[2021] NSWCATCD 145
NCAT Consumer and Commercial
2021-04-29
Blake AM
Original judgment source is linked above.
Introduction
The evidence
The applicable contractual terms
The correspondence between the parties
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions
Consideration
Whether the builder failed to proceed with the works diligently in breach of the contract as at 5 April 2019
Introduction
The applicable legal principles
The evidence
The applicable contractual terms
The correspondence between the parties
The first Mullally affidavit
The second Mullally affidavit
The Lucien witness statement
The first Lucien affidavit
The second Jamieson report
The submissions of the owner
The submissions of the builder
Consideration
Whether the builder failed to remedy defective work or remove faulty or unsuitable materials in breach of the contract as at 5 April 2019
Introduction
The evidence
The applicable contractual terms
The correspondence between the parties
The first Lucien affidavit
The oral evidence of the builder
The joint building report
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
Whether the owner validly terminated the contract under its terms
Introduction
The evidence
The applicable contractual terms
The correspondence between the parties
Correction of structural plans 5 business days 15 November 2018
Re-location of floor 5 business days 22 November 2018
wastes
New window / door supplier 34 business days 18 January 2019
Police suspension of works 14 December 2018 48 business days 27 March 2019
Christmas shut down: 25.12.18-1.1.19 6 business days 4 April 2019
Australia day holiday 1 business day 5 April 2019
Unavailability of kitchen manufacturer to supply doors 7.12.18-20.1.19 21.1.19-21.2.19 44 business days 6 June 2019
Non-selection of paint colours by owner 31.1.19-21.2.19 15 business days 27 June 2019
Rain days 10 business days 11 July 2019
Delay caused by owner's stone floor suppliers and installers 8 business days 23 July 2019
Inability to carry bathtub delivered on 25 February 2019, to upstairs bathroom, due to inadequate width of stairs or size of bathtub. 9 days and ongoing 5 August 2019
Delay in delivery of tapware and fixtures and fittings 7 days 14 August
2019
Delay caused due to change in front door previously approved by Owner and door hardware. 10 Days and ongoing 28 August
2019
14 Change to garage door selection by Owner on 1 April 2019, 110 days and ongoing 16 December 2019 Period of delay 11 December 2018, to 1 April 2019 Total 305 days Revised date for practical completion 16 December 2019
Pursuant to clause 7 of the contract our client claims an extension for the reasons stated above and as notified, fi-om 9 November 2018 until 16 December 2019. Given the above our client anticipates that a revised date for practical completion of the work will be on 16 December 2019, noting that your clients home will be reasonably capable of being used, in accordance with clause 8 of the contract before that date due to our client's diligent work, which continues on site, despite your client's contentions."
Correction of structural plans 5 Extension of time accepted 5
Re-location of floor wastes 5 Extension of time accepted, although 5 business days is generous 5
Extension of time not accepted.
New window/door 34 The window delay was caused by the manufacturer "Aneeta", not the nominated supplier, "Lifestyle Glass". Aneeta carry out the installation of ail their windows therefore the original supplier, "Iconic", would have also been delayed by Aneeta. 7
supplier Iconic carried out a final check measure on 26/07/18 and Lifestyle Glass carried out their final check measure on 1/08/18. The delay caused by the change in window supplier was therefore 7 business days.
The Owner is not responsible for delays caused by the Builder's subcontractors and suppliers - any such delay is a matter between the Builder and the third party.
Extension of time not accepted.
On 14 December 2018 the Builder caused the plasterers to sand the walls and the timber floors to be laid (on incorrect frame) simultaneously with the painters painting the walls. This was ruining the finish of the painting and was dearly a sequencing problem which would mean the painting would have to be re-done. In order to mitigate loss (of either party) the Owner raised the issue with the Builder, which caused him to become aggressive towards the Owner.
Police suspension of works 14 December 2018 48 On 14 December 2018 at 7:26am the Builder threatened the Owner on site, raising his clenched fist to the Owner's face and saying words to the effect of; "If you were a man, 1 would punch you in the face". 0
Furthermore, the Builder threatened to cause damage to the Owner's property, saying words to the effect of: "/ will make sure that you never get to move into your house. 1 will smash it all down."
As such, the police assistance sought by the Owner was, without a doubt, warranted and due to the fault of the Builder. The Builder was locked out by the Owner from approximately 5:45pm on Friday 14 December 2018 until 6;00am Tuesday 18 December 2018, which is a total of one (1) working day. The Builder chose not to carry out any further work at the site until 14 January 2019.
The Builder's assertion that a delay of 48 business days ensued following the police intervention (which in itself was the result of threatened violence by the Builder) is utterly absurd and without merit.
