PART A - Base Conditions
A. Conditions that Identify Approved Plans
Development in Accordance with Plans/documentation
A1. The development must be carried out in accordance with Drawings numbered DA2-0090; DA2-1002; DA2-4000 and DA2-4001, dated 11 February 2016, drawn by Humphrey + Edwards, and Drawings numbered DA2-0001.02; DA2-1000.02 and DA2-1001.02, dated 12 May 2016, drawn by Humphrey+ Edwards, and endorsed with Council's approval stamp, except where amended by the following conditions and this consent.
(Reason: To ensure that the form of the development undertaken is in accordance with the determination of Council, Public Information)
Plans on Site
A2. A copy of all stamped approved plans, specifications and documents (including the plans, specifications and documents submitted and approved with the Construction Certificate) must be kept on site at all times so as to be readily available for perusal by any officer of Council or the Principal Certifying Authority.
All documents kept on site in accordance with this condition must be provided to any officer of the Council or the certifying authority upon their request.
(Reason: To ensure that the form of the development undertaken is in accordance with the determination of Council, Public Information and to ensure ongoing compliance)
No Demolition of Extra Fabric
A3. Alterations to, and demolition of the existing building shall be limited to that documented on the approved plans.
(Reason: To ensure compliance with the approved development) Paved Outdoor Area
A4. Deleted (see condition 11)
A5. Deleted (see condition 11).
C Prior to the Issue of a Construction Certificate
Structural Adequacy of Existing Building
Cl. A report prepared by an appropriately qualified and practising structural engineer, certifying the structural adequacy of the property and its ability to withstand the proposed additional, or altered structural loads during all stages of construction shall be submitted to the Certifying Authority for approval prior to issue of any Construction Certificate. The certified report must also include all details of the methodology to be employed in construction phases to achieve the above requirements. The methodology in the certified report must be complied with at all times.
(Reason: To ensure the structural integrity of the building is maintained)
Heritage Architect to be commissioned
C2. An appropriately qualified and experienced heritage architect must be commissioned to assist the design development, contract documentation and overseeing of construction works on the site for their duration by undertaking regular inspections of the works in progress and providing advice in relation to heritage matters.
Written details of the engagement of the experienced heritage architect must be submitted to the Certifying Authority prior to the issue of any Construction Certificate.
Note: if advice provided by the heritage architect is to the effect that works requiring development consent be carried out, such works would require an application under s96 of the Environmental Planning and Assessment Act 1979 or further development application. This condition, and any advice given by the heritage architect, should not be construed as authorising the carrying of development with/ otherwise than in accordance with the development consent.
(Reason: To ensure that all matters relating to significant fabric and spaces are resolved and recorded using best practice for heritage conservation)
External Colours and Finishes
C3. The external colours and finishes shall match those as existing and/ or be compatible with surrounding development. A schedule of external colours and finishes must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.
(Reason: To ensure that the completed colours and finishes of the works are compatible with surrounding development)
Stormwater Disposal
C4. Stormwater runoff generated by the approved development must be conveyed by gravity to the existing site stormwater drainage disposal system. A licensed tradesman shall install plumbing components to achieve this requirement in accordance with the BCA and current plumbing standards and guidelines. Plans and specifications which comply with this condition must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.
(Reason: To ensure appropriate provision for disposal and stormwater management arising from the development)
Works to Out Buildings
C5. Roof tiles to be replaced only where necessary and are to match the original roof tiles.
Existing original pedestrian door to be restored and retained in situ such that n is visible from the interior of the existing out building.
A nib wall (minimum of 230 mm) to be retained where the internal walls are proposed for demolition within the out building.
New windows and doors to the out buildings are to be timber framed.
Exterior Colour Scheme of the new works to be sympathetic to the existing out buildings.
The Certifying Authority must ensure that the building plans and specifications submitted, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.
(Reason: To allow for the interpretation of the original internal space and to conserve the heritage significance of the buildings.)
D. Prior To Any Commencement
Public Liability Insurance -Works on Public Land
D1. Any person or contractor undertaking works on public land must take out Public Risk Insurance with a minimum cover of $20 million in relation to the occupation of public land and the undertaking of approved works within Council's road reserve or public land, as approved by this consent. The Policy is to note, and provide protection/full indemnification for North Sydney Council, as an interested party. A copy of the Policy must be submitted to Council prior to commencement of any works. The Policy must be valid for the entire period that the works are being undertaken.
(Note: Applications for hoarding permits, vehicular crossings etc will require evidence of insurance upon lodgement of the application.)
