HEADNOTE
[This headnote is not to be read as part of the judgment]
The appellant and cross-respondent, Pierre Kazzi, was the sole director, shareholder and nominated supervisor of Oxford (NSW) Pty Ltd (Oxford), a building company. The respondents and cross-appellants (the Owners) contracted with Oxford to construct a six-unit apartment building on land in Gerringong. The date stipulated in the contract for practical completion of the building works was 4 July 2017. Oxford did not complete the works by that date. On 5 April 2019, the Owners terminated the contract.
In January 2020, Oxford commenced proceedings against the Owners to recover outstanding amounts pursuant to invoices it had served under the contract. The Owners brought a cross-claim against Oxford and Mr Kazzi, seeking damages from Oxford for breach of contract in relation to the costs they incurred to complete the building works and rectify defective works, and damages from Mr Kazzi for breach of the duty in s 37 of the Design and Building Practitioners Act 2020 (NSW) (the DBP Act) to avoid economic loss caused by defective works. As part of their claim for damages against both Oxford and Mr Kazzi, the Owners sought the interest they incurred on borrowings as a result of the works not being completed by the date of practical completion, relying on Hungerfords v Walker (1989) 171 CLR 125; [1989] HCA 8 ("Hungerfords").
The primary judge, Stevenson J, delivered four judgments in the proceedings. On 6 April 2023, his Honour handed down the first judgment, rejecting Oxford's claims and upholding the Owners' claims in part: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 [2023] NSWSC 343 ("Oxford (No 1)"). His Honour found that Oxford had wrongly purported to suspend the works under the contract, which the Owners then validly terminated. His Honour concluded that the Owners were entitled to damages from Oxford for the costs to complete the incomplete works and to rectify defective works, and for Hungerfords interest albeit from 20 March 2019 (the date on which the Owners demanded that Oxford resume construction), rather than the date of practical completion.
The primary judge dismissed the Owners' claim against Mr Kazzi. His Honour was not satisfied that the Owners had established a breach of duty on the part of Mr Kazzi personally, or proved what component of the expenses they had incurred related to rectifying the defective works, as opposed to completing incomplete works. As to the latter, his Honour rejected the evidence of Patrick Mahedy, who was the architect who designed the building and whom the Owners retained to supervise the completion and rectification works following termination of the contract with Oxford.
Following Oxford (No 1), the Owners raised with the primary judge that he had not dealt with their claim for Hungerfords interest against Mr Kazzi. In a further judgment delivered on 21 June 2023, his Honour dismissed this claim on the basis that the Owners had not established how Mr Kazzi had breached his statutory duty and what consequences flowed from the alleged breach: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 2) [2023] NSWSC 680 ("Oxford (No 2)").
Following Oxford (No 2), the Owners raised with the primary judge that Mr Kazzi had in fact admitted, during the hearing, that he had breached his statutory duty in relation to two of the defects on which the Owners relied: the pouring of the ground floor and first floor concrete slabs in a manner that resulted in the building encroaching on adjacent lots (defect B2); and the use of concrete that was below the structural engineer's specifications (defect B10).
On 28 July 2023, following a further hearing, his Honour gave a judgment in which he concluded that in Oxford (No 2) he had overlooked Mr Kazzi's admitted breaches of duty. His Honour awarded the Owners Hungerfords interest against Mr Kazzi from the same date (20 March 2019) as he had awarded that interest against Oxford: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 3) [2023] NSWSC 881 ("Oxford (No 3)"). On 15 August 2023, his Honour made final orders, including, relevantly, entering judgment for the Owners against Mr Kazzi in the sum of $277,579.50, plus the costs of the cross-claim: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 4) [2023] NSWSC 960.
By his appeal, Mr Kazzi challenged the primary judge's decision in Oxford (No 3). Grounds 1 and 2 of the appeal alleged that the Owners had not previously articulated a claim for Hungerfords interest against Mr Kazzi in respect of defects B2 and B10. Grounds 3 to 5 challenged the primary judge's conclusion that those defects caused the Owners to continue to incur interest on their borrowings until July 2020 in circumstances where other works precluded the issuing of an occupation certificate or a strata plan until late June or July 2020.
The Owners filed a cross-appeal which sought judgment against Mr Kazzi in the sum of $918,545.46. The Owners alleged that the primary judge erred in concluding, in Oxford (No 1) and Oxford (No 3), that Hungerfords interest should run only from 20 March 2019, rather than the date of practical completion under the contract (ground 1). The Owners also challenged the primary judge's conclusion, in Oxford (No 1), that they had failed in their claim against Mr Kazzi for damages for breach of his statutory duty under s 37 of the DBP Act in relation to defects B2, B10, and a further 12 defects. Specifically, the Owners took issue with (1) his Honour's finding that the Owners had not established that Mr Kazzi breached his statutory duty in relation to those defects (ground 2); (2) his Honour's finding that the Owners had not proved their loss (ground 3); and relatedly, (3) his rejection of the evidence of Mr Mahedy (ground 4).
The Court held (Mitchelmore JA, Gleeson JA and Basten AJA agreeing), dismissing the appeal and allowing the cross-appeal: