© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2009] VCAT 1343
Victorian Civil and Administrative Tribunal
2009-07-13
Stuart J, Mr P
Original judgment source is linked above.
5m long x 0.9 wide grated outlet pit. Outfall flow will be pre-developed only grated pit will spread flows onto adjacent landowner
In truth there is no single test for whether declaratory relief should be given under Section 149B of the Planning and Environment Act 1987 where the purport of the application is that a particular action or determination is void. There are as many grounds for the Tribunal to make such a declaration as the general law on judicial review provides grounds for attack upon administrative action. Whole textbooks have been written on the subject. What is necessary is that a legal flaw must be found in what has been done. It is insufficient for an applicant for declaratory relief to persuade the Tribunal that had the Tribunal been 'standing in the shoes' of the decision maker it would have done otherwise. If the decision maker has acted legally and properly in making the impugned determination it cannot be declared invalid.
There is a well established principle in private law that the exercise of a right, for instance, to cancel a contract may later be defended in court upon a basis other than the one which the actor had in mind, even if the ground later relied upon was wholly unknown to him. Shepherd v Felt and Textiles of Australia [1931] HCA 21; (1931) 45 CLR 359.
MacMillan v Port Phillip City Council and Havercroft Pty Ltd [2005] VCAT 1793 [32], [35]
As buildings and works require a primary planning permission and there is no such planning permission, it is submitted that the .......... crushing plant cannot be the subject of a secondary consent approval.
It is trite to say that a permit cannot be granted for a development that was not the subject of the planning permit application.
It would have been sought as part of the permit application. It would have been detailed on the application plans as was the concrete batching plant.
The materials recycling activity is to be undertaken by a mobile crushing plant within the designated area.
The stockpile areas occupy a total of 17,550 sq m as compared to 2,700 sq m as depicted in the application plans.
The Tribunal finds the plan to locate a drainage storage basin adjacent to both the existing leachate dam and materials crushing facility is a practical way of preventing drainage entering the Love property and provides the opportunity for water re-use in either concrete batching operations or dust suppression measures.
Shows only the internal roadways being area to be wetted down as per dust management plan.
If the intention was truly to ensure that no water drained from the subject land onto any other land, then it is difficult to understand the choice of the word 'from'. If all the runoff was to be contained within the site boundaries then there would be no drainage 'from the site' at all.
The method of disposal of stormwater from all roofed, sealed and stockpiled areas, including the use of an on-site detention system (if required).
Should be interpreted in a manner which enables it to operate in a valid and reasonable way, rather than in a way which would be invalid or unreasonable (having regard to the nature of the permission being granted).
Condition 13 should be confined to the need to drain any runoff water that is generated as a consequence of the use and development authorised by the permit.
Given the secondary consent power contained in Condition 8 the permit itself enables further permission to be granted for buildings and works of that nature.
When it comes to determining consistency with a permit, it is necessary to consider not only the words used in the permit, but also the conditions of the permit.[1] In the present case, these conditions include condition 2. Hence this permit envisages that, once plans have been endorsed under condition 1, the development may be altered from that described on those endorsed plans if the responsible authority consents in writing. No doubt a point will be reached when the changes result in development that is outside the scope of what was contemplated by the permit and its conditions, but that point is not reached simply because the changes result in development that is not in accordance with the endorsed plans or, for that matter, that is not in accordance with plans which might be endorsed under condition 1.
Either the type of crushing plant nor its appearance. This indicates therefore that there was no intention to be restrictive on this front.
From a planning merits perspective, Council is comfortable with the structure that has been assembled for the purpose of rock crushing. Visual amenity impacts are limited, having regard to the nature of the site and surrounds. Other amenity impacts can be adequately managed.
The intent of Condition 13 is to collect uncontrolled stormwater discharge. Condition 13 cannot be interpreted to mean that no stormwater can be discharged beyond the site boundaries. Rather the condition means that stormwater flowing from the permitted uses should be contained before being allowed to flow from the site.
Achieves the outcome that water leaves the land at a rate and quality that would flow onto the adjacent land prior to the development.
Commonsense dictates that, at least in some circumstances, water falling on the site will have to eventually leave the site. Any interpretation that flies in the face of this proposition should be rejected.
Clearly contemplates that there will be development that is, buildings or works, for or associated with a crushing facility.
But [according to Mr Morris] the permit does not confine crushing operations to this area. Rather it allows the endorsement of plans that are generally in accordance with the 2006 VCAT plan; and then allows amendment of these plans by the Responsible Authority.
Application No. 709220 (Cond No. 1 parts (b), (c), (d), (e), (f), (g), (h), (k), (l) and (o) *pursuant to secondary consent provisions of cond No. 8.
By the notation stated above, the Council is satisfied that the amended plan was generally in accordance with the relevant plans or was approved (as a secondary consent) under Condition 8.
A question of fact to be judged on the facts and circumstances of the case.
and further, the less detail and precision there was in the primary document:
The more flexibility is given by the phrase 'generally in accordance with'.
Contains further descriptions and details of the crushing facility. However none of these changes are inconsistent with the permit.
It is sufficient if the matters raised in Condition 30 are considered in some way, to the satisfaction of the Responsible Authority.
that no reasonable responsible authority could consider that the plan adequately dealt with the emission of dust from the rock crushing plant
reserved for decisions that, looked at objectively, are so devoid of any plausible justification that no reasonable body of persons could have made them.
