(ii) Item 893.14 is described as "strip lighting to stair missing", however no location is specified. The plaintiff has been unable to locate this alleged defect.
54 In Re Stewardson Stubbs and Collett Pty Ltd v Bankstown Municipal Council (1965) NSWLR 1671 the court was concerned with a contract which required the relevant notice "specify the default". Moffit J at 1675 commented on this provision as follows:
"A default can be specified in two ways; one is by directing attention to the provision in the contract in respect of which default is made. The other is by giving particulars of the manner in which a breach has occurred. In order to specify the default I think at least the former must be pointed out. But each case will depend on its own circumstances as to whether in order to specify the default there must be added some particulars such as will identify the particular breach alleged."
55 The defendant also referred to Hounslow London Borough Council v Twickenham Garden Developments Ltd (1971) 1 Ch 233 at 265, "to suggest that the level of detail need only direct the contractor's mind to what is said to be amiss". In FPM Constructions Pty Ltd v Council of the City of Blue Mountains [2005] NSWCA 340, the Court of Appeal approved that statement and said at [151] the following:
"151 It follows that a contractual notice should be read with the understanding which will be brought to the exercise by the recipient, including his or her knowledge of the circumstances in which it is given. If the recipient is a builder, it should not be assumed that the reader will understand technical legal terms, but it may be assumed that expressions commonly adopted in that industry will be understood. However, each case will turn upon its own particular circumstances, including the identity of the contracting parties. In the same way, the notice need not be construed as a contract, eschewing reference to any material not identified on the printed page. That does not mean that the builder should be left to guess at the provision said to have been breached, nor as to the particular conduct said to be in breach, if that has not been specified and if there is doubt as to its identity. Further, in considering whether a particular notice is adequate to identify a particular breach, a court may take into account the response of the builder. That is not, of course, to say that the builder can demonstrate inadequacy by simply claiming that no response can properly be given; however, where an appropriate response is provided, the adequacy of the notice may be difficult to dispute."
56 Returning to the notice, the nature of the contractual provisions that have been breached have been set out by reference to the paragraphs in the contract. In respect of the first breach the relevant clauses have been specified. Those clauses specify a time for compliance, which was passed when the notice was issued. The second breach namely the failure to rectify the defects correctly refers to the clauses referring to an obligation to rectify. However under the terms of clause 10.15 the rectification must be carried out prior to final completion or as specified in the project director's notice. In each case it is presently 30 June 2011. Thus time had not passed at the time of the issue of the clause 16.2 notice so arguably there would be no breach in respect of the failure to rectify. Thus the drawing of attention to the particular items of work assumes more importance.
57 So far as drawing attention to the particular items of work are concerned, the table attached to the notice identifies the location of the problem and then contains two columns headed "General Remarks" and "Defect Description". A general perusal of them indicates what one would imagine would be sufficient to draw the contractor's attention to the problem concerned. From the first example quoted the claim that there is no requirement for inspection risers suggests that that the contractor would wish to dispute the contractual basis for this requirement. One can thus assume there might be a dispute about it. As to the second item, it is true that there is no location specified in the schedule.
58 So far as the time allowed, there is only two months allowed after a week for establishment. Evidence has been given that this should be adequate. The only suggestion in the evidence of any problem that would impact upon this, seems to be the question of re-cuttings some travertine benches. The evidence sought to be led by the plaintiff of the lead-time was rejected and accordingly the only evidence available suggests that this may take four weeks to cut. This no doubt can be accommodated in the program and one would have thought that since this defect had been notified in 2009 that it may have been put in hand.
59 It is to be noted that there are 154 defects in the clause 16.2 notice for which 2 months is allowed compared with the 1521 defects in the project directors notice for which 12 months was allowed. Naturally the 154 probably contain the more serious of the defects.
60 Having regard to the evidence, there is plainly no arguable case that the time given in the notice is not appropriate.
61 Another point in respect of the breach that is necessary to support a notice under clause 16 is that the actual breach alleged in the notice does not have to be established as for a notice to be valid there need only be a bone fide claim by the proprietor that the builder has not materially complied with its obligations under the contract.
62 In support of this construction of clause 16.2, the defendant relies on Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd (No 3) [2007] FCA 2082 in which Gilmour J held:
"[39] If it were the case that, on its proper construction, ONGC could not call on the guarantees until there was an admitted or established breach of contract, the time at which an arbitral tribunal or court might determine that matter could well be after the performance guarantees had expired: cf Ideas Plus Investments at [39] per Steytler P. Such a construction does not, in my view, make commercial common sense: McCann v Switzerland Insurance Australia Limited (2000) 203 CLR 579 at [22] and [23] per Gleeson CJ.