Progress claim 9
23 FPM Constructions claimed to be entitled to payment of $285,580.90 the subject of progress claim 9 delivered on 9 April 2003. The Council contended that it was not obliged to pay because the Contract was terminated on 10 April 2004, before FPM Constructions became entitled to payment. For present purposes I assume that the Contract was validly terminated, see later in these reasons. The Superintendent did not issue a payment certificate on the progress claim, prior to termination or at all.
24 I will return to the question of a false statutory declaration in relation to progress claim 9.
25 FPM Constructions contended that the termination of the Contract discharged the parties from further performance, but did not divest "rights which have already been unconditionally acquired" (McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457 at 477 per Dixon J); it said that it had an accrued right to payment. If it did, it could recover the payment notwithstanding termination (see Hyundai Heavy Industries Co Ltd v Papadopoulos (1980) 1 WLR 1129; Stocznia Gdanska SA v Latvian Shipping Co (1998) 2 WLR 574). The argument came down to the submission that, by force of cl 42.1, having delivered the progress claim it had an accrued right to recover either the amount certified by the Superintendent or, if the Superintendent did not issue a payment certificate within 28 days, the amount of the progress claim; that it had the right at the time the Contract was terminated even though it was not then known which of the amounts it could recover because there had not been certification and the 28 days had not elapsed; and that, after the lapse of the 28 days without certification, the amount was known to be the amount of the progress claim.
26 We were referred to Aquatec-Maxcon Pty Ltd v Minson Nacap Pty Ltd [2004] VSCA 18. Implicit in the discussion of ground 7 in its [31]-[45] was that the contractor under AS4303-1999 had an accrued right to be paid its progress claims at the time the contract was terminated. From the decision at first instance, Minson Nacap Pty Ltd v Aquatec-Maxcon Pty Ltd [2000] VSC 402, the progress claims 13, 14 and 15 had been delivered and the Superintendent had not issued payment certificates within the required 35 days, all before termination. The case does not assist on the present question.
27 By cl 44.10, on termination of the Contract the rights and liabilities of the parties were "the same as they would have been at common law had [FPM Constructions] repudiated the Contract and [the Council] elected to treat the Contract at an end and recover damages". This did not exclude the accrued right principle of McDonald v Dennys Lascelles Ltd; it made it necessary to decide whether FPM Constructions had the accrued right.
28 In asking whether FPM Constructions had the accrued right, there must be considered whether the Superintendent had power to issue a payment certificate after termination of the Contract. If termination of the Contract brought to an end his power in that respect, FPM Constructions could not have a right to the amount certified by him, because it could not call for certification. Nor do I think it could have a right to the amount of the progress claim in default of certification within 28 days, because the default provision assumed possible, indeed expected, certification by the Superintendent and operated in default of that occurring. I do not think it operated if the default was that the Superintendent's power had come to an end.
29 It is well established that the acceptance by an innocent party of the repudiation of a contract does not bring the contract to an end for all purposes. An arbitration clause part of the contract may continue to have effect (Heyman v Darwins Ltd (1942) AC 356; Codelfa Constructions Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337), as may a choice of forum, a choice of law or a limitation clause (Photo Production Ltd v Securicor Transport Ltd (1980) AC 827; Port Jackson Stevedoring Pty Ltd v Salmond and Spraggon (Australia) Pty Ltd (1980) 144 CLR 300).
30 In Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd (2002) BCL 322 this Court held that the Superintendent under AS2124-1992 could grant an extension of time after the contract had been terminated, even if the contractor had not applied for it prior to termination; see at [80]. The decision has been questioned by a learned commentator in 18 BCL 281, although with less doubt if the contractor had applied for the extension of time prior to termination, and does not directly transpose to certification of payment under the Contract. The notion of a Superintendent's power surviving termination for some purposes was nonetheless recognised.
