CONSIDERATION
8These proceedings were transferred by the Supreme Court to this Court and are therefore within class 4 of this Court's jurisdiction: Land and Environment Court Act 1979 s 20(1)(cj). Through an administrative error in this Court's registry, the proceedings were wrongly numbered as class 3 proceedings, but that does not change the effect of the statute and has no costs consequence.
9Costs as between Moorebank and Tanlane are governed by s 98 of the Civil Procedure Act 2005 and r 42.1 of the UCPR. Subject to the rules of court, costs are in the discretion of the Court: s 98. Subject to Part 42 of the UCPR, if the Court makes any order as to costs, the Court is to order that the costs follow the event unless it appears to the Court that some other order should be made as to the whole or any part of the costs: r 42.1 of the UCPR.
10Moorebank's first submission is that it succeeded in the proceedings and therefore Tanlane should pay its costs under the general costs follow the event rule in r 42.1. I disagree.
11In considering the appropriate exercise of discretion under r 42.1 in the present case, an important consideration is the nature of the proceedings. These proceedings are a far cry from conventional civil litigation. Conventional civil litigation is about vindication of rights. That is the essential context for the general costs follow the event rule in r 42.1. An application for an easement under s 88K of the Conveyancing Act is not about vindicating rights but about obtaining rights by appropriating the property of another. The fundamental costs principle under s 88K is that, generally, the owner of the land to be burdened by the threatened easement should be entitled to resist it without fear as to costs, and that the applicant seeking the easement must pay that owner's costs. This is reflected in s 88K(5) which provides: "The costs of the proceedings are payable by the applicant, subject to any order of the Court to the contrary". In my opinion, given the context of the whole of s 88K, this refers to the costs of the owner of the land to be burdened by the easement: Mitchell v Boutagy [2001] NSWSC 1045, (2001) 118 LGERA 249 at [60]; Khattar v Wiese [2005] NSWSC 1014 at [77]; Owners Strata Plan 13635 v Ryan [2006] NSWSC 342 at [12]; 117 York Street Pty Ltd v Proprietors of Strata Plan No 16123 (1998) 43 NSWLR 504 at 523. In Rainbowforce Pty Ltd v Skyton Holdings Pty Ltd [2010] NSWLEC 2, (2010) 171 LGERA 286 at [181] Preston CJ at LEC referred to s 88K(5) creating an entitlement in "the person affected by the easement" but his Honour was not contemplating a third party joined to the proceedings, such as Tanlane. The s 88K(5) entitlement to costs will only be lost if and insofar as the person entitled to it has engaged in unreasonable conduct, such as by making the proceedings more expensive: Rainbowforce at [182].
12Secondly, this is a rare case where the interests of a third party, Tanlane, were intertwined with and not dissimilar to the Council's interests, and were potentially affected by the proposed easements such that it was joined to the proceedings. The Council was at risk of appropriation of its land and disruption of its long term plan for a road bridge connecting various lands east of Brickmakers Drive to Brickmakers Drive. Tanlane was at risk of conflict with its development consent granted by the Council and its ancillary agreement with the Council for the construction of the road bridge, as well as with its easement over Moorebank's land granted by the Supreme Court (subject to valuation) for that purpose. The road bridge was necessary to service Tanlane's proposed large residential subdivision and marina.
13A major concern of the Council and Tanlane was that the location and design of Moorebank's proposed ramps to the road bridge, structure or embankment, or other road access to Brickmakers Drive, might conflict with their interests, particularly if, as Moorebank proposed, the Planning Assessment Commission and not the Council became the approval authority pursuant to Part 3A of the Environmental Planning and Assessment Act 1979. The further amended summons was silent as to the location and design of any such ramps. The Marshall plan for surface access to Brickmakers Drive over the council land, which Moorebank was pursuing when it commenced the proceedings, would conflict with the Tanlane easement and was exhibited in early 2013 as part of the Part 3A process. It was conceivable that the Marshall Plan might have been approved under the Part 3A process, although Moorebank was professing in early 2013 to have moved to an alternative ramps design.
14Having regard to these matters, in my opinion Tanlane should not have had to fear an adverse costs order if it unsuccessfully resisted the imposition of the easements, unless it engaged in unreasonable conduct which added to the expense of the proceedings. Conversely, as Tanlane recognises, given the involvement of the Council as a contradictor Tanlane would not be in a position to ask for costs if it were successful in resisting the imposition of the easements. In short, in my opinion, there should be no order for costs against Tanlane, unless it was unreasonable in its conduct of the proceedings whereby costs were increased.
15I would add that the premise of Moorebank's above submission that it won and Tanlane lost the proceedings is not black and white. In fact, the parties each enjoyed some success. Moorebank was successful in that it obtained the easements and the owner's consent term that it wanted, but it was unsuccessful in otherwise limiting the terms to those set out in the further amended summons. Council and Tanlane achieved a substantial measure of success in that the orders for the easements were subject to extensive conditions for their protection. For example, orders 5 and 5A contained important undertakings by Moorebank in relation to its Part 3A application, the ramps design and related matters.