This does not mean that any non-transforming change to the endorsed development could be approved by the Responsible Authority pursuant to a condition such as Condition 2. Such a change must also be consistent with the permit ... because it would be illogical for a secondary consent to produce an outcome inconsistent with the primary consent (the permit) which created the right to give secondary consent.
Interpreting permits ... requires discipline. The focus must remain on identifying the meaning of the words in the permit not on unincorporated underlying documents.
All drainage from the site shall be contained within the site boundaries.
In the present case, the permit allowed the development of the land with a building and provided that the development, as shown on endorsed plans, must not be altered without the written consent of the responsible authority. This form of permission contemplates the possibility that the development will be altered from that shown on the endorsed plans. It is arguable that the permit might be regarded as only contemplating the possibility of written consent being given if this occurred before the development commenced or, at least, before the development was completed. But common experience tells us that development is sometimes carried out in a manner different than that permitted, yet the differences are such that it is still reasonable to consent to them after the event. Why should a permit expressly allowing the possibility of consent being given for the alteration of the development be interpreted to as to exclude this reasonable possibility? Further, it is also commonplace that once development is carried out the owner may wish to effect minor changes to the development. Why should a permit expressly allowing the possibility of consent being given for the alteration of the development be interpreted so as to deny this possibility in every circumstance simply because the development has been carried out?
Inconsequential having regard to the primary purpose of the planning controls which created the need for the primary permission.
In my opinion, a power to grant a permit subject to conditions authorizes the responsible authority to grant a permit for a use or development which differs from the use or development the subject of the application for a permit, provided that the difference is not so radical as to enable it to be said, viewing the matter broadly and fairly, that to grant a permit on the supposed conditions would not be to grant the permit applied for with modifications, but to grant a different permit. This is plainly a matter of degree, and indeed it is almost one of impression. In my view, the changes made may be considerable without necessarily bringing it about that the permit granted is a different as opposed to a modified permit. Whether more may be countenanced by way of limiting the development or use, as opposed to extending it, before the point is reached at which alteration ceases to be modification and becomes transformation, is a question which I find it unnecessary to decide. On this question fairness and convenience may point towards one conclusion and logic towards another.
The clause is not limited to amending the name of the applicant. It specifically allows an amendment to the application to include a use or development different from the use or development mentioned in the application. It even enables an amendment to the land. In allowing a different use and/or a different development it allows 'quite radical changes' that might well amount to transformations in terms of Addicoat v Fox (No. 2) [1979] VR 357.
No consequence having regard to the purpose of the planning control under which the permit was granted.
The third objective of the SUZ4 zoning is "To encourage land management practice and rehabilitation that minimises adverse impact on the issue and development of nearby land". We make several comments here. First, the requirement here is that any adverse impacts be minimised, rather than the test being that there are no adverse impacts. Second, what constitutes a reasonable degree of "minimisation" depends in part upon the level of sensitivity associated with the other uses occurring on the nearby land.
In our opinion, the decision of the Tribunal in Mentone Mansions Pty Ltd v Kingston City Council (2000) 6 VPR 128 correctly sets out relevant principles in relation to the amendment of endorsed plans using an informal consent mechanism.
The entire development, including the carparking, office, silos, conveyors, all roads including existing and proposed access ways, all stockpiles and all settlement ponds, depicted on one plan.
means that there is an ample authorisation to the permit holder to 'fill in blanks'. The permit holder and the Responsible Authority therefore have done no more than was precisely contemplated by Condition 1. Leaving scope to add matters of detail, the terms of Condition 1(b) gave the permit holder and Responsible Authority ample 'elbow room' for the permit holder to propose and Council to accept and endorse the revised development as depicted in the February plan.
The extent of the development site in the context of the whole lot of which the development site forms part, being the lot with the street address of No. 335 O'Herns Road in Epping (ie Lot 4 P/T:TP PLN:805492A) which includes the existing municipal dog pound and gas extraction area activities.
required that that single plan place the development in its appropriate context.
Here is a permit to build what you have already depicted and fill in the blanks however you feel like.
The recycling plan includes an area in which the mobile crushing unit operates, an adjacent stockpiles were the crushed material.
Concerning any matter which the person may refer to the Tribunal for determination by the Planning Division.
Without recourse to authority I would have said that s.114 of the Planning Act is not attempting to deal with the type of situation now under discussion. The structure of the Act, as well as the verbiage of the section, suggests that the reference in sub-s.(1) to "contravention of the Act" is not addressing a contravention alleged to exist because an extension or amendment proper on its face might be successfully attacked as involving a wrong exercise of discretion in the decision to extend or amend. The difficulty of making s.114(1) apply to such a case was highlighted, I consider, by the necessary recourse, in the submissions of counsel for the Shire, to s.14(1) of the Appeals Act as the source of jurisdiction to create the very contravention or prospective contravention which is the sine qua non of the availability of s.114.
(1997) 18 AATR 285, 298
[1] Gant v Greater Geelong City Council (2003) 15 VPR 230.
Love
Whittlesea SC [2009] VCAT 1343
(1931) 45 CLR 359
(1994) 51 FCR 213