McMahon Services Australia Pty Ltd v Howmet Systems Australia Pty Ltd, formerly Alcoa Australia Rolled Products Pty Ltd
[2022] FCA 31
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2022-01-28
Before
Besanko J
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
- The applicant's Interlocutory application dated 15 June 2021 be dismissed. Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Introduction 1 This is an Interlocutory application by the applicant for further particulars of two paragraphs in the Defence filed by the respondent. The applicant in the proceeding is McMahon Services Australia Pty Ltd and it brings a total cost claim against the respondent in relation to the decommissioning and demolition of the respondent's Aluminium Smelting Plant in Yennora which is located in Western Sydney, New South Wales (the project). 2 Paragraph 114 of the applicant's Statement of claim is as follows: 114. The Change to Services caused the increased costs incurred by McMahon claimed in these proceedings, and: 114.1. the time-related costs of Variations as described at paragraphs [55] to [57] (inclusive) above are the best particulars that can be provided at this stage as to the causes of McMahon's claimed increased costs from those variations and delay and disruption; and 114.2. because of the nature of change in scope of works and delay and disruption, including the ongoing nature of them, and continual rescheduling, it is impractical and unreasonable, through no fault of McMahon, to provide further particulars of: 114.2.1. causation, beyond the matters described in the factual matters relied upon above; and 114.2.2. the different classes of costs and the causation of specific heads of costs in respect to each category, beyond that provided in the factual matters relied upon below; 114.3. the Change to Services, and the effects flowing from them, are the substantial causes of McMahon's claimed increased costs; 114.4. there are no other relevant and substantial causes of McMahon's claimed increased costs; 114.5. the increased costs claimed by McMahon would not have been incurred in any event or but/for the conduct of AARP described herein; 114.6. there has been no claim for, and McMahon's claim excludes, any increased costs substantially caused by matters other than AARP's actions; and 114.7. the costs claimed by McMahon are reasonable. 3 The phrase "Change to Services" used in this paragraph is defined elsewhere in the Statement of Claim as follows: Change to Services means additional works performed by McMahon as directed by AARP or for the benefit of AARP … 4 The paragraphs in the Defence which are relevant for the purposes of the Interlocutory application are as follows: 114. It denies paragraph 114 and says further that: … (c) in breach of the Contract, McMahon failed to exercise due skill, care and diligence in the execution of the Services by mismanaging the planning, timing and sequencing of the Services as required by Clause 5.2 of the Umbrella Agreement; Particulars Particulars will be provided prior to the hearing. (d) McMahon underestimated the equipment requirements to perform the demolition work and consequently underestimated the tender price and the period of time required to complete the Services; and Particulars Particulars will be provided prior to the hearing. … 5 The order which is sought by the applicant is that the respondent provide further particulars of paragraphs 114(c) and 114(d) of the Defence.