31 The Contract provided for appointment of a Superintendent, and provided that the Principal should ensure that there was at all times a Superintendent and that "in the exercise of the functions of a Superintendent under the Contract" the Superintendent should act honestly and fairly, in a timely manner and reasonably (cl 23). The Superintendent was given a number of "functions". Some could only arise while work was being carried out (for example, interpreting ambiguities or discrepancies (cl 8.1), approving a proposed subcontractor (cl 9.2), providing information for setting out (cl 28.1), directing the order of works (cl 33.1), directing suspension of work (cl 32.1) and variations to the work (cl 40.1)). Others were not functions to be performed only while work was being carried out (the obvious example is issuing the Final Certificate (cl 42.6)). Granting extensions of time and issuing payment certificates were functions which could be performed after work had ceased, since they called for assessment of past carrying out of work.
32 It is another question again whether the functions could be performed after termination of the Contract. Reference to exercise of the functions of a Superintendent "under the Contract", however, did not in my view mean that the Contract had still to subsist. It meant that the functions were found in the Contract. Nothing else confined the exercise of the function of issuing a payment certificate, at least where the exercise of the function has been initiated by delivery of a progress claim, to the subsistence of the Contract.
33 The duration of the Superintendent's power must be found in the parties' intention as revealed in the Contract. There was no express revelation. There was, however, provision for FPM Constructions to receive periodical payment for work it had carried out, with a mechanism for arriving at an amount payable. The mechanism of progress claim followed by certification and payment or default payment recognised that FPM Constructions should be paid for work it had carried out, the payment being on account only and subject to a final working out of the position between the parties (cl 42.1 last sentence). There was obvious good sense in the Superintendent dealing with a progress claim outstanding at the time of termination, in order to give effect to the mechanism for payment for work carried out in the past, and a Principal which terminated the Contract (or accepted a repudiation) could scarcely complain if it nonetheless had to pay for the past work in accordance with the contractual mechanism earlier set in motion.
34 In my opinion, despite the termination of the Contract the Superintendent could issue a payment certificate on progress claim 9.
35 The effect of cl 23 was that the Council had to ensure that the Superintendent dealt with the progress claim, and to that extent further performance was required of it. But the Contract made provision for failure in timely dealing with the progress claim, and so for what happened when the Council did not ensure that the Superintendent dealt with it - not by way of damages, but by the default entitlement to payment of the amount of the progress claim.
36 In Westralian Farmers Ltd v Commonwealth Agricultural Service Engineers Ltd (in liquidation) (1936) 54 CLR 361 a selling agent was appointed to buy tractors from the manufacturer in America for resale, and was entitled to a percentage rebate payable on arrival of the tractors in Australia. It bought some tractors. The agency agreement was thereafter terminated, but before the arrival of the tractors. It was held that the manufacturer was liable to pay the rebate.
37 The joint judgment of Dixon and Evatt JJ included (at 379-80) -
"The first ground upon which the appellant company denies its liability to pay the percentage upon these tractors is that under the terms of the agreement no such liability could arise until the goods arrived at Fremantle and before this happened the contract ceased to have any further executory operation. When a contract comes to an end by reason of the occurrence of an event upon which the parties have by an express provision made it terminate, the question whether an inchoate liability arising thereunder does or does not become enforceable must in the end be governed by the intention of the parties. It is a rule of law that when a simple contract is discharged by the election of one party to treat himself as no longer bound after the other has committed a breach of the contract, rights and obligations which have already arisen from the partial execution of the contract shall remain unaffected (see McDonald v. Dennys Lascelles Ltd . No doubt it is open to the parties to provide in advance for such an event and by a stipulation to the contrary to produce some other effect. When the parties themselves have provided for the determination of the contract on a given contingency, the consequences flow altogether from their contractual stipulation and are governed by their intention, either actual or imputed. In the present case, however, all the agreement expressly says is that in any of the specified events it shall immediately terminate and be at an end. In applying such a compendious provision to a continuing relationship of the complicated character which the agreement establishes some guidance may be found in the nature of the agreement and of the obligations to which it gives rise. But primarily it remits the inquiry to a general consideration of what is involved in the sudden termination of an executory agreement under which liabilities are accruing from day to day. We are concerned only with a liability to pay a liquidated demand. In general the termination of an executory agreement out of the performance of which pecuniary demands may arise imports that, just as on the one side no further acts of performance can be required, so, on the other side, no liability can be brought into existence if it depends upon a further act of performance. If the title to rights consists of vestitive facts which would result from the further execution of the contract but which have not been brought about before the agreement terminates, the rights cannot arise. But if all the facts have occurred which entitle one party to such a right as a debt, a distinct chose in action which for many purposes is conceived as possessing proprietary characteristics, the fact that the right to payment is future or is contingent upon some event, not involving further performance of the contract, does not prevent it maturing into an immediately enforceable obligation.
38 I do not think that provision for certification by the Superintendent involved FPM Constructions' entitlement to payment being contingent on further performance of the Contract. If the Superintendent certified, exercising his function notwithstanding termination of the Contract, FPM Constructions was entitled to payment pursuant to the Contract and notwithstanding its termination - no question of accrued right arose. If the Superintendent did not certify, the event on which the right to payment turned was the lapse of 28 days; not performance of the Contract, but if anything its non-performance. As Westralian Farmers Ltd v Commonwealth Agricultural Service Engineers Ltd (in liquidation) shows, it does not matter that FPM Constructions' inchoate right matured into an enforceable obligation only after termination. In my opinion, subject to considering its bifurcation it should be held that FPM Constructions had an accrued right as at the termination of the Contract.
39 I do not think it matters that it was not then known whether the right would be an entitlement to the amount in a payment certificate or, in default, the amount of the progress claim. A right to damages for breach of contract may be an accrued right, although the amount of the damages is not known. A right to one amount of damages plainly differs from a right to one or other of two amounts depending upon whether a payment certificate is issued, but it demonstrates that what matters is the right, not its outcome. FPM Constructions had a right which would result in one or other of the two amounts, in the manner the mechanism worked a right to the amount of the progress claim after the lapse of 28 days defeasible to a certified amount if the Superintendent issued a payment certificate. In my opinion, that was within the accrued right principle of McDonald v Dennys Lascelles Ltd.
40 I return to the question of a false statutory declaration in relation to progress claim 9.
41 The Council's pleaded defence alleged that FPM Constructions had not given the Superintendent a statutory declaration as required by cl 43.2. The language was of no statutory declaration at all, unlike that of the defence in relation to progress claim 8 which alleged that a false statutory declaration had been provided.
42 According to an affidavit of Mr Yazbek sworn on 19 June 2003, a statutory declaration declared on 16 June 2003 and referable to progress claim 9 was sent to the Council on that date. The Council's defence was dated 16 June 2003 and was filed on 17 June 2003. It is readily understandable that it was prepared and filed without knowledge of the statutory declaration.
43 The statutory declaration said that all subcontractors had been paid, in the same manner as the statutory declaration of 2 April 2003. The Council's evidence included evidence from representatives of AJC and Smith that the invoices earlier mentioned were unpaid as at 16 June 2003. That was not contested in other evidence.
44 The Council's written submissions provided to the judge identified as one of the issues -
"c. What was FPM Constructions Pty Limited ('FPM') required to deliver in accordance with clause 42.1 of the contract ('the contract') between FPM and the Council for the City of the Blue Mountains ('BMCC') in submitting payment claims (relevantly Progress Claim 8 and 9 ) to the superintendent, was such material delivered and the effect, if relevant, of any non-delivery on the determination of the superintendent?" (emphasis added)
45 Although the Council's defence with respect to progress claim 9 was not amended, this provides strong grounds for the conclusion that the defence with respect to that progress claim became the same as the defence with respect to progress claim 8, that the statutory declaration provided to the Superintendent was false. No reason appears why the Council would not have propounded that defence, its evidence extending to the falsity of the statutory declaration of 16 June 2003, and the written submissions indicate that it relied on the defence. The body of the written submissions, however, dealt only with the false statutory declaration in relation to progress claim 8, although it did so as part of "Issue 3: the clause 42.1 obligation", apparently referable to the issue c earlier identified. The Council accepted in the supplementary written submissions later mentioned that it "did not submit to the trial judge that Progress Claim 9 was not payable because the relevant statutory declaration was false", which in the light of the issue c must mean did not expressly submit.