(Reason: To ensure the community is protected from the cost of any claim for damages arising from works on public land)
Sydney Water Approvals
D2. Prior to the commencement of any works, the approved plans must be submitted to a Sydney Water Quick Check agent or Customer Care Centre to determine whether the development application will affect Sydney Water's sewer and water mains, stormwater drains and/or easements, and if further requirements need to be met. The approved plans will be appropriately stamped. The Certifying Authority must ensure that a Quick Check agent/Sydney Water has appropriately stamped the plans before the commencement of building works.
Note: For Quick Check agent details please refer to 'Your Business" section of
Sydney Water's web site at www.sydneywater.com.au then see Building and
Renovating under the heading Building and Developing, or telephone 13 20 92.
(Reason: To ensure compliance with Sydney Water requirements)
Asbestos Material Survey
D3. Prior to the commencement of any works, a report must be prepared by a suitably qualified person in relation to the existing building fabric to be demolished and/or disturbed identifying the presence or otherwise of asbestos contamination and, if asbestos contamination is present, making recommendations as to the work required to safely address the contamination.
Any demolition works or other works identified in the report as having to be carried out must be carried out in accordance with the recommendations of the report and the following:
i. the removal of asbestos must be undertaken by a WorkCover licensed contractor;
ii. all removal must be in strict accordance with the requirements of the WorkCover Authority in relation to the removal, handling and disposal of material containing asbestos and any Work Safe Australia requirements.
iii. during the removal of any asbestos a sign stating "DANGER ASBESTOS REMOVAL IN PROGRESS" must be erected in a visible position at the boundary of the site; and
iv. Waste disposal receipts must be provided to the Certifying Authority as proof of correct disposal of asbestos laden waste.
The report must be submitted to the Certifying Authority for approval prior to the issue of any Construction Certificate. The Certifying Authority must ensure that the report, and other plans, referenced on and accompanying the issued Construction Certificate, fully satisfy the requirements of this condition.
(Reason: To ensure the long term health of workers on site and occupants of the building is not put at risk unnecessarily)
Commencement of Works Notice
D4. Building work, demolition or excavation in accordance with this development consent must not be commenced until the developer has given at least 2 days notice to North Sydney Council of the person's intention to commence building work, demolition or excavation in accordance with this development consent.
(Reason: To ensure appropriate safeguarding measures are in place prior to the commencement of any building work, demolition or excavation)
Section 60 application
D5. An application under section 60 of the NSW Heritage Act must be submitted and approved by the NSW Heritage Council prior to work commencing.
(Reason: Statutory)
Photographic Survey
D6. The applicant shall prepare a digital photographic archival recording of the existing building to record the building prior to, during and after completion of works.
The digital photographic archival recording is to be in accordance with the Heritage Council of NSW guidelines How to Prepare Archival Records of Heritage Items (1998) and Photographic Recording of Heritage Items Using Film or Digital Capture (2006).
The applicant shall submit the digital photographic archival recording to the Heritage Division prior to the occupation of the building.
(Reason: To provide a historical record of heritage significant fabric on site for archival purposes)
E. During Demolition and Building Work
Historical fabric and relics
E1. Significant built elements and landscape features to be adequately protected during the works from potential damage. Protection systems must ensure significant fabric is not damaged or removed.
The installation of new services shall be carried out in such a manner as to minimise damage to or removal of historic fabric and shall not obscure historic features. Any penetrations through heritage fabric for supply and waste pipes should be prevented.
The Applicant must ensure that if any historical archaeological 'relics' within the meaning of Heritage Act 1977, are disturbed by the works necessary for the new development, the Heritage Council of NSW is notified in accordance with Section 146 of the Heritage Act 1977. Further advice, assessment and approval may be required before works continue in the area subject to the nature of the discovery.
Should any Aboriginal 'objects' be uncovered by the work, excavation or disturbance of the area is to stop immediately and the Office of Environment & Heritage is to be informed in accordance with Section 89A of the National Parks and Wildlife Act, 1974 (as amended). Aboriginal 'objects' must be managed in accordance with an approved Aboriginal heritage impact permit under Section 90 of the National Parks and Wildlife Act, 1974.
(Reason: To prevent the unnecessary destruction or removal of unrecorded historical or Aboriginal relics)
Parking Restrictions
E2. Existing public parking provisions in the vicinity of the site must be maintained at all times during works. The placement of any barriers, traffic cones, obstructions or other device in the road shoulder or kerbside lane is prohibited without the prior written consent of Council. Changes to existing public parking facilities/restrictions must be approved by the North Sydney Local Traffic Committee. The Developer will be held responsible for any breaches of this condition, and will incur any fines associated with enforcement by Council regulatory officers.
