Keegan v Ballast Point Pty Ltd
[2022] NSWCA 179
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2022-08-31
Before
Meagher JA, Brereton JA, Kirk JA
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] The appellant as Owner and respondent as Builder were parties to a cost plus residential building contract, which was in a standard form prepared by the Master Builders Association of New South Wales. After works had been completed, an issue arose as to whether moneys remained owing by the Owner to the Builder for the cost of works undertaken and a builder's fee. The general conditions of contract (clause 17) provided for the making by the Builder of monthly payment claims, which were to be paid within 10 days of the Builder submitting the relevant claim. The Special Conditions appointed an Architect to administer the contract on the Owner's behalf. Special Condition 3 provided that the Architect was to assess and certify the Builder's payment claims "pursuant to the provisions of the contract". In proceedings commenced by the Builder in the District Court, the Owner contended that no further amount was due and payable because under the contract he was only obliged to pay amounts as assessed and certified by the Architect, which he had done. The primary judge (S J Gibb DCJ) rejected this construction. Her Honour considered that, properly construed, the contract obliged the Owner to pay payment claims independently of whether they had been assessed and certified by the Architect. The primary judge entered judgment for the Builder in the sum of $219,531.65. On appeal, the sole issue was whether Special Condition 3 was to be construed as having the effect that the Owner's obligation to pay in response to a payment claim was only in respect of amounts assessed and certified by the Architect. The Court (Meagher JA, Brereton and Kirk JJA agreeing) held, dismissing the appeal with costs: