© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWDC 147
District Court of NSW
2017-05-03
Original judgment source is linked above.
Introduction
The Caravan Park
The Cyclone and its Aftermath
The Plaintiff's Claim
The Defendant's Position
Reasons for rejecting the tender of the reports by DWA
The Insurance Policy
The Policy Schedule
The Evidence
Exhibit A - Four Affidavits of Mr Roscic
Exhibit B - Affidavit of Steve Moore
Exhibit C - Report of Mr Ghorbanian dated 9 September 2016
Exhibit D - Joint Chronology
Exhibit E - Insurance Schedule
Exhibit F - Amended Scott Schedule
Exhibit 1 - Underwriting History Documents
Exhibit 2 - Reports by John Graham of Phase8
Issues in Dispute on the Pleadings
The Interpretation of the Contract
Findings by reference to the issues in the case
Whether or not, and if so to what extent, the Policy issued by Hollard to Ningaloo provided cover for damage to "services" to insured buildings
Whether, and if so to what extent, the Electricity Distribution System (as it existed on and prior to 13 March 2015) was a "service" to the insured buildings for the purposes of the Policy
To what extent was the Electricity Distribution System (as it existed on and prior to 13 March 2015) damaged as a result of Cyclone Olwyn on 13 March 2015
Whether Hollard was required to indemnify Ningaloo in relation to damage to the Electricity Distribution System as a result of Cyclone Olwyn, and if so in respect of what part or parts of the Electricity Distribution System was Hollard required to provide indemnity
Did Hollard wrongly refuse to indemnify Ningaloo in relation to damage to the Electricity Distribution System, or any part of that system, as a result of Cyclone Olwyn in breach of its obligations under the Policy
To the extent that Hollard was required to indemnify Ningaloo for damage to the Electricity Distribution System or any part of that system as a result of Cyclone Olwyn, what was the value of that indemnity
To the extent that Hollard was required to indemnify Ningaloo for damage to the Electricity Distribution System or any part of that system as a result of Cyclone Olwyn, was the cost of reinstating or replacing that system or any part of that system, by constructing a new underground Electricity Distribution System, covered under the "Extra Cost" clause in the Policy
To the extent that Hollard is obliged to indemnify Ningaloo, but the value of that indemnity is limited to expenditure actually incurred by Ningaloo in connection with the reinstatement work undertaken by Ningaloo following Hollard's refusal to indemnify it, whether, and if so to what extent was that expenditure reasonably incurred
To the extent that Hollard wrongly refused to indemnify Ningaloo in relation to damage to the Electricity Distribution System or any part of that system as a result of Cyclone Olwyn in breach of its obligations under the Policy, what is the quantum of damages to which Ningaloo is entitled
Interest
Orders 1. judgment for the plaintiff in the sum of $125,765.17, plus interest; 2. the defendant to pay the plaintiff's costs of the proceedings; 3. the exhibits to be retained by the Court for 28 days; 4. liberty to apply within 14 days to vary the costs order, if necessary; 5. I direct that within 14 days the parties submit either a joint submission on the question of interest or, alternatively, if agreement cannot be reached, then submissions as to same, not exceeding five pages in length.
Endnote
Ningaloo Escape Pty Limited
The Hollard Insurance Company Pty Limited
[2015] HCA 37
(1973) 129 CLR 99
(1982) 149 CLR 337
(2000) 203 CLR 579
(2005) 221 CLR 522
(2015) 256 CLR 104