(Reason: To ensure that existing kerbside parking provisions are not compromised during works)
Road Reserve Safety
E3. All public footways and roadways fronting and adjacent to the site must be maintained in a safe condition at all times during the course of the development works, with no obstructions caused to the said footways and roadways. Construction materials and plant must not be stored in the road reserve without approval of Council. A safe pedestrian circulation route and a pavement route free of trip hazards must be maintained at all times on or adjacent to any public access ways fronting the construction site.
Where public infrastructure is damaged, repair works must be carried out in when and as directed by Council officers (at full Developer cost). Where pedestrian circulation is diverted on to the roadway or verge areas, clear directional signage and protective barricades must be installed in accordance with AS1742-3 (1996) "Traffic Control Devices for Work on Roads". If pedestrian circulation Is not satisfactorily maintained across the site frontage, and action is not taken promptly to rectify the defects, Council may undertake proceedings to stop work.
(Reason: Public Safety)
Temporary Disposal of Stormwater Runoff
E4. During construction, stormwater runoff must be disposed in a controlled manner that is compatible with the erosion and sediment controls on the site. Immediately upon completion of any impervious areas on the site (including roofs, driveways, paving) and where the final drainage system is incomplete, the necessary temporary drainage systems must be installed to reasonably manage and control runoff as far as the approved point of stormwater discharge. Such ongoing measures must be to the satisfaction of the Certifying Authority.
(Reason: Stormwater control during construction)
Removal of Extra Fabric
E5. Should any portion of the existing building, trees, or curtilage of the site which is indicated on the approved plans to be retained be damaged for whatever reason, all the works in the area of the damaged portion are to cease and written notification of the damage is to be given to Council forthwith. No work is to resume until the written approval of Council to do so is obtained. Failure to comply with the provisions of this condition may result in the Council taking further action including legal proceedings if necessary.
(Reason: To ensure compliance with the terms of this development consent)
Noise and Vibration
E6. The works must be undertaken in accordance with the "Interim Construction Noise Guideline" published by the NSW Environment Protection Authority, to ensure excessive levels of noise and vibration do not occur so as to minimise adverse effects experienced on any adjoining land.
(Reason: To ensure residential amenity is maintained in the immediate vicinity)
No Work on Public Open Space
E7. No work can be undertaken within adjoining public lands (ie Parks, Reserves, Roads etc) without the prior written consent of Council. In this regard the developer is to liaise with Council prior to the commencement of any design works or preparation of a Construction and Traffic Management Plan.
(Reason: Protection of existing public infrastructure and land and to ensure public safety and proper management of public land)
Developer's Cost of Work on Council Property
E8. The developer must bear the cost of all works associated with the development that occurs on Council's property, including the restoration of damaged areas.
(Reason: To ensure the proper management of public land and funds)
No Removal of Trees on Public Property
E9. No trees on public property (footpaths, roads, reserves, etc.) unless specifically approved by this consent shall be removed or damaged during construction including for the erection of any fences, hoardings or other temporary works.
(Reason: Protection of existing environmental infrastructure and community assets)
Spacial Permits
E10. Unless otherwise specifically approved in writing by Council, all works, processes, storage of materials, loading and unloading associated with the development must occur entirely on the property.
The developer, owner or builder may apply for specific permits available from Council's Customer Service Centre for the undermentioned activities on Council's property. In the event that a permit is granted by Council for the carrying out of works, processes, storage of materials, loading and unloading associated with the development on Council's property, the development must be carried out in accordance with the requirements of the permit. A minimum of forty-eight (48) hours notice is required for any permit: -
1) On-street mobile plant
Eg. cranes, concrete pumps, cherry-pickers, etc. restrictions apply to the hours of operation, the area of operation, etc. Separate permits are required for each occasion and each piece of equipment. It is the developer's, owner's and builder's responsibilities to take whatever steps are necessary to ensure that the use of any equipment does not violate adjoining property owner's rights.
(Reason: Proper management of public land)
2) Hoardings
Permits are required to erect Class A and Class B hoardings. If an 'A' Class hoarding is to alienate a section of Council's property, that section will require a permit for the occupation of Council's property.
(Reason: Proper management of public land)
3) Storage of building materials and building waste containers (skips) on Council's property
Permits to utilise Council property for the storage of building materials and building waste containers (skips) are required for each location. Failure to obtain the relevant permits will result in the building materials or building waste containers (skips) being impounded by Council with no additional notice being given. Storage of building materials and waste containers on open space reserves and parks is prohibited.
(Reason: Proper management of public land)
4) Kerbside restrictions, construction zones
Attention is drawn to the existing kerbside restrictions adjacent to the development. Should alteration of existing kerbside restrictions be required, or the provision of a construction zone, the appropriate application must be made and the fee paid to Council. Alternatives to such restrictions may require referral to Council's Traffic Committee and may take considerable time to be resolved. An earlier application is suggested to avoid delays in construction programs.
(Reason: Proper management of public land)
Construction Hours
E11. Building construction and works must be restricted to within the hours of 7.00 am to 5.00 pm Monday to Friday and on Saturday to within the hours of 8.00 am to 1.00 pm inclusive, with no work on Sundays and Public Holidays.
Demolition and excavation works must be restricted to within the hours of 8.00 am to 5.00 pm Monday to Friday only. For the purposes of this condition:
1) "Building construction" means any physical activity on the site involved in the erection of a structure, cladding, external finish, formwork, fixture, fitting of service installation and the unloading of plant, machinery, materials or the like.
2) "Demolition works" means any physical activity to tear down or break up a structure (or part thereof) or surface, or the like, and includes the loading of demolition waste and the unloading of plant or machinery.
3) "Excavation work" means the use of any excavation machinery and the use of jackhammers, rock breakers, excavators, loaders, or the like, regardless of whether the activities disturb or alter the natural state of the existing ground stratum or are breaking up/removing materials from the site and includes the unloading of plant or machinery associated with excavation work.
All builders, excavators must display, on-site, their twenty-four (24) hour contact telephone number, which is to be clearly visible and legible from any public place adjoining the site.
(Reason: To ensure that works do not interfere with reasonable amenity expectations of residents and the community)
Out of Hours Work Permits
E12. Where it is necessary for emergency works to occur outside those hours allowed by these conditions, an application may be made to Council's Customer Services Centre for a permit to carry out emergency works outside of the approved hours. If a permit is issued the development must be carried out in accordance with any requirements of the permit. A permit and shall only be approved if public safety or convenience is at risk. Any further variation shall require the lodgement and favourable determination of a modification application pursuant to Section 96 of the Environmental Planning and Assessment Act 1979.
Notes:
1) Failure to obtain a permit for work outside of the approved hours will result in on the spot fines being issued, or Council pursuing any action required (including legal proceedings) to have the out of hours work cease, without prior warning.
2) Further information on permits can be obtained from the Council website at www.northsydney.nsw.gov.au.
3) It is recommended that applications for permits be lodged as early as possible to allow sufficient time for determination by Council and avoid disruption or delay due to conflicting priorities.
4) Permit Emergency for such occurrence shall be limited to two occasions per calendar month
(Reason: To ensure that works do not interfere with reasonable amenity expectations of residents and the community)
Health and Safety
E13. All work undertaken must satisfy applicable occupational health and safety and construction safety regulations, including any WorkCover Authority requirements to prepare a health and safety plan. Site fencing must be installed sufficient to exclude the public from the site. Safety signs must be erected that warn the public to keep out of the site, and provide a contact telephone number for enquiries.
Further information and details regarding occupational health and safety requirements for construction sites can be obtained from the internet at www.workcover.nsw.gov.au
(Reason: To ensure the health and safety of the community and workers on the site)
Prohibition on Use of Pavements
E13.1 Building materials must not be placed on Council's footpaths, roadways, parks or grass verges, (unless a permit is obtained from Council beforehand). A suitable sign to this effect must be erected adjacent to the street alignment.
(Reason: To ensure public safety and amenity on public land)
Plant & Equipment Kept Within Site
E14. All plant and equipment used in the undertaking of the development/ works, including concrete pumps, wagons, lifts, mobile cranes, hoardings etc, must be situated within the boundaries of the site (unless a permit is obtained from Council beforehand) and so placed that all concrete slurry, water, debris and the like must be discharged onto the building site, and is to be contained within the site boundaries.
Details of Council requirements for permits on public land for standing plant, hoardings, storage of materials and construction zones and the like are available on Council's website at www.northsydney.nsw.gov.au.
(Reason: To ensure public safety and amenity on public land)
F. Operational Conditions imposed under EP&A Act and Regulations and other relevant Legislation
Building Coda of Australia
F1. All building work must be carried out in accordance with the provisions of the Building Code of Australia
(Reason: Prescribed Statutory)
Appointment of a Principal Certifying Authority (PCA)
F2. Building work, demolition or excavation in accordance with the development consent must not be commenced until the developer has appointed a Principal Certifying Authority for the building work in accordance with the provisions of the EP&A Act and its Regulations.
