© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2000] VSC 402
Supreme Court of Victoria
2000-10-05
Byrne J
Original judgment source is linked above.
PRACTICE AND PROCEDURE - summary judgment - claim based on progress certificates issued under AS4303-1995 - claim based on uncertified progress claims - whether progress claims formally defective - whether payment must be made without deduction for defective work - whether stay of execution.
In fact, a third certificate, No. 12, was issued on 14 March 1998. This showed the total certified value of work to be only $2,929,680. After deduction of the amount said to have been paid, namely, $3,595,549 the amount shown was $665,867.92 due from Minson to Aquatec. In this sense, it was a negative certificate. It was accepted before me that this certificate contained an error inasmuch as the superintendent had recorded Minson as having been paid $3,595,549, on account of work previously done, apparently on the assumption that certificate 10 had been paid in full. In fact, the total amount previously paid was that shown in certificate 10, namely, $3,290,918. Certificate 11 contains the same error. This means, nonetheless, that certificate 12 remains a negative certificate; it should, however, show a payment due from Minson to Aquatec of $361,238. The three certificates ought therefore to have shown the following figures:
"(h) in the premises: (i) the Plaintiff's offer contained in its facsimile of 17 March 1997 was not an offer to `carry out design and construct... the Civil works... on terms and conditions as previously agreed'; (ii) the Defendant's response to the offer contained in its facsimile of 18 March 1997 did not correspond with the Plaintiff's offer and did not amount to an acceptance of it; (iii) no sub-contract was concluded between the Plaintiff and the Defendant; (iv) the Defendant denies the allegations in paragraph 4 of the Amended Statement of Claim and all other allegations in the Amended Statement of Claim by which reliance is placed upon the terms and conditions of any sub-contract between the Plaintiff and the Defendant."
"By an agreement made on or about 18 March 1997 Aquatec engaged Minson as subcontractor to design and construct civil works for the project (`the works') for the sum of $3,580,132 according to the terms and conditions therein (`the sub-contract')."
The defence of 22 August asserts that it relies upon the following facts in defence of the claim. Fact (c) is expressed as follows:
"As to paragraph 4 thereof the Defendant admits that in or about March of 1997 it entered into a sub-contract with the Plaintiff for the Plaintiff to design and construct civil works for the project."
42.1 Payment Claims, Certificates, Calculations and Time for Payment (1) At the times for payment claims or upon completion of the stages of the work under the Subcontract stated in Annexure Part A and upon the issue of a Certificate of Practical Completion and within the time prescribed by Clause 42.5, the Subcontractor shall deliver to the Subcontract Superintendent claims for payment supported by evidence of the amount due to the Subcontractor and such information as the Subcontract Superintendent may reasonably require. Claims for payment shall include the value of work carried out by the Subcontractor in the performance of the Subcontract to that time together with all amounts then otherwise due to the Subcontract arising out of the Subcontract. (4) Within 21 days of receipt of a claim for payment, the Subcontract Superintendent shall assess the claim and shall issue to the Main Contractor and to the Subcontractor a payment certificate stating the amount of the payment which, in the Subcontract Superintendent's opinion, is to be made by the Main Contractor to the Subcontractor or by the Subcontractor to the Main Contractor. The Subcontract Superintendent shall set out in the certificate the calculations employed to arrive at the amount and, if the amount is more or less than the amount claimed by the Subcontractor, the reasons for the difference." (6) Subject to the provisions of the Subcontract, within 35 days of receipt by the Subcontract Superintendent of a claim for payment or within 14 days of issue by the Subcontract Superintendent of the Subcontract Superintendent's payment certificate, whichever is the earlier, and within 21 days of the issue of a Final Certificate, the Main Contractor shall pay to the Subcontractor or the Subcontractor shall pay to the Main Contractor, as the case may be, an amount not less than the amount shown in such certificate as due to the Subcontractor or to the Main Contractor, as the case may be, or if no payment certificate has been issued, the Main Contractor shall pay the amount of the Subcontractor's claim. A payment made pursuant to this Clause 42.1 shall not prejudice the right of either party to dispute under Clause 47 whether the amount so paid is the amount properly due and payable and on determination (whether under Clause 47 or as otherwise agreed) of the amount so properly due and payable, the Main Contractor or the Subcontractor, as the case may be, shall be liable to pay the difference between the amount of such payment and the amount so properly due and payable. (7) Payment of moneys shall not be evidence of the value of work or an admission of liability or evidence that work has been executed satisfactorily but shall be a payment on account only, except as provided under Clause 42.6"
The paragraphs within cl 42.1 are not numbered in the document. I have inserted numbers in brackets for ease of reference.
In progress certificate 12 these items are treated as follows:
In the progress claims that followed, the contract value of the works in question remained as before progress certificate 12, but the percentage payable was increased by Minson to 99% for each site in respect of water retaining and other reinforced structures and to 100% for Apollo Bay earthworks. These claims represented Minson's assessment of the percentage completion of these items in its earlier claims, certainly from claim 11.
"The negative amount of -$665,867.92 is a derivative of our current problems with respect to the non-compliance of the aeration basins on both sites, with regard to Structural Integrity and Water Tightness Integrity. Thus, these structures are currently valueless in their present state and this is reflected on the accompanying spreadsheet in dollar terms."
No such spreadsheet was part of the exhibit. I read this sentence as asserting that the tanks were leaking and that they were therefore valueless or, in the case of Lorne, 23% less valuable than Minson asserted. Mr McFarlane relies on cl. 30.4 as the basis for his entitlement to decrease the value. No argument was presented on this, presumably on the basis that it was a triable issue. For my purpose, it is necessary that I observe that, on its face, the diminution in the value of work performed appears not so much to depend upon cl. 30.4 as on cl. 30.3. Much, however, will turn on the terms of the superintendent's direction, and this is not before me. If, however, the reduction in certificate 12 represents a change by the superintendent in his assessment of the value of work performed as a result of the appearance of defects, then Minson cannot be criticised for holding a different view of this value. As with any difference of opinion as to the value of work performed, the contract provides procedures for resolving this. The first of these procedures is for the superintendent to reject the sub-contractor's assessment with reasons in the certificate issued in response to the claim. The first basis of attack upon the progress claim, therefore, fails.
"If the Sub-contract is terminated pursuant to Clause 44.4(b) or 44.9, the rights and liabilities of the parties shall be the same as they would be at common law had the defaulting party repudiated the Sub-contract and the other party had elected to treat the Sub-contract as at an end and recover damages."
[4] Lamac Developments Pty Ltd v Devaugh Pty Ltd [1999] WASC 76, Master Bredmayer (AS 2545-1993)
[5] Leighton Contractors Pty Ltd v East Gippsland Catchment Management Authority [2000] VSC 26 at [23]
Minson Nacap Pty Ltd
Aquatec Maxcon Pty Ltd [2000] VSC 402
(1997) 189 CLR 146