© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2024] NSWCA 143
Court of Appeal (NSW)
2024-04-24
Gleeson JA, Mitchelmore JA
Original judgment source is linked above.
Background
The Contract
The events leading to termination of the Contract
The Owners' cross-claim against Oxford and Mr Kazzi
The evidence of Mr Mahedy
Determination of the Owners' cross-claim against Mr Kazzi
Failure to establish breach of the s 37 duty (cross-appeal, ground 2)
Section 37 of the DBP Act
The Owners' case against Mr Kazzi for breach of the duty in s 37
Defect B1: failure to build a retaining wall along Noble Street boundary; and Defect B3: change to basement perimeter load bearing walls
Defect B2: boundary encroachments
Defect B4: Entry foyer below Noble Street level
Defect B5: failure to construct the foyer façade and roof in accordance with the Amended Consent and construction certificate drawings
Defect B8: defective wiring in basement
Defect B9: failure to install fire-rated door jambs on basement and unit fire doors; and Defect B16: failure to comply with fire resistance requirements
Defect B10: concrete strength of ground and first floor slabs below structural engineer's specifications
Defect B11: parts of first floor concrete slab built to external brickwork
Defect B12: pergolas constructed using materials not fit for purpose
Defect B13: water and gas points installed too close to balcony balustrades, enabling children to climb and fall
Defect B14: leaking through double brick parapet wall
Defect B15: failure to design or construct wheelchair access to unit C1
Conclusion as to defects and breach of duty by Mr Kazzi
Rejection of Mr Mahedy's evidence (cross-appeal, grounds 3 and 4)
The additional invoices
The Owners' claim against Oxford and Mr Kazzi for interest on their borrowings
The challenges to the primary judge's determination of interest
Ground 1 of the cross-appeal: date from which interest should run
Grounds 3 to 5 of the appeal: fire safety works
Conclusion
Endnote
Kazzi
KR Properties Global Pty Ltd t/as AK Properties Group
(2023) 110 NSWLR 557; [2023] NSWCA 5 The Owners - Strata Plan No 84674 v Pafburn Pty Ltd [2023] NSWCA 301 The Owners - Strata Plan No 87060 v Loulach Developments Pty Ltd (No 2) [2021] NSWSC 1068 Category: Principal judgment Parties: Pierre Kazzi (Appellant / Cross-Respondent) KR Properties Global Pty Ltd (ACN 602 693 729) t/as AK Properties Group (ABN 62 971 068 965) (First Respondent / First Cross-Appellant) Calm Properties Pty Ltd (formerly AS Coaching Pty Ltd) (ACN 602 073 343) ATF Calm Properties Unit Trust (ABN 19 756 796 114) t/as AK Properties Group (ABN 62 971 068 965) (Second Respondent / Second Cross-Appellant) Representation: Counsel: M Ashhurst SC / T Poisel (Appellant / Cross-Respondent) J Horowitz (Respondents / Cross-Appellants)
Solicitors: Fortis Law (Appellant / Cross-Respondent) Horowitz & Bilinsky (Respondents / Cross-Appellants) File Number(s): 2023/00277906 Publication restriction: Nil Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Equity - Technology and Construction List Citation: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 4) [2023] NSWSC 960 Date of Decision: 15 August 2023 Before: Stevenson J File Number(s): 2020/00007703
HEADNOTE [This headnote is not to be read as part of the judgment] The appellant and cross-respondent, Pierre Kazzi, was the sole director, shareholder and nominated supervisor of Oxford (NSW) Pty Ltd (Oxford), a building company. The respondents and cross-appellants (the Owners) contracted with Oxford to construct a six-unit apartment building on land in Gerringong. The date stipulated in the contract for practical completion of the building works was 4 July 2017. Oxford did not complete the works by that date. On 5 April 2019, the Owners terminated the contract. In January 2020, Oxford commenced proceedings against the Owners to recover outstanding amounts pursuant to invoices it had served under the contract. The Owners brought a cross-claim against Oxford and Mr Kazzi, seeking damages from Oxford for breach of contract in relation to the costs they incurred to complete the building works and rectify defective works, and damages from Mr Kazzi for breach of the duty in s 37 of the Design and Building Practitioners Act 2020 (NSW) (the DBP Act) to avoid economic loss caused by defective works. As part of their claim for damages against both Oxford and Mr Kazzi, the Owners sought the interest they incurred on borrowings as a result of the works not being completed by the date of practical completion, relying on Hungerfords v Walker (1989) 171 CLR 125; [1989] HCA 8 ("Hungerfords"). The primary judge, Stevenson J, delivered four judgments in the proceedings. On 6 April 2023, his Honour handed down the first judgment, rejecting Oxford's claims and upholding the Owners' claims in part: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 [2023] NSWSC 343 ("Oxford (No 1)"). His Honour found that Oxford had wrongly purported to suspend the works under the contract, which the Owners then validly terminated. His Honour concluded that the Owners were entitled to damages from Oxford for the costs to complete the incomplete works and to rectify defective works, and for Hungerfords interest albeit from 20 March 2019 (the date on which the Owners demanded that Oxford resume construction), rather than the date of practical completion. The primary judge dismissed the