Christmas shutdown 6 Extension of time is accepted. 6
Although, If the Builder had carried out works under the Contract with due diligence and completed works by Christmas as he was contractually obliged to do, the Christmas shut down period would not have been in any way relevant.
Australia Day Holiday 1 Extension of time is accepted. 1
Although, if the Builder had carried out works under the Contract with due diligence and completed works by Christmas as he was contractually obliged to do, the Christmas shut down period would not have been in any way relevant.
Extension of time not accepted.
Unavailability of kitchen manufacturer to supply doors 44 There was no meeting with the joiner scheduled for 7 December 2018. The Owner received a text message at 7;33am on 7 December 2018 from the foreman saying: "Can you come in this morning?" however the Owner was not available. No meeting with the joiner was "cancelled" by the Owner. 0
The Builder failed to ensure the joiner proceeded with due diligence and the resulting delay is the fault of the Builder.
The Owner is not responsible for delays caused by the Builder's subcontractors and suppliers - any such delay is a matter between the Builder and the third party.
Non-selection of paint colours by owner 15 Extension of time not accepted. 0
The paint colours are specified by AKD and are already part of the Contract. No selection by the Owner is required and, as such, the extension of time claim is unsubstantiated and illogical.
Extension of time not accepted.
Rain days 10 The Contract provides at clause 7; "Both the contractor and the owner (if applicable) must take all reasonable steps to minimise any delay to the work". Furthermore, the work as a whole must be affected by the delay and the critical path of construction activity interrupted. 0
The Builder could have carried out internal work on rain days.
Extension of time not accepted.
*Only new item Further to the above, the Owner gives notice that; A. Some of the delays alleged by the Builder are concurrent delays. For the Builder to simply add up the number of days the works were allegedly delayed by, after various events occurred, is without contractual basis and results in an untenable position of the Builder. B. Importantly: i. the Builder previously issued claims for extensions of time on 31 January 2019 and 12 March 2019, which collectively contained items (1) to (13) above. ii. the Owner responded to the Builder's claim for extensions of time dated 31 January 2019 by notice served on the Builder on 7 February 2019 and In that response addressed items (1) to (10) above; iii. the Owner responded to the Builder's claim for extensions of time dated 12 March 2019 by notice served on the Builder om 15 March 2019 and in that response addressed items (11) to (13) above; iv. the Builder has failed to acknowledge that the Builder's previous extension of time claims are without basis and has simply repeated those claims on 12 March 2019 and 8 April 2019. C. The date for practical completion in the Contract is 7 November 2018. With an extension of time of 24 business days as accepted by the Owner the works under the Contract were due to be completed by 11 December 2018. D. The Builder's claim for extensions of time until 16 December 2019 is strenuously rejected by the Owner and held to be wholly unsubstantiated. The Owner requires the Builder to proceed with the works under the Contract with due diligence and without further delay. E. The Owner reserves her rights in respect of claiming delay damages from the Builder, including loss of rent arising from an inability to lease the dwelling, and storage costs arising from being unable to furnish the dwelling, since the date for completion under the Contract."
The submissions of the builder
The submissions of the owner
Consideration
Whether the owner validly terminated the contract under the general law
Introduction
The evidence
The applicable legal principles
The submissions of the owner
The submissions of the builder
Consideration
Whether the works undertaken by the builder were defective, and if so the reasonable cost of rectifying the defects
Introduction
The rate for labour that should be allowed to rectify defective works
The first Jamieson report
The Lee report
The concurrent oral evidence of the experts
Consideration
The time that should be allowed to rectify defective works
The first Jamieson report
The Lee report
The concurrent oral evidence of the experts
Consideration
Item 11.1 - First floor addition - insulation in the roof cavity
The joint building report.