46 FPM Constructions' written submissions before the judge did not address either the statutory declaration of 2 April 2003 or that of 16 June 2003. They addressed a different statutory declaration again, that of 30 January 2003 the subject of the notice to show cause. It was in slightly different terms, and was accompanied by a letter referring specifically to AJC and Smith. The judge spoke of "the" or "a" statutory declaration; he said that he "refer[red] to the other proceedings as well", but that the statutory declaration was "part of the area of concern as far as the Council was concerned when it issued the Show Cause notice … ". This left uncertain whether his Honour had in mind a statutory declaration other than that of 30 January 2003, and if so which one or ones. His Honour did hold that the defence in respect of progress claim 8 had been made out, "particularly having regard to the deficits, if I could use that word, in the statutory declaration". He did not say the same as to progress claim 9, no doubt because he upheld the defence involving termination of the Contract.
47 If the Council's submissions dealing with the false statutory declaration in relation to progress claim 8 were accepted, the defence would seem to extend inevitably to progress claim 9. Whether the falsity of the statutory declaration of 16 June 2003 was in issue at the trial, as a defence with respect to progress claim 9, was nonetheless itself in issue on appeal. FPM Constructions maintained that it was not; the Council maintained that it was. These positions were taken, with each party stating the basis for its position, when after judgment had been reserved the Court sought clarification of the treatment of the matter in the submissions on appeal. Supplementary written submissions were received. Remarkably, the Council's written submissions perpetuated the error that the statutory declaration material to progress claim 8 was the declaration of 28 January 2003.
48 FPM's grounds of appeal appeared to be influenced by a misunderstanding that the only statutory declaration in question was that of 31 January 2003. They challenged that it was false. The written submissions did the same. The misunderstanding was appreciated in the course of FPM Constructions' oral submissions, and counsel put submissions in relation to the statutory declaration of 2 April 2003 and the defence concerning its falsity with respect to progress claim 8. But in commencing his oral submissions on appeal, counsel for FPM Constructions referred to "the statutory declaration to support progress claim 9" and said, "There is no suggestion that there is any falsity about that statutory declaration". His statement was not then controverted by counsel for the Council. He did not revisit progress claim 9 after the misunderstanding came to be appreciated.
49 The Council's written submissions were responsive to those of FPM Constructions, and did not expressly deal with the falsity of either of the other statutory declarations. When in due course counsel for the Council put oral submissions in relation to the statutory declaration of 2 April 2003 with respect to progress claim 8, at their conclusion he said, "Progress claim No 9 raises similar issues in relation to the stat dec and I don't need to go over them again". He did not elaborate.
50 Counsel for FPM Constructions did not return to the matter in reply.
51 It seems to me that the likely position is that, while the falsity of the statutory declaration of 16 June 2003 was an issue at the trial, the Council did not make fully clear that it relied on that falsity as a defence with respect to progress claim 9 and, perhaps with an erroneous focus on the statutory declaration of 31 January 2003 alone, FPM Constructions did not appreciate that the Council took that defence. Unfortunately, that remained the case on appeal, until the Court was moved to enquire further by the contrasting assertions in oral submissions to which I have referred.
52 It would be unpalatable to decide the appeal in this respect on a point over which there had been a misunderstanding. The Council submitted, however, that despite the regrettable history there could be no prejudice to FPM Constructions because it had stated plainly that progress claim 9 "raised similar issues in relation to the stat dec", FPM Constructions had not returned to the matter in reply, there was nothing FPM Constructions could say to avoid the inevitable extension of the defence to progress claim 9, and FPM Constructions had not said anything on the substance of the matter in its supplementary written submissions. It asked that, if a formal notice of contention was required, it have leave to file one.
53 The point arises only because I have held that FPM Constructions had an accrued right at the time the Contract was terminated, because its right was "[s]ubject to the provisions of the Contract", and thus subject to the Council withholding payment if a statutory declaration had not been provided to the Superintendent as required by cl 43.2. Beazley and Basten JJA are of a different view and the appeal in this respect will therefore fail on the prior question.
54 As at present advised, I consider that the statutory declaration defence in relation to progress claim 9 was before the judge, and was raised in the appeal and should be permitted to be formalised by a notice of contention; I am unable to see how FPM Constructions could distinguish recovery of progress claim 9 from recovery of progress claim 8 in this respect. I have, however, some disquiet that, even now, FPM Constructions has not addressed the substance of the defence. Accordingly, while I agree with the orders proposed by Basten JA, I have sought fully to explain the circumstances in which I have come to the view that the defence succeeds, and hence the appeal fails, as to progress claim 9.