of the Amended Summons was a causally related to the exposure of Mr Hern to the pleaded risk, in that in my consideration of this element at [304] of the Judgment I focused on the specific risk that manifested in the Incident and Mr Hern's contribution to his being exposed to the risk rather than the general class of risk and whether the particularised omissions were a significant or substantial cause of Mr Hern being exposed to the risk of injury? 26. Did I apply the correct legal principle as to the test in relation to whether the failure on the part of the defendant to implement any or all pleaded measures in [16] and [17] of the Amended Summons was or were causally related to the exposure of Mr Hern to the pleaded risk, in that in my consideration of this element at [304] of the Judgment I focused on whether the particularised failures of the defendant were the cause of the injury to Mr Hern, rather than whether there was a causal relation between the pleaded omissions and the risk to which Mr Hern was exposed?
Appendix B
Endnote
Amendments 11 February 2020 - Formatting error DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 11 February 2020
Orr
Cobar Management Pty Ltd
(2000) 49 NSWLR 653
(2006) 226 CLR 256
(1996) 186 CLR 389
(1993) 43 FCR 280
(1987) 16 FCR 359
(2010) 186 FLR 410
(1999) 48 NSWLR 616
(1994) 181 CLR 251
(2001) 202 CLR 439
(1987) 163 CLR 54
(1986) 161 CLR 278
(1923) 33 CLR 369
(1906) 4 CLR 802
(1995) 184 CLR 19