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
Item 11.4 - First floor addition - ceiling penetrations
The applicable contractual terms
The Pearce report
The joint building report
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
Item 12.1 - First floor addition - external wall insulation
The joint building report
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
Item 14 - Water ingress on southern boundary above internal stairs
The Zakrzewski report
The Kyle report
The second Mullally affidavit
The Burton report
The joint building report
The oral evidence of the builder
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
Items 16, 17 and 18 - Preliminaries, Overhead & Profit, and Contingency
The joint building report
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
Conclusion
Whether the builder ought to be ordered to pay damages rather than rectify the defective work
Introduction
The applicable provisions of the HB Act
The application of s 48MA of the HB Act
The measure of damages for breach of a building contract
The submissions of the owner
The submissions of the builder
Consideration
Whether the works undertaken by the builder were incomplete, and if so the damages recoverable by the owner
Introduction
The applicable contractual terms
The first Jamieson report
The submissions of the owner
The submissions of the builder
Consideration
Item 47 - A9 - garage bin storage enclosure not erected
The applicable contractual terms
The first Jamieson report
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The correspondence between the parties
The second Jamieson report
The submissions of the owner
The submissions of the builder
Consideration
Item 65 - B24 - allowance for Rinnal 26 with fluting
The applicable contractual terms
The first Mullally affidavit
The first Lucien affidavit
The joint building report
The first Jamieson report
The submissions of the owner
The submissions of the builder
Consideration
Item 66 - B25 - supply and install Clipsall Classic 2000 power points and Clipsall Classic 2000 power points with USB
The applicable contractual terms
The first Mullally affidavit
The first Lucien affidavit
The first Jamieson report
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The first Mullally affidavit
The first Lucien affidavit
The Lee report
The oral evidence of the builder
The oral evidence of the owner
The concurrent oral evidence of the experts
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The submissions of the owner
The submissions of the builder
The submissions in reply of the owner
Consideration
The applicable contractual terms
The first Mullally affidavit
The Lucien witness statement
The first Lucien affidavit
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The first Mullally affidavit
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The correspondence between the parties
The first Mullally affidavit
The submissions of the owner
The submissions of the builder
Consideration
Conclusion
Whether the owner paid for work to be undertaken by the builder, and if so is entitled to restitution of the amount paid
Introduction
Items 74 and 75 - Volar screens 50%contributionand other 50%contribution
The applicable contractual terms
The correspondence between the parties
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The first Mullally affidavit
The Lucien witness statement
The oral evidence of the builder
The submissions of the owner
The submissions of the builder
Consideration
The applicable contractual terms
The correspondence between the parties
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The submissions of the owner
The submissions of the builder
Consideration
Item 80 - credit for Vola flush plates supplied but not installed
The applicable contractual terms
The correspondence between the parties
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The submissions of the owner
The submissions of the builder
Consideration
Conclusion
Whether the owner is entitled to damages for damages for delay
Introduction
The applicable legal principles
The first Lucien affidavit
The submissions of the owner
The submissions of the builder
Consideration
Whether the builder is entitled to be paid for variations and additional works, and if so what amount
Introduction
Quantum meruit
The Lucien witness statement
The first Mullally affidavit
The front door
The correspondence between the parties
The submissions of the builder
The submissions of the owner
Consideration
The applicable contractual terms
The Lucien witness statement
The first Mullally affidavit
The first Lucien affidavit
The second Mullally affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions of the builder
The submissions of the owner
Consideration
The applicable contractual terms
The Lucien witness statement
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions of the builder
The submissions of the owner
Consideration
Item 34 - Additional works - Fitting of TV unit in bedroom
The Lucien witness statement
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions of the parties
Consideration
Item 35 - Additional works - Rendering neighbour's side fence
The Lucien witness statement
The first Mullally affidavit
The oral evidence of the builder
The oral evidence of the owner
The submissions of the builder
The submissions of the owner
Consideration
Item 36 - Additional works - Suspended ceiling first floor
The applicable contractual terms
The Lucien witness statement
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder and the owner
The submissions of the builder
The submissions of the owner
Consideration
Item 37 - Additional works - Change floor batten level on ground floor
The correspondence between the parties
The Lucien witness statement
The first Mullally affidavit
The first Lucien affidavit
The oral evidence of the builder
The submissions of the builder
The submissions of the owner
Consideration
Conclusion
The costs of the two proceedings
Orders
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 16 February 2022
Kitto v TGSBC Pty Ltd [2004] WABDT 28 Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115; [2007] HCA 61 Lawrence v Ciantar; Ciantar v Lawrence [2019] NSWSC 464 Leeda Projects Pty Ltd v Zeng (2020) 61 VR 384; [2020] VSCA 192 Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635; [2008] HCA 27 Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221; [1987] HCA 5 Toplace Pty Ltd v Rashidianfar [2021] NSWCATAP 235 Roude v Helwani [2020] NSWCA 310 Vasco Investments Ltd v Morgan Stanley Australia Ltd [2014] VSC 455 Woodward v D J & T L Mellross Pty Ltd [2018] NSWCATAP 179 Xtraordinary Constructions Pty Ltd v Luppino [2021] SASC 132 Texts Cited: J Edelman, McGregor on Damages (21st edition, 2020, Thomson Reuters) New South Wales Legislative Assembly, Parliamentary Debates (Hansard), 6 May 2014 Rawlinsons Australian Construction Handbook (38th edition, 2020, Rawlinsons Publishing) Category: Principal judgment Parties: HB 19/48969: Anthony Allan Lucien (Applicant) Nerida Mullally (Respondent)
The relevant legal principles
[2020] VSCA 192
[2014] VSC 455
[2021] SASC 132
[2007] QCA 136
[2010] WASC 160
(1995) 65 SASR 1
(2007) 233 CLR 115
(2020) 61 VR 384
(2008) 232 CLR 635
(1987) 162 CLR 221
(2006) 65 NSWLR 648