Owners' claim against Mr Kazzi. His Honour was not satisfied that the Owners had established a breach of duty on the part of Mr Kazzi personally, or proved what component of the expenses they had incurred related to rectifying the defective works, as opposed to completing incomplete works. As to the latter, his Honour rejected the evidence of Patrick Mahedy, who was the architect who designed the building and whom the Owners retained to supervise the completion and rectification works following termination of the contract with Oxford. Following Oxford (No 1), the Owners raised with the primary judge that he had not dealt with their claim for Hungerfords interest against Mr Kazzi. In a further judgment delivered on 21 June 2023, his Honour dismissed this claim on the basis that the Owners had not established how Mr Kazzi had breached his statutory duty and what consequences flowed from the alleged breach: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 2) [2023] NSWSC 680 ("Oxford (No 2)"). Following Oxford (No 2), the Owners raised with the primary judge that Mr Kazzi had in fact admitted, during the hearing, that he had breached his statutory duty in relation to two of the defects on which the Owners relied: the pouring of the ground floor and first floor concrete slabs in a manner that resulted in the building encroaching on adjacent lots (defect B2); and the use of concrete that was below the structural engineer's specifications (defect B10). On 28 July 2023, following a further hearing, his Honour gave a judgment in which he concluded that in Oxford (No 2) he had overlooked Mr Kazzi's admitted breaches of duty. His Honour awarded the Owners Hungerfords interest against Mr Kazzi from the same date (20 March 2019) as he had awarded that interest against Oxford: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 3) [2023] NSWSC 881 ("Oxford (No 3)"). On 15 August 2023, his Honour made final orders, including, relevantly, entering judgment for the Owners against Mr Kazzi in the sum of $277,579.50, plus the costs of the cross-claim: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 4) [2023] NSWSC 960. By his appeal, Mr Kazzi challenged the primary judge's decision in Oxford (No 3). Grounds 1 and 2 of the appeal alleged that the Owners had not previously articulated a claim for Hungerfords interest against Mr Kazzi in respect of defects B2 and B10. Grounds 3 to 5 challenged the primary judge's conclusion that those defects caused the Owners to continue to incur interest on their borrowings until July 2020 in circumstances where other works precluded the issuing of an occupation certificate or a strata plan until late June or July 2020. The Owners filed a cross-appeal which sought judgment against Mr Kazzi in the sum of $918,545.46. The Owners alleged that the primary judge erred in concluding, in Oxford (No 1) and Oxford (No 3), that Hungerfords interest should run only from 20 March 2019, rather than the date of practical completion under the contract (ground 1). The Owners also challenged the primary judge's conclusion, in Oxford (No 1), that they had failed in their claim against Mr Kazzi for damages for breach of his statutory duty under s 37 of the DBP Act in relation to defects B2, B10, and a further 12 defects. Specifically, the Owners took issue with (1) his Honour's finding that the Owners had not established that Mr Kazzi breached his statutory duty in relation to those defects (ground 2); (2) his Honour's finding that the Owners had not proved their loss (ground 3); and relatedly, (3) his rejection of the evidence of Mr Mahedy (ground 4). The Court held (Mitchelmore JA, Gleeson JA and Basten AJA agreeing), dismissing the appeal and allowing the cross-appeal:
As to grounds 3 and 4 of the cross-appeal: (3) Where a party by their conduct has made the precise assessment of damages difficult, the court should assess compensation in a robust manner, relying on the presumption against wrongdoers, the onus of proof, and by resolving doubtful questions against the party: [139]. Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd (No 3) [2012] VSC 99; Houghton v Immer (No 155) Pty Ltd (1997) 44 NSWLR 46; McCartney v Orica Investments Pty Ltd [2011] NSWCA 337 applied. (4) The primary judge erred in taking the view that Mr Mahedy's evidence did not provide a sufficiently reasoned methodology on which to rely: [140], [146]. Mr Mahedy's close involvement in project managing the Building after the Contract was terminated meant he was able to provide detail of what occurred on the site: [132].
As to grounds 3 to 5 of the appeal and ground 1 of the cross-appeal: (6) The primary judge did not find that there was an "implied agreement" or "waiver" to extend the date of practical completion: [168]. (7) Where an injury is the result of multiple conjunctive causal factors, it is sufficient for a plaintiff to prove that the defendant's negligence caused or materially contributed to the injury: [169]. Amaca Pty Ltd v Booth (2011) 246 CLR 36; [2011] HCA 53 applied. (8) Whilst there were concurrent causes of the delay between 20 March 2019 and 30 June 2020, including the outstanding fire safety works, Mr Kazzi's negligence was a material cause of the delay which extended back to the date of practical completion under the contract: [172].
[2024] HCASL 96
(2011) 246 CLR 36
(1992) 176 CLR 408
(1997) 44 NSWLR 46
(1989) 171 CLR 125
(2023) 110 NSWLR 557