Evidence
5There is substantial agreement between the parties about the facts pertinent to this dispute. The statement of agreed facts (SOAF) was tendered (exhibit A). It states as follows:
Definitions
1 In these Agreed Facts, terms are defined as follows:
a. Barangaroo Land means Lots 1, 3, 5 and 6 of deposited plan 876514 in New South Wales.
b. BDA means the Barangaroo Delivery Authority.
c. BDA Act means the Barangaroo Delivery Authority Act 2009 (NSW).
d. PDA means Barangaroo Stage 1 Project Development Agreement which is the subject of Agreed Facts [20] and [21] below.
e. Relevant Period means the period 7 July 2010 to 30 June 2013 (inclusive).
f. Rated Land means lots 3, parts of lot 5 and 6 of DP 876514, being the land south of the "Stage One Boundary" line of the Barangaroo Land, that line being marked on the document labelled Respondent's Annexure A to the Points of Defence.
2 Unless otherwise defined, defined terms in this Agreed Statement of Facts have the same meaning as in the PDA other than for "Licensed Area" which is defined with respect to each of the relevant licences.
The Barangaroo Land and the BDA
3 The Barangaroo Land forms part of an approximately 22 hectare site known as Barangaroo.
4 On 4 June 2009, title to the Barangaroo Land was vested in the BDA for an estate in fee simple.
5 The BDA is constituted under the BDA Act as a corporation which is, for the purposes of any Act, a NSW Government Agency.
6 As a NSW Government Agency, the BDA has the status, privileges and immunities of the Crown in right of New South Wales.
7 In the exercise of its functions, the BDA is subject to the control and direction of the Minister administering the BDA Act.
8 The Barangaroo Land is Crown land within the meaning of the Crown Lands Act 1989 (NSW) and the Local Government Act 1993 (NSW) (the LG Act).
The Barangaroo Concept Plan
9 On 9 February 2007, the then Minister for Planning approved a concept plan submitted by the Sydney Harbour Foreshore Authority (SHFA), the predecessor in title of the Barangaroo Land, for development of the Barangaroo Land, subject to modification (Barangaroo Concept Plan).
10 The Barangaroo Concept Plan was approved in approval MP06_0162 and, as at November 2013, has subsequently been modified on four occasions.
11 In addition to approving the Barangaroo Concept Plan, the Minister also approved the inclusion of the Barangaroo Land in the State Environmental Planning Policy (Major Development) 2005 as a State Significant Site.
12 The Approved Concept Plan includes the following key aspects for Barangaroo South:
a. a maximum of 490,240 square metres of gross floor area (commercial, retail and residential);
b. public waterfront promenade the length of the site;
c. three commercial towers with maximum floor area of 351,882 square metres; The maximum height for the tallest tower will be 209 metres and the other two towers will be 180 metres in height;
d. 800 residential apartments with a maximum floor area of 105,358 square metres and an estimated 1500 residents;
e. an additional hotel building has been approved with a maximum floor area of 33,000 square metres. This building is currently the subject of negotiation between Lend Lease and the NSW Government; and
f. all buildings to be held by way of 99 year lease from the Barangaroo Delivery Authority.
Development of Barangaroo South
13 The development of the Barangaroo Land commenced with a tender process (Stage 1 Tender) for the development of the southern portion of the Barangaroo Land known as Barangaroo South (Stage 1 Development).
14 In April 2008, SHFA called for expressions of interest (EOI) in the Stage 1 Tender.
15 On 25 September 2008, SHFA informed Lend Lease Development Pty Limited (LLD) that it had been shortlisted for the Stage 1 Tender and issued LLD with a request for detailed proposals (RFDP).
16 In August 2009, the BDA issued LLD with a Stage 1 RFDP- Final Phase Proponent Brief (Final Phase RFDP).
17 On 5 November 2009, LLMP was incorporated as a wholly owned subsidiary of LLD.
18 On 20 December 2009, LLMP was announced as the successful bidder in the Stage 1 Tender.
The PDA for the Barangaroo Stage 1 Development
19 On 5 March 2010, the BDA, LLMP and Lend Lease Corporation Limited entered into the PDA.
20 The PDA has been amended on a number of occasions by the following documents on the following dates:
a. First deed of amendment, 8 June 2010
b. Second deed of amendment, 30 July 2010
c. Third deed of amendment, 23 December 2010
d. Fourth deed of amendment, 14 June 2012
21 The PDA provides for the BDA to grant construction licences to LLMP to permit LLMP to carry out the Stage 1 Works (Construction Zone Licence).