16I turn to Moorebank's alternative submission that Tanlane's conduct unreasonably prolonged the proceedings in the following respects.
17First, Moorebank submits that Tanlane went beyond the matters which were necessary to protect its interest, namely the conditions of any easement that might be granted, which would have taken little time, and that the vast amount of its submissions and evidence related to issues that went to whether the easements should be granted. I do not accept the submission. I have earlier held that Tanlane was entitled to resist the imposition of the easements without fear of an adverse costs order.
18Secondly, Moorebank submits that Tanlane unreasonably prolonged the proceedings by duplicating the Council's expert planning, traffic and structural engineering evidence, notwithstanding that it had assured the Supreme Court, when it applied to be joined to the proceedings, that it would make efforts to ensure there was no duplication: see [4] above. To put that assurance in context, Tanlane points to the transcript of proceedings before Pembroke J where senior counsel for Tanlane said that Tanlane and Council should ensure that they did not duplicate evidence but that Tanlane, having conducted much of the litigation over the years, had collected much of the evidence and was on top of the issues. Tanlane acknowledges that there was duplication and that if there was no reasonable excuse it may have to bear costs. However, Tanlane submits that it was not reasonably able to avoid duplication in its expert evidence because Moorebank, having put on its evidence over about six months, on 21 March 2013 succeeded in obtaining an order from Sheahan J for expedition of the hearing (Moorebank Recyclers Pty Ltd v Liverpool City Council [2013] NSWLEC 33) and on 28 March 2013 his Honour fixed the proceedings for hearing commencing on 20 May 2013 and ordered the respondent to file their evidence within four weeks, which included Easter. Consequently, Tanlane submits, there was no reasonable time for the experts for Tanlane and the Council to confer to avoid duplication. Tanlane tells me it provided Council with its expert evidence, but there is no evidence of efforts to have Council and Tanlane experts to confer to avoid duplication. I think there should also be taken into account that the respondents had Moorebank's evidence (other than valuation evidence) from 7 March 2013, so they in fact had nearer two months to prepare their evidence. In the circumstances, I am not persuaded that duplication could not have been avoided in the available time. Given that Tanlane was joined to the proceedings taking into account its assurance that it would make efforts to avoid duplication in evidence, I think it is reasonable in the circumstances that Tanlane should bear the additional costs thereby incurred by Moorebank and for which Moorebank is liable to the Council.
19Thirdly, Moorebank submits that Tanlane unreasonably prolonged the proceedings because it raised the following matters which were irrelevant or of little relevance:
(a)Tanlane tendered and addressed what Moorebank describes as a vast number of irrelevant historical planning documents. Although I think far too many such documents were tendered, as they were tendered jointly, with some then removed from the bundle because of Moorebank's objections, and as there was an issue as to the Council's historical long term planning for the area, I am disinclined to conclude that this should have an adverse costs consequence for Tanlane.
(b)Moorebank submits that Tanlane's approach was that the Court should undertake a full merits review of the Part 3A application, including considering air quality evidence, which was irrelevant. As I observed in Moorebank (No 2), in proceedings such as these the court does not look at the likelihood of development consent (or project approval) being granted but can determine whether there is no chance of it being granted. The court also has to consider whether the proposed development is reasonably necessary for the effective use of the applicant's land, which requires some consideration of the development's desirability or economic effect and appropriateness for the area. Expert evidence for both Tanlane and the Council delved into the merits of Moorebank's proposed development, particularly through Tanlane's planner, but could be viewed as going to such issues. The Council's planner generally agreed with Tanlane's planner, and thus in that respect the Council and Tanlane ultimately had a similar evidentiary case. There was overreaching in how far the evidence went to the merits, but I am not satisfied that substantial costs were incurred by Moorebank relating to Tanlane's evidentiary case in this regard over and above the costs relating to Council's evidentiary case on the merits.
(c)Moorebank criticises Tanlane's submissions and evidence at the end of the hearing as to whether Moorebank should be permitted to adduce evidence of the correspondence of Moorebank's planner, Mr Kennan, with the Department of Planning. This related to very recent moves by Mr Kennan behind the scenes to bolster Moorebank's case: see Moorebank (No 2) at [85] - [88]. Although there may have been some initial overreaction by Tanlane to this development, the process which Tanlane instigated disclosed relevant documents which the Court would not have otherwise seen that it was reasonable to put before the Court. I do not think this should adversely affect Tanlane in costs.
20In the result, duplication of expert evidence is the only matter in respect of which I think Tanlane should have a costs liability. Evaluation of the additional costs thereby incurred is not capable of precise arithmetical assessment (which the parties did not venture) and is a matter of broad impression. My impression is that matters of duplication of evidence made only a modest contribution to the length of the hearing. I infer that its contribution to Tanlane's and the Council's preparation time was similar. My evaluation is that the additional costs for duplication of evidence should be assessed at 5 per cent.
21Given this result, I do not propose to make any separate order as to the costs of Moorebank's notice of motion.