(Reason: Statutory; To ensure appropriate safeguarding measures are in place prior to the commencement of any building work, demolition or excavation)
Construction Certificate
F3. Building work, demolition or excavation in accordance with the development consent must not be commenced until a Construction Certificate for the relevant part of the building work has been issued in accordance with the provisions of the EP&A Act and its Regulations.
(Reason: Statutory; To ensure appropriate safeguarding measures are in place prior to the commencement of any building work, demolition or excavation)
Occupation Certificate
F4. A person must not commence occupation or use of the whole or any part of a new building (new building includes an altered portion of, or an extension to, an existing building) unless an Occupation Certificate has been issued in relation to the building or part. Only the Principal Certifying Authority appointed for the building work can issue an Occupation Certificate.
(Reason: Statutory)
Critical Stage Inspections
F5. Building work must be inspected by the Principal Certifying Authority on the critical stage occasions prescribed by the EP&A Act and its Regulations, and as directed by the appointed Principal Certifying Authority.
(Reason: Statutory)
Commencement of Works
F6. Building work, demolition or excavation in accordance with this development consent must not be commenced until the developer has given at least 2 days notice to North Sydney Council of the person's intention to commence the erection of the building.
(Reason: Statutory; To ensure appropriate safeguarding measures are in place prior to the commencement of any building work, demolition or excavation)
Excavation/Demolition
F7. 1) All excavations and backfilling associated with the erection or demolition of a building must be executed safely and in accordance with appropriate professional standards.
2) All excavations associated with the erection or demolition of a building must be properly guarded and protected to prevent them from being dangerous to life or property.
3) Demolition work must be undertaken in accordance with the provisions of AS2601- Demolition of Structures.
(Reason: To ensure that work is undertaken in a professional and responsible manner and protect adjoining property and persons from potential damage)
Protection of Public Places
F8. 1) A hoarding and site fencing must be erected between the work site and adjoining public place.
2) If necessary, an awning is to be erected, sufficient to prevent any substance from, or in connection with, the work falling into the public place.
3) The work site must be kept lit between sunset and sunrise if it is likely to be hazardous to persons in the public place.
4) Any such hoarding, fence or awning is to be removed when the work has been completed.
5) No access across public reserves or parks is permitted.
Note: Prior to the erection of any temporary fence or hoarding over property owned or managed by Council, written approval must be obtained. Any application needs to be accompanied by plans indicating the type of hoarding and its layout. Fees are assessed and will form part of any approval given. These fees must be paid prior to the approval being given. Approval for hoardings will generally only be given in association with approved building works, maintenance or to ensure protection of the public. An application form for a Hoarding Permit can be downloaded from Council's website.
(Reason: To ensure public safety and the proper management of public land)
Maximum Capacity Site Sign
F9. A sign must be displayed in a prominent position in the building stating the maximum number of persons, as specified in this development consent, that are permitted in the building.
(Reason: Prescribed Statutory)
I. On-Going/Operational Conditions
Hours of Operation/Patron Numbers
I1. The normal hours of operation and maximum patron numbers are:
● 7am to 12 midnight, Monday to Saturday.
● 7am to 10pm, Sunday.
● the Outdoor Area is to cease use at 9pm.
● a maximum of 600 patrons between 7am and 9pm, 7 days per week.
● a maximum 400 patrons between 9pm and midnight for the Club, Monday to Saturday and 9pm to 10pm Sundays.
● Anzac Day, no opening time but subject to normal hours of operation for closing and maximum patron numbers.
Except as amended or restricted by the following:
● the Outdoor Area may operate with a 250 patron limit between 9pm and 10pm, 7 days for a 12 month trial period,
● the Club may operate with a maximum 600 patron limit between 9pm and 10pm for a 12 month trial period,
● the Club may operate with a maximum of 400 patrons between 10pm and midnight, Monday to Saturday for a 12 month trial period.
● the Club may operate for special event days in accordance with the following table:
Special Event Days (Not the Trial Period) Special Event Days (Trial Period)
A maximum of 900 patrons until 9.30pm A maximum of 900 patrons until 10pm
A maximum of 600 patrons between 9.30pm and 12.30am (the following day) A maximum of 600 patrons between 10pm and 12.30am (the following day)
A maximum of 400 patrons between 12.30am and 2.00am (the following day) A maximum of 400 patrons between 12.30am and 2.00am (the following day)