22 A Construction Zone Licence, as provided for by the PDA as executed, granted to LLMP, as Developer, "a non-exclusive licence to access and occupy the Developer Secured Area". On 23 December 2010, the PDA was amended so as to grant to LLMP, as Developer, "a non-exclusive licence to access and use the Developer Secured Area".
Licences
23 Between July 2010 and November 2012, the BDA granted LLMP a series of licences as set out below at paragraphs [24] to [38].
First Access Licence
24 On 7 July 2010, the BDA granted a 'Barangaroo Stage 1 Early Works Licence' to LLMP (First Access Licence).
25 The First Access Licence was in force from 7 July 2010 to 6 July 2011 pursuant to clause 2.2 and, pursuant to clause 2.1, granted to LLMP, as the Developer, "a non-exclusive licence to access and occupy the Licensed Area".
Second Access Licence
26 On 21 July 2011, the BDA granted a 'Barangaroo Stage 1 Basement 1A Works Licence' to LLMP (Second Access Licence).
27 The Second Access Licence was in force from 7 July 2011 to 13 July 2012 pursuant to clause 2.2 and, pursuant to clause 2.1, granted to LLMP, as the Developer, "a non-exclusive right to access and use the Licensed Area".
C4 Construction Zone Licence
28 On 6 July 2012, the BDA granted a Construction Zone Licence to LLMP pursuant to clause 13.1 of the PDA (C4 Construction Zone Licence).
29 The C4 Construction Zone Licence commenced on 7 July 2012 and expires on the Practical Completion of the relevant Stage 1 Works Portion, being the Commercial Building C4 works the subject of the approval granted by the Minister for Planning for Major Project No 10_0025 (C4 Construction Zone Licence Period).
30 The C4 Construction Zone Licence granted to LLMP, as Developer, "a non-exclusive licence to access and use the Developer Secured Area".
Basement Construction Zone Licence
31 On 6 July 2012, the BDA granted a Construction Zone Licence to LLMP pursuant to clause 13.1 of the PDA (Basement Construction Zone Licence).
32 The Basement Construction Zone Licence commenced on 7 July 2012 and expires on the Practical Completion of the relevant Stage 1 Works Portion, being the works the subject of the approval granted by the Minister for Planning for Major Project No 10_0023 (Basement Construction Zone Licence Period).
33 The Basement Construction Zone Licence granted to LLMP, as Developer, "a non-exclusive licence to access and use the Developer Secured Area".
Third Access Licence
34 On 12 July 2012, the BDA granted a 'Barangaroo Stage 1 Sisco/C3 C5 Pilings Licence' to LLMP (Third Access Licence).
35 The Third Access Licence was in force between 13 July 2012 and 14 July 2013 pursuant to clause 2.2 and, pursuant to clause 2.1, granted to LLMP, as the Developer, "a non-exclusive licence to access and use the Licensed Area".
C5 Construction Zone Licence
36 On 9 November 2012, the BDA granted a Construction Zone Licence to LLMP pursuant to clause 13.1 of the PDA (C5 Construction Zone Licence).
37 The C5 Construction Zone Licence commenced on 9 November 2012 and will expire on the Practical Completion of the relevant Stage 1 Works Portion, being the works associated with Commercial Building C5 (C5 Construction Zone Licence Period).
38 The C5 Construction Zone Licence granted to LLMP, as Developer, "a non-exclusive licence to access and use the Developer Secured Area".
