Headnote
[This headnote is not to be read as part of the judgment]
The appellants, members of the Melino family, were the registered proprietors of farm land in regional NSW used for sugar cane farming. In 2016 the respondent, Roads and Maritime Services, compulsory acquired part of the appellants' land for the purpose of constructing an upgrade of the Pacific Highway.
At the time of acquisition, the acquired land was being used for both sugar cane production and cattle grazing. There was a dwelling on the acquired land occupied at the date of acquisition by a tenant as well as various fixtures relating to the farming operations.
The appellants made several claims for compensation pursuant to the Land Acquisition (Just Terms Compensation) Act 1991 (NSW) ("Just Terms Act"). The primary judge awarded the appellants compensation in respect of the market value of the acquired land (including fixtures), the decrease in value of the adjoining land and a number of disturbance claims. However, the primary judge declined to award compensation for disturbance in respect of the replacement costs of the construction of a replacement dwelling, new cattle yards, a new shed, a new garage, new water tanks and an effluent disposal system to be constructed on the residue land for the purpose of conducting the continuing cattle grazing business. The primary judge also declined to award compensation for the costs incurred in an abandoned proposal to relocate the existing dwelling, loan establishment fees and interest and an agreed sum for the cost of road works.
On appeal the issues were:
(i) Whether the primary judge erred in declining to award compensation for the costs of building a new dwelling and relocating the existing dwelling;
(ii) Whether the primary judge erred in declining to award compensation for the cost of replacing the farm structures;
(iii) Whether the primary judge erred in declining to award compensation for loan establishment fees and interest;
(iv) Whether the primary judge erred in failing to award compensation at an agreed amount for the cost of road works.
The Court (Beazley P, Basten JA, Payne JA) held, allowing the appeal:
In relation to issue (i),
Per Payne JA (Beazley P agreeing):
The Just Terms Act does not expressly or implicitly provide that the value paid for land compulsorily acquired necessarily includes "the full compensatory value for all fixtures included in the acquisition". It was an error on a question of law for the primary judge to so conclude: [82]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), ss 55, 59; Mir Bros Unit Constructions Pty Ltd v Roads and Traffic Authority of New South Wales [2006] NSWCA 314; Roads and Traffic Authority (NSW) v Peak [2007] NSWCA 66; Roads and Traffic Authority (NSW) v McDonald (2010) 79 NSWLR 155; [2010] NSWCA 236; Tolson v Roads and Maritime Services [2014] NSWCA 161; (2014) 201 LGERA 367; Health Administration Corporation v George D Angus Pty Ltd (2014) 88 NSWLR 752; [2014] NSWCA 352; Roads and Maritime Services v Allandale Blue Metal Pty Ltd [2016] NSWCA 7 applied.
The correct approach to s 59(1)(f) in the present case was to ask whether the appellants had reasonably incurred financial costs (or might reasonably incur such costs), relating to the actual use of the land, as a direct and natural consequence of the acquisition: [83]-[84]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), ss 59(1)(f) applied.
Applying this approach, on the findings made by the primary judge the appellants had already received compensation for the market value of the dwelling, which encapsulated the right to potential profits from renting the property after the date of the acquisition. The primary judge's reasoning did not disclose error on a question of law: [85]
While the primary judge did not consider the appellants' claim for the cost of a replacement dwelling under s 59(1)(c), this was not a material error: [95]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), ss 59(1)(c) applied.
Per Basten JA:
Section 59(1)(c) of the Just Terms Act, which covers financial costs reasonably incurred "in connection with the relocation of those persons" is only engaged where those persons are relocated. None of the owners was living on the land at the date of acquisition and therefore none required relocation: [9]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 59(1)(c) applied.
No item in s 59 was intended to allow for the cost of purchasing land for relocation, nor, indeed, for other purposes. It follows that the reference in s 59(1)(f) to "any other financial costs" relating to the actual use of the acquired land, and incurred as a "direct and natural consequence of the acquisition", does not include the cost of replacing the old house which had been on the acquired land and for which market value was payable under s 55(a): [10]-[12]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 59(1)(f) applied.
In relation to issue (ii),
Per Payne JA (Beazley P agreeing):
The question of whether s 59(1)(f), like other parts of s 59(1), is restricted to ancillary costs, and does not extend to purchasing or rebuilding structures should be determined in a case where the point has been squarely addressed by the parties: [77]
Roads and Traffic Authority (NSW) v Peak [2007] NSWCA 66; Roads and Traffic Authority (NSW) v McDonald (2010) 79 NSWLR 155; [2010] NSWCA 236; Roads and Maritime Services v Allandale Blue Metal Pty Ltd [2016] NSWCA 7 considered.
The primary judge erred on a question of law in failing to address the appellants' separate claim for disturbance. The matter must be remitted to the Land and Environment Court: [86]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 59(1)(f) applied.
Per Basten JA:
Section 59(1)(f), like other parts of s 59(1), is restricted to ancillary "costs", and does not extend to purchasing or rebuilding structures: [19]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 59(1)(f) applied.
As a matter of statutory construction, the correct exercise is to assess the loss of the farm structures as special value of the land to the person entitled to compensation, on the date of acquisition, pursuant to s 55(b). Because the valuers did not approach their valuations on that basis, and the primary judge consequently did not allow any amount for the loss of the farm structures beyond their value to the hypothetical purchaser of the acquired land, the issue must go back for redetermination in the Land and Environment Court: [20]-[24]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 55 applied.
Tolson v Roads and Maritime Services [2014] NSWCA 161; (2014) 201 LGERA 367; Mir Bros Unit Constructions Pty Ltd v Roads and Traffic Authority of New South Wales [2006] NSWCA 314 considered.
In relation to issue (iii),
Per Payne JA (Beazley P agreeing):
Neither of the amounts claimed as financial costs reasonably incurred in connection with the execution of a new mortgage resulting from the relocation were allowable within the scope of s 59(1)(e): [110]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 59(1)(e) applied.
Section 59(1)(f) must be read in its context as part of s 59 and in its place part of the tightly drawn constraints imposed by the section. It would not be a coherent application of s 59 for a financial cost which is specifically excluded from compensation by s 59(1)(e) to be allowable under the immediately succeeding sub-paragraph, 59(1)(f): [111]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), s 59(1)(f) applied.
Fitzpatrick Investments Pty Limited v Blacktown City Council (No 2) [2000] NSWLEC 139; (2000) 108 LGERA 417 considered.
Per Basten JA:
If the capital costs of the new farm structures were recoverable under s 59(1)(f), the financing costs must also be a direct and natural consequence of the acquisition. That connection was not established in circumstances where interest on compensation is payable pursuant to s 49(1), at the rate provided for in s 50, from the date of acquisition to the date of payment of the compensation: [26]
Land Acquisition (Just Terms Compensation) Act 1991 (NSW), ss 49(1), 50, 59(1)(f) applied.
In relation to (iv),
Per Payne JA (Beazley P and Basten JA agreeing):
The primary judge's award of compensation for the cost of road works was based on the only evidence before him of the cost of the road. The decision to accept this evidence was not "irrational, illogical and not reasonably open on the evidence". The appellants, who were given the opportunity to produce further evidence of additional payments made for the road, produced no such evidence: [123]