*Only new item
Further to the above, the Owner gives notice that;
A. Some of the delays alleged by the Builder are concurrent delays. For the Builder to simply add up the number of days the works were allegedly delayed by, after various events occurred, is without contractual basis and results in an untenable position of the Builder.
B. Importantly:
i. the Builder previously issued claims for extensions of time on 31 January 2019 and 12 March 2019, which collectively contained items (1) to (13) above.
ii. the Owner responded to the Builder's claim for extensions of time dated 31 January 2019 by notice served on the Builder on 7 February 2019 and In that response addressed items (1) to (10) above;
iii. the Owner responded to the Builder's claim for extensions of time dated 12 March 2019 by notice served on the Builder om 15 March 2019 and in that response addressed items (11) to (13) above;
iv. the Builder has failed to acknowledge that the Builder's previous extension of time claims are without basis and has simply repeated those claims on 12 March 2019 and 8 April 2019.
C. The date for practical completion in the Contract is 7 November 2018. With an extension of time of 24 business days as accepted by the Owner the works under the Contract were due to be completed by 11 December 2018.
D. The Builder's claim for extensions of time until 16 December 2019 is strenuously rejected by the Owner and held to be wholly unsubstantiated. The Owner requires the Builder to proceed with the works under the Contract with due diligence and without further delay.
E. The Owner reserves her rights in respect of claiming delay damages from the Builder, including loss of rent arising from an inability to lease the dwelling, and storage costs arising from being unable to furnish the dwelling, since the date for completion under the Contract."
- On 16 April 2019 at 8.37am, Mr Tengstrom sent an email to the owner and the builder in which he requested her to get Sydney Tap to contact her when they received the handle so that he could book in the plumber (the 16 April 2019 at 8.37am email).
- On 24 April 2019, the owner's lawyers sent a letter to the builder's lawyers enclosing the 24 April 2019 notice in which the owner relevantly stated:
"THE OWNER GIVES NOTICE pursuant to clause 25 of the Contract, that the Builder has failed to remedy his breaches of the Contract, such breaches being notified to the Builder in writing by Notice of Default dated 5 April 2019:
1. The Builder is failing to diligently proceed with the work under the Contract (Works); and
2. The Builder has failed to remedy defects in the Works and remove faulty or unsuitable materials used in relation to the Works;
FURTHER, THE OWNER GIVES NOTICE to the Builder pursuant to clause 25 of the Contract that the Contract is hereby terminated.
FURTHER AND IN THE ALTERNATIVE, THE OWNER GIVES NOTICE that the Builder has demonstrated that the Builder cannot complete the Works within the time agreed under the Contract, namely 36 calendar weeks from the date referred to in Clause 5 of the Contract (1 March 2018), adjusted in accordance with the terms of the Contract, and such timeframe is an essential term of the Contract. The Owner gives notice that she exercises her common law right to terminate the Contract."
- In the 6 May 2019 letter the builder's lawyers relevantly stated:
We refer to your client's purported Notice of Termination dated 24 April 2019, and are instructed to reply to that purported notice as follows:
No Basis for Termination & Defective Notices
There is no basis for the purported termination, and the purported termination notice is defective on the following grounds;
1. On 29 March 2019, your client demanded the rectification of defects other than in accordance with contract Clause 23. This demand was premature, as clause 23 deals with defects and the time for the same to be rectified. Your client has 13 weeks from the date of completion which is defined in clause 8, of the contract.
2. Following the letter dated 29 March 2019, your client has then purported to issue a Notice of Default. That notice is dated 5 April 2019, and is defective in that it seeks to engage Clause 23 of the Contract in circumstances where to do such is entirely premature. The second part of the notice relies on the proposition that the Builder has failed to proceed diligently with the work. This is a factual matter and would no doubt be the subject of evidence. That said because your client has introduced prematurely the "Notification of Defects" the entirety of the notice is defective.
3. In a further letter dated 12 April 2019, your client makes reference to Clause 23 of the Contract, which states in the margin note that; defect rectification is not to be used to finish items of work that should have been completed.
4. The suggestion that work is not being done belies the correspondence with the Builder. See for example the email from the Builder to the Owner dated 28 March 2019, copy attached.
5. On 11 April 2019, there then appears to be a purported notice issued by your client pursuant to Clause 7 of the Contract disputing the extension of time claimed by the Builder. This then requires the matter in the absence of agreement to be dealt with in accordance with Clause 27 (Dispute Resolution), That has not occurred.
6. Finally, your client has issued a purported Notice of Termination pursuant to Clause 25 of the Contract. The purported Termination Notice is defective because it proceeds on two (2) erroneous bases, one of which is patently wrong, namely item 2 which is directed at the "completion of work" that is only engaged in Clause 23 of the contract and self-evidently permits a Defects rectification period of 13 weeks. That time has not commenced and the mechanism in the contract has not been followed.
Builders Acceptance of Repudiation by Owner
We hereby advise and give notice that your client's conduct amounts to a repudiation of the contract, and our client accepts that repudiation and will now sue her for the loss and damages suffered which arise from her repudiatory conduct in accordance with the contract terms.
We otherwise reserve all of our client's rights, including the tendering of this letter on any issue including costs."