Rates and Charges Notices
39 The respondent issued LLMP with the following rates and charges notices on or about 7 December 2012 with respect to the Rated Land:
a. Notice for the period 7 July 2010 to 30 June 2011 in the amount of $3,428,670.95 (First Rates Notice);
b. Notice for the period 1 July 2011 to 30 June 2012 in the amount of $7,057,445.95 (including balance brought forward) (Second Rates Notice);
c. Notice for the period 1 July 2012 to 30 June 2013 in the amount of $10,769,380.95 (including balance brought forward) (Third Rates Notice): and
d. Notice for the amount of $5,384,690.95, being 50% of the total rates levied by the Third Rates Notice.
Liabilities and Responsibilities
40 LLMP obtained and paid for public liability insurance in relation to works on the Rated Land for the Relevant Period.
41 LLMP procured an OH&S plan from the Builder and provided warranties in relation to the effect of compliance with that plan in accordance with the requirements of clause 36 of the PDA in relation to the Rated Land during the Relevant Period.
42 LLMP commenced paying for the provision of the following services to the Rated Land at the following times:
a. Electricity: in or around November 2010;
b. Water: in or around August 2010;
c. Sewerage (comprising a connection to a pre-existing sewer point on the Rated Land): in or around June 2011; and
d. Telecommunications (comprising 3 telephone lines): in or around December 2010.
43 LLMP paid for and undertook activities, commencing in the last quarter of 2010 and from time to time during the Relevant Period, relating to the establishment of the construction site on the Rated Land, including the installation of hoardings and the taking of measures to secure the construction site.
44 LLMP engaged contractors, including but not necessarily limited to AECOM Australia Pty Ltd, to undertake investigation works on the Rated Land during the Relevant Period.
45 In or about June 2010, LLMP engaged contractors, including but not necessarily limited to, Casey & Lowe Pty Ltd, to carry out archaeological works which commenced in or about August 2010, pursuant to the approval for Major Project MP 07_077 as part of the Early Works (as defined in the PDA).
Subleases
46 Confidential Agreed Fact: LLMP has entered into agreements in relation to the future tenancy of part of the commercial buildings including, but not limited to, the following:
a. "Agreement for Sub-lease" with KPMG Australian Services Pty Ltd as trustee for the KPMG Australia Service Trust dated 17 February 2012, pursuant to which LLMP agrees to procure a sub-lease from the Lessor (defined in that Agreement as a person whom the BDA has confirmed is an Acceptable Tenant and who accepts a Call Offer made by the BDA pursuant to cl 27 of the PDA, or, alternatively, LLMP, if a Put Offer has been accepted by the BDA pursuant to cl 28 of the PDA), CONFIDENTIAL.
b. "Office Agreement for Lease" with Westpac Banking Corporation dated 21 June 2012, pursuant to which LLMP agrees to procure a sub-lease from the Lessor (defined in that Agreement as a person whom the BDA has confirmed is an Acceptable Tenant and who accepts a Call Offer made by the BDA pursuant to cl 27 of the PDA, or, alternatively, LLMP, if a Put Offer has been accepted by the BDA pursuant to cl 28 of the PDA), CONFIDENTIAL.
c. Agreement for sub-lease with Lend Lease Management Services Limited dated 7 July 2012, pursuant to which LLMP agrees to procure a sub-lease from the Lessor (defined in that Agreement as a person whom the BDA has confirmed is an Acceptable Tenant and who accepts a Call Offer made by the BDA pursuant to cl 27 of the PDA, or, alternatively, LLMP, if a Put Offer has been accepted by the BDA pursuant to cl 28 of the PDA).
47 LLMP has entered into a memorandum of understanding with CBRE (RP) Pty Ltd on 3 April 2013 in relation to the sale (by way of 99 year leases) of residential apartments within the two residential buildings known as Anadara and Alexander. All 159 of those apartments were sold off the plan on 31 August 2013.
Profit
48 LLMP is currently paying, by instalment, moneys to the BDA which, by the expiry of the PDA will total in excess of several hundred million dollars in accordance with the terms of the PDA.
49 The current budgets of LLMP, which are varied from time to time, are based on a number of assumptions as to future events which may prove to be incorrect and are only accurate as a prediction to the point in time at which they are created, show that LLMP anticipates making a profit and thereby receiving a benefit from the development of the Rated Land.