Is the Financial hardship faced by the Applicant a relevant matter that can be taken into account, in weighing up the different considerations relevant to the application to modify the development consent?
- The Council relies on Davies v Penrith City Council [2013] NSWLEC 1141 for the proposition that anthropocentric considerations must not be permitted to intrude into or inform the planning merit assessment process: at [116]-[121]. However, the Court accepts that the facts in that decision (regarding a personal factor of a person's disability in connection with the location of a garage) are suitably different from the current facts as to be distinguishable.
- Moreover, the Court is obliged under s 79C(1) of the EPA Act to consider a range of matters, including "the likely impacts of [the] development, including environmental impacts on both the natural and built environments, and social and economic impacts in the locality": s 79C(1)(b). Such impacts do not exist in a vacuum.
- The consequence of the Applicant's inability to secure the owners' agreement (and therefore registration of the easement) is that the Works are unable to proceed. Mr Ding outlines in some detail what the economic consequence of this will be for the Applicant (and thus potentially for the development). The evidence for the Applicant shows that a delay in commencement of construction will cost the Applicant a considerable amount - not only the holding and associated costs, which are estimated to be in the order of $550,000 - $600,000, but further consequential costs. These consequences include delay in completion of the Works; delay in completion of contracts for sale of future subdivided lots and financial loss in the form of holding costs and potential loss of sales. According to Mr Byrum, if the preferred tenderer (whose price if very favourable to the Applicant) is unable to be engaged prior to Christmas, "I apprehend that the entire civil works program … will be significantly delayed, probably by at least 3 months, and likely to ultimately be at higher cost to the applicant".
- The Applicant says that due to contractual provisions the certificate of subdivision must be issued by December 2017 at the latest. If not, purchasers may exercise their right to rescind their contracts, of which 61 have to date been exchanged. Such contract rescissions could lead to a consequential loss of income, and loss of opportunity not to mention the further costs of marketing and holding the land.
- In relation to financial impact, the Council makes the following submissions: notwithstanding "having some sympathy for what might be described as the Applicant's 'personal position' as set out [in an affidavit], that position cannot be used, and should not be permitted to be used, to usurp a proper planning outcome which is presently reflected in the agreed conditions by dint of the s 34 agreement entered into between the parties".
- I do not doubt the Applicant's statements regarding potential financial impact, nor is their veracity challenged by the Council. Indeed, submits the Council, incurring costs is "part and parcel of the risk of developing land". However, there is disagreement between the parties as to relevance and the weight to be ascribed to them.
- The Council's view in this respect is that the circumstances the Applicant faces are not hardship, but an incidental fact, and a risk that developers take. To give that situation any weight at all casts aside the proper development of land in favour of commercial considerations.
- The Applicant presses the relevance of the financial impact as a relevant consideration, referring to the Court's discretion, and its obligations to consider the circumstances of the case. In so doing it relies upon the decision in Dipper v Pittwater Council [2006] NSWLEC 273, a decision of the Chief Judge of this Court, for the proposition that, speaking generally, personal considerations (such as hardship) can be taken into account as a discretionary matter in considering planning matters. I respectfully concur with this view, and have taken the Applicant's financial position into consideration as a relevant matter for consideration.
- Having considered the evidence, the circumstances of the case, the public interest and the submissions of the parties, I have formed the view that the potentially negative economic impacts for the Applicant, while significant and regrettable, do not outweigh the necessity for a registered easement to be in place prior to the commencement of the Works. Whilst I find that the financial impact is a relevant consideration, this does not outweigh the legal obligations which otherwise attach to the Applicant in this case, nor does it outweigh other matters (set out below) of public interest.
- What the Applicant seeks is effectively to reduce its financial risk by transferring some risk to the owners of the Affected Land, who are not parties to this proceeding. The Court cannot sanction such an approach in these circumstances.
- This application is made in the situation where, as matters presently stand, a registered easement has not been able to be obtained. In this case, I am not being asked to consider (and indeed am unable to) whether the easement should be imposed on the Affected Land. Instead, I am asked to exercise discretion to modify the Consent in the manner sought by the Applicant, to allow the Works to commence in the absence of a registered easement, which easement the Applicant says will be secured prior to the issue of the subdivision certificates.
- In seeking the exercise of the Court's discretion, the Applicant has the persuasive burden to demonstrate to me amongst other things that it has taken all reasonable steps to secure the registration of the easement. It is appropriate that the Applicant - in terms of the easement, the dominant owner - bears this persuasive burden, as the very essence of an easement is that "the servient owner is obliged to suffer or not to do something on his own land, for the advantage of the dominant owner". It is not clear on the evidence that the Applicant has exhausted all opportunities, or made all reasonable attempts, to obtain the easement. Thus, this burden has not been discharged.
- In addition, I have considered the Applicant's proposal to commence proceedings to seek registration of an easement within either three or six months from the date of issue of a construction certificate. However, this does not cure the fundamental problem for the Applicant that it needs the permission of the owners of the Affected Land to discharge water over it in the manner intended.
- I have also taken account of the fact that the period of time for which the affected land will be impacted by the flow of water is open-ended, given that the regional drainage solution for Blacktown has no confirmed start date. The discharge of waters over the Affected Land will be both for an open-ended period of time, and will involve a greater amount of water than presently drains over the Affected Land. While the rate of flow of water to the Affected Land may not be greater after the Works than before the Works, nonetheless there will simply be more of it as a result of the Works (occasioned in part by the vast increase in impermeable surfaces).
- I also accept the Council's submission that to modify the Consent as sought by the Applicant would create an unacceptable level of uncertainty, the uncertainty being that there is no guarantee that a registered easement is able to be secured. This uncertainty could lead to two unacceptable outcomes. Firstly, it would be a wholly unsatisfactory outcome if, upon completion of the Works and all that that involves, the subdivision certificate was unable to be issued due to the absence of a registered easement. Secondly, it would be an unacceptable outcome for the owners of the Affected Land to be impacted by the Works, without the benefit of the easement. It is not as if the Works could be undone to stop the impact, once they had commenced. This would not be feasible. The owners of the Affected Land, in this scenario, would be left in an unprotected position. I agree with the Council that the appropriate time at which assurance ought to be provided is prior to the commencement of the Works.
- It may be that an easement may be able to be secured upon the making of further inquiries, or upon the submission of appropriate evidence to another Court at another time, but that is not necessary for me to decide.
- As to the orderly and economic use and development of the land, the Applicant asserts that a decision not to modify the conditions the subject of this appeal will work against this objective.
- I do not accept this submission. The orderly and economic use and development of the land requires sufficient certainty. While it would be the best outcome for the Works to be able to be commenced with alacrity and for actual and potential losses not to be incurred, these factors do not displace the obligation in these circumstances for a registered easement to be in place prior to the issue